Ternera Gold Deposit - Phase 1 Open Pit Scoping Study
Released
Released
Announcement PDF
PHASE 1 SCOPING STUDY CAUTIONARY STATEMENT
The Scoping Study referred to in this ASX release has been undertaken for the purpose of initial evaluation of a potential
development of the El Zorro Gold Project in the Atacama region of Northern Chile. It is a preliminary technical and
economic study of the potential viability of the El Zorro Gold Project. The Scoping Study outcomes, production target
and forecast financial information referred to in this release, are based on low accuracy level technical and economic
assessments that are insufficient to support estimation of Ore Reserves. The Scoping Study has been completed to a
level of accuracy of +/- 35% in line with a scoping level study accuracy. While each of the modifying factors were
considered and applied, there is no certainty of eventual conversion to Ore Reserves, or that the production target
itself will be realised. Further exploration and evaluation work and appropriate studies are required before Tesoro Gold
will be in a position to estimate any Ore Reserves or to provide any assurance of an economic development case.
Given the uncertainties involved, investors should not make any investment decisions based solely on the results of the
Scoping Study.
The Mineral Resources scheduled for extraction in the Scoping Study production plan, show results of approximately
84% which are classified as Measured and/or Indicated and 16% as Inferred during this 8-year operating period. The
Company has concluded that it has reasonable grounds for disclosing a production target which includes a proportion
of Inferred material. However, there is a low level of geological confidence associated with Inferred Mineral Resources
and there is no certainty that further exploration work will result in the determination of Indicated Mineral Resources or
that the production target itself will be realised. Indicated Resources comprise 84% of the production schedule during
the payback period of the Project and an average of 84% over life of the operation. Tesoro Gold confirms that the
financial viability of the El Zorro Gold Project is not dependent on the inclusion of Inferred Resources in the production
schedule.
The Mineral Resources underpinning the production target in the Scoping Study have been prepared by a Competent
Person in accordance with the requirements of the JORC Code (2012) and the Competent Person’s Statement is found
on page 13 of this ASX release. For full details of the Mineral Resources Estimate, please refer to Tesoro Gold’s ASX
Announcement dated 9 March 2023. Tesoro Gold also confirms that it is not aware of any new information or data
that materially affects the information included in that release. All material assumptions and technical parameters
underpinning the estimates in that ASX release continue to apply and have not materially changed.
This announcement may contain certain forward-looking statements and opinions. Forward-looking statements,
including projections, forecasts and estimates, are provided as a general guide only and should not be relied on as
an indication or guarantee of future performance and involve known and unknown risks, uncertainties, assumptions,
contingencies and other important factors, many of which are outside the control of the Company and which are
subject to change without notice and could cause the actual results, performance or achievements of the Company
to be materially different from future results, performance or achievements expressed or implied by such statements.
Past performance is not necessarily a guide to future performance and no representation or warranty is made as to
the likelihood of achievement or reasonableness of any forward-looking statements or other forecasts. Nothing
contained in this announcement, nor any information made available to you is, or and shall be relied upon, as a
promise, representation, warranty or guarantee as to the past, present or the future performance of Tesoro Gold.
Tesoro Gold has concluded that it has a reasonable basis for providing these forward-looking statements and its
forecast financial information contained within this release. This includes a reasonable basis to expect that it will be
able to fund the development of the El Zorro Gold Project upon successful delivery of timely key development
milestones. A detailed explanation for these conclusions is outlined throughout this ASX release and in the Appendix.
While Tesoro considers all of the material assumptions to be based on reasonable grounds, there is no certainty that
they will prove to be correct, or that the range of outcomes indicated by the Scoping Study will be achieved.
To achieve the range of outcomes indicated in the Scoping Study, pre-production funding in excess of US$132M may
be required and there is no certainty that Tesoro Gold will be able to source that amount of funding when required. It
is also possible that such funding may only be available on terms that may be dilutive to, or otherwise affect the value
of Tesoro Gold’s shares. It is also possible that Tesoro Gold could pursue other value realisation strategies such as a sale,
partial sale or joint venture of the El Zorro Gold Project. This could materially reduce Tesoro’s proportionate ownership
of the El Zorro Gold Project.
No Ore Reserve has been declared. This ASX release has been prepared in compliance with the current JORC Code
(2012) and the ASX Listing Rules. All material assumptions, including sufficient progression of all JORC modifying factors,
on which the production target and forecast financial information are based, have been included in this ASX release.
Sign up HERE to our Investor Hub
ASX: TSO OTCQB: TSORF
ASX ANNOUNCEMENT
4 APRIL 2023
TERNERA GOLD DEPOSIT
PHASE 1 OPEN PIT SCOPING STUDY OUTCOMES
TECHNICALLY AND FINANCIALLY ROBUST STARTER PIT
GOLD MINING AND PROCESSING OPERATION
Tesoro Gold Limited (Tesoro or the Company) (ASX:TSO, OTCQB:TSORF) is pleased to present the key
outcomes of the Phase 1 Scoping Study (the Study) completed at the Company’s El Zorro Gold
Project (El Zorro or the Project) in Chile.
The Study has confirmed the technical and financial robustness of an initial, stand-alone open pit
gold mining and processing operation at El Zorro. It outlines preliminary evaluation of an operation
based solely on the shallowest portion of the February 2023 Ternera Deposit Mineral Resource.
Substantial potential upside to this starter development is set to be driven by inclusion of further in-pit
resource ounces, expanded open pit and/or underground mining of deeper resource ounces,
further resource additions from within the Ternera Exploration Target zone, drill-out of near-mine
growth targets, and exploration drilling of high-impact district targets.
Tesoro’s dual track advancement strategy at El Zorro is focused on aggressively growing the existing
resource base in parallel with ongoing progression along Ternera’s development pathway.
PHASE 1 SCOPING STUDY HIGHLIGHTS
Key Parameters (± 35%)
Unit
Study Estimate
Ore throughput
Mt
17.1
Gold grade
g/t
1.25
Production ounces
koz
651
Plant throughput
Mtpa
2.4
Average annual steady state production
koz pa
93
Production life (excluding pre-strip)
years
7.4
Forecast average All‐In‐Sustaining‐Cost (AISC)
US$/oz
1,068
Total pre‐production capital cost (including pre-strip)
US$M
132
Economic Outcomes (± 35%)
Unit
Base
Spot1
Gold price
US$/oz
1,750
1,950
NPV5% (pre-tax, ungeared)
US$M
201
300
%
27.5
37.1
Net cashflow (pre-tax, undiscounted, ungeared)
US$M
312.3
442.5
Payback from first production
years
3.4
2.8
IRR (pre-tax, ungeared)
1. Approximate gold spot price as at 28 March 2023
TESOROGOLD.COM.AU
1
ASX ANNOUNCEMENT 4 APRIL 2023
SUBSTANTIAL POTENTIAL UPSIDE DRIVERS
•
Further 170 koz available within optimised pit shell. Approximately 170 koz Au resides between
the base of the Scoping Study pit design and the optimal pit shell at US$1,750/oz, offering
immediate potential for open pit production expansion to 822 koz Au.
•
Underground development. Incorporation of further Ternera Mineral Resource Estimate (MRE)
ounces into the mine schedule via potential underground mining (part of the next phase of
study).
•
Resource additions within Ternera Exploration Target area. Additional Project upside potential
with further exploration within the initial constrained Ternera Exploration Target area.
•
Key Ternera extensional targets. Drill-out and potential conversion of growth targets at Toro
Blanco and Kitsune (situated within 3km of the Ternera Deposit).
•
High impact El Zorro district targets. Remain to be unlocked, including the prospective geology
defined at the Animas Viejas Target (35km north of Ternera).
NEXT STEPS
•
Phase 2 Ternera Scoping Study targeted for Q4 2023.
•
Commencement of select Pre-Feasibility level workstreams targeted for Q2 2023.
•
Extensional drilling of Ternera and near-deposit prospects coupled with exploration drilling of
El Zorro district targets through 2023.
•
Updated MRE for Ternera (and El Zorro) scheduled for Q4 2023.
•
Continued environmental baseline and project approvals processes through 2023.
Tesoro Managing Director, Zeff Reeves, commented:
“We are delighted to present the outcomes of the initial evaluation of a Phase 1 Open Pit Project at
El Zorro. The Study outlines a simple, robust gold project with conventional mining and metallurgy,
located close to supporting infrastructure in a well-established, supportive mining jurisdiction.
Phase 1 highlights the clear potential for a technically and financially compelling new Chilean mining
project with a short payback period and strong cash flow generation over an initial 8-year operating
period.
Critically, this Study incorporates less than half of the existing Ternera global gold resource. Additional
studies are underway to assess further potential along strike and below the base of the Phase 1 open
pit, encompassing the potential for a larger open pit plus underground development.
Ongoing resource and extensional drilling at Ternera, and more broadly across El Zorro, provides
outstanding potential to substantially grow the Ternera development from these initial Study
parameters. Evidence of this potential is readily apparent in the recent significant exploration
successes delivered at El Zorro.
Tesoro is committed to further advancing and growing the scale of the Ternera development by
continuing to extend the Ternera Deposit and delineating additional gold resources throughout the
emerging El Zorro Gold District.”
TESOROGOLD.COM.AU
2
ASX ANNOUNCEMENT 4 APRIL 2023
INTRODUCTION
Tesoro has assessed the development potential of an initial, gold mining and processing operation
at the Ternera Gold Deposit (the Deposit) within the El Zorro Gold Project in Chile. The Phase 1
Scoping Study assesses the Project on a 100% basis (Tesoro 85%).
The Project is in the Atacama region of northern Chile, 13km inland from the Pacific Ocean and 57km
by road from the port of Caldera. The area is well-supported by existing road, power and water
infrastructure. Chile is a long-established, supportive mining jurisdiction that has the largest copper
production globally, and second largest output of lithium.
The Study was prepared by Tesoro with input from a team of expert independent consultants (refer
Table 1). It provides a preliminary assessment of the potential viability of the Project based on low
level technical and economic accuracy (± 35%).
The Study considers the initial development of a Phase 1 open pit mining operation on the upper
200m of the Deposit to feed a 2.4 Mtpa gold processing plant. Outcomes demonstrate the ability of
the Deposit to support the estimated capital required for the development of the Project at a scale
that would result in an annual average gold production of between 90 and 100 koz per annum.
Figure 1: Project location with proximate operating mines in detail
TESOROGOLD.COM.AU
3
ASX ANNOUNCEMENT 4 APRIL 2023
Figure 2: Regional infrastructure
Table 1: Contributing parties
Study Input
Contributor
Study Compilation
Tesoro
Geology
Tesoro, Cube Consulting
Resource Estimation
Lynn Widenbar and Associates
Geotechnical
Peter O’Bryan and Associates
Mining Studies
Tesoro
Mining Costs
Tesoro, Mining Contractors
Metallurgical Test Work
GRES, ALS Perth
Process Engineering & Design
GRES
Operating Costs
Tesoro, GRES
Infrastructure
Tesoro
Capital Costs
Tesoro, GRES
Environmental, Social & Permitting
Tesoro
Financial Modelling
Tesoro
TESOROGOLD.COM.AU
4
ASX ANNOUNCEMENT 4 APRIL 2023
KEY STUDY OUTCOMES AND ASSUMPTIONS
The Study has confirmed that an initial starter open pit at the El Zorro Gold Project presents a
technically and commercially viable development opportunity. A summary of the initial physical and
financial evaluation of the Project case at a 2.4 Mtpa throughput rate is shown in Table 2, with
additional details provided in the Scoping Study Executive Summary presented below.
Table 2: Scoping Study evaluation period results and key assumptions (100% ownership basis)
Physicals and Costs (± 35%)
Ore tonnage
Mt
17.1
Gold grade
g/t
1.25
Contained ounces
Koz
689
Plant throughput
Mtpa
2.4
Evaluation period (excluding pre-strip)
years
7.4
waste:ore
8.3:1
Process gold recovery (life of mine average)
%
94.5
Process production – total evaluation period
koz
651
Process production – average annual steady state
koz pa
93
Upfront capital – plant and process infrastructure
US$M
108.0
Upfront capital – open pit mining
US$M
13.5
Upfront capital – pre strip
US$M
10.4
Operating costs – mining
US$/oz Au
585
Operating costs – processing
US$/oz Au
368
Operating costs – general and administration
US$/oz Au
102
Strip ratio
Financials and Key Assumptions (± 35%)
Gold price
Discount rate (real)
US$/oz
%
Base
Spot1
1,750
1,950
5
5
AISC (life of mine average)
US$/oz
1,068
1,068
NPV5% (pre-tax)
US$M
201
300
%
27.5
37.1
Net cash flow (undiscounted, pre-tax)
US$M
312
442.5
Payback period (pre-tax)
years
3.4
2.8
IRR (pre-tax)
1. Approximate gold spot price as at 28 March 2023
Mineral royalties on gold mining activities are not imposed at a provincial or federal level in Chile. In
this study, no mineral royalties are assumed assessable with respect to the Project.
Chile has a well-established mining tax regime that is considered attractive to foreign investors due
to its stability and transparency. Once in production, mining exploration and pre-production capital
expenditure can be offset against a flat 27% corporate tax rate. Additional tax concessions are
available to mining companies, which are subject to government approval. A detailed tax schedule,
TESOROGOLD.COM.AU
5
ASX ANNOUNCEMENT 4 APRIL 2023
including assessment of all available concessions, will be developed during future Pre-Feasibility
Study work.
PRODUCTION PROJECTIONS
The Study utilises cut-off grades, dilution and mining recoveries appropriate for the style of mining
and mineralisation type. Mining rates provide 2.4 Mt pa mill feed to the gold processing plant. A
mining dilution factor of 10% @ 0g/t Au was applied to all mill feed tonnes, and a mining loss of 5%
used for all optimisation runs and production schedules.
Table 3: Annual gold output (process throughput rate of 2.4 Mtpa)
Year
Total
Y1
Y2
Y3
Y4
Y5
Y6
Y7
Y8
Y9
Au koz
651
0.0
31.3
94.1
92.5
96.3
88.5
95.8
91.7
61.2
(koz)
Figure 3: Annual recovered gold and head grade
SENSITIVITY ANALYSIS
Project sensitivity analysis demonstrates, like most mining developments, the greatest economic
sensitivity to changes in commodity price/revenue and operating cost parameters.
TESOROGOLD.COM.AU
6
ASX ANNOUNCEMENT 4 APRIL 2023
Figure 4: El Zorro Gold Project NPV5% (pre-tax) sensitivity analysis (US$M)
PROJECT CONFIGURATION
Mineral Resources
Ternera MRE was updated in March 2023 to 42.6Mt @ 1.07g/t Au for 1.46Moz Au (unconstrained at a
0.3g/t Au cut-off) (refer ASX announcement 9 March 2023, Ternera Mineral Resource Update and
Initial Exploration Target). Of this, 54% of resource tonnes and 56% of contained gold ounces reside
in the Indicated Mineral Resource category, with the remainder classified as Inferred. There have
been no changes to the Ternera MRE since the date of publication.
Table 4: Ternera Gold Deposit updated Mineral Resource Estimate reported at various cut-offs (unconstrained)
Indicated
Inferred
Total
Au g/t cut off
Mt
Au g/t
koz
Mt
Au g/t
koz
Mt
Au g/t
koz
2.00
2.6
3.75
317
2.0
3.71
241
4.7
3.73
558
1.00
7.2
2.25
523
5.6
2.24
400
12.8
2.24
923
0.50
16.3
1.39
727
12.8
1.37
561
29.1
1.38
1,288
0.30
23.2
1.09
815
19.4
1.03
645
42.6
1.07
1,459
Phase 1 Pit Optimisation
Optimisation studies on the Ternera MRE indicate the potential for a high-value Phase 1 open pit
project extending just 200m below surface to produce 651 koz of gold. The optimised pit represents
less than half of the total Ternera MRE (at 0.30 Au g/t cut off) with 84% of the resulting production
target residing in the Indicated category and the remaining 16% in the Inferred category.
Table 5: Phase 1 Ternera Gold Deposit optimised pit production target (US$1,750/oz at 0.46 g/t Au)
Indicated
Inferred
Total
Pit
Mt
Au g/t
koz
%
Mt
Au g/t
koz
%
Mt
Au g/t
koz
Phase 1
14.8
1.22
582
84
2.3
1.45
107
16
17.1
1.25
689
Optimisation studies also demonstrated the economic potential of a larger 822 koz open pit,
extending approximately 290m below surface, which could be mined at a higher strip ratio (not
adopted for this Study).
TESOROGOLD.COM.AU
7
ASX ANNOUNCEMENT 4 APRIL 2023
Mining
The Study assumed open pit mining with all mining activities to be performed by a mining contractor
under the direction and management of Tesoro. Mining costs have been estimated based on the
use of a 230-tonne diesel hydraulic excavator and 120-tonne truck fleet. Mining costs are a
combination of budget estimates from a leading South American open pit mining contractor and
Tesoro database costs.
The modelling is based on preliminary pit, run of mine and waste dump designs. Open pit mining
schedules were developed based on a single pit, targeting a mill feed rate of 2.4 Mt p.a. at the
highest grade possible.
Over an initial 8-year operating life, the Phase 1 pit provides approximately 17.1 Mt of mill feed at an
average grade of 1.25g/t Au and a strip ratio of 8.3:1.
Figure 5: El Zorro Gold Project Ternera conceptual site layout
Processing
The process plant design was undertaken by GR Engineering based on the outcomes from
metallurgical test work programs performed at ALS Metallurgy in Perth. The program was undertaken
using seawater to assess the gravity recoverable gold and cyanide leaching characteristics over a
range of grind sizes. Results confirmed a gravity gold recovery response of 45% and total gold
recoveries of 94.5% utilising a standard CIP process at a relatively coarse grind size (P80 = 150µm).
TESOROGOLD.COM.AU
8
ASX ANNOUNCEMENT 4 APRIL 2023
Figure 6: El Zorro Gold Project process plan flowsheet
Figure 7: El Zorro Gold Project mill throughput by resource category
Infrastructure and services
The area proximate to El Zorro is well-supported by existing road, power and water infrastructure. As
a greenfield development, design and construction of all required site infrastructure and services will
form part of the Project.
Power supply options were considered with the support of a Chilean power engineering company.
The recommended supply route is via a connection to the Totoralillo substation located
TESOROGOLD.COM.AU
9
ASX ANNOUNCEMENT 4 APRIL 2023
approximately 21.6km in a straight line to the south-west of the Project area. The estimated capital
cost for connection is approximately US$10M with the cost of grid electricity approximately
US$0.105/kWh, including transmission tolls and other levies.
Water required for the Project is planned to be extracted from the sea using an approved seawater
extraction facility and pumped 20km to site via a purpose-built and operated pipeline and pumping
system. On-site, the seawater would be used for ore processing, dust suppression and as a feed to
a Reverse Osmosis plant to meet Project potable water requirements.
Provision has been made for the construction and operation of a 175-man accommodation camp
and the installation of mobile phone and data communications systems at the Project site.
Tailings and waste management
All tailings generated by processing of gold bearing ores are to be filtered and dry stacked in a
purpose-built Tailings Storage Facility (TSF). A tailing filtration rate of approximately 0.9 t/m2/h has
been assumed for the preliminary design unit for dry stacked tailings given the coarse target
comminution size for the process.
An area has been identified as a potential TSF location and incorporated into the conceptual site
layout design. A valley embankment TSF has been adopted with the embankment constructed from
appropriate mine waste. Future studies will incorporate detailed engineering design and test work
and will consider the merits of a stand-alone TSF against incorporating filtered tailings into proposed
waste dumps (co-disposal).
Proposed waste dump areas have been identified in locations to the east and southeast of the open
pit, distal from currently identified mineralisation trends and of sufficient size to contain Phase 1 open
pit and future mining waste material.
LICENCE TO OPERATE
Approvals
The Environmental Impact Assessment (EIA) and approvals procedure for mining projects in Chile are
well-established and understood. The Company has commenced baseline studies and works on the
EIA and Project approvals.
Figure 8: El Zorro Gold Project planned development schedule based upon maximum time to permit.
TESOROGOLD.COM.AU
10
ASX ANNOUNCEMENT 4 APRIL 2023
Based on the maximum time for approval expectations, construction of the Project is anticipated to
commence prior to the end of 2027 with first gold production in 2028.
There have been no impediments to the approval, development and operation of the Project
identified to date and the Company is endeavoring to gain all approvals and permits within the
estimated timeframe.
Social sustainability
The Company expects development and construction of the Project will involve more than
500 people and employ in excess of 175 personnel, including contractors, when at full production.
Tesoro plans to engage a high proportion of the workforce from within the surrounding communities
and towns.
CAPITAL COST ESTIMATE
A total pre-production capital cost estimate of US$132M has been estimated in consultation with
independent specialists, a leading South American mining contractor and GR Engineering Services.
Pre-strip mining costs of US$10M for the period preceding commercial production has been included
in the total cost. The estimate has primarily been derived using a typical Scoping Study desktop
approach to an accuracy of ± 35%.
Table 5: El Zorro Gold Project pre-production capital cost estimate (2.4 Mtpa plant and infrastructure)
Area
Capital cost estimate (US$M)
Processing plant
62.5
Project infrastructure
39.0
Other costs
6.6
Mining capital
13.5
Pre–strip mining activities
10.4
Total pre-production capital cost
132.0
Sustaining capital (residual initial LOM)
8.6
OPERATING COST ESTIMATE
Operating cost estimates have been constructed in consultation with independent specialists, a
mining contractor and GR Engineering Services and derived across the three key areas of the Project,
namely mining, processing and administration. The operating cost estimate has primarily been
derived using a desktop approach to an accuracy of ± 35%, typical of a Scoping Study.
A mining contractor operating strategy is to be adopted for the Project and assumes all material in
the pit will require drill and blast. A mining cost quotation was obtained with processing and general
and administrative costs estimated from first principles with inputs from process consumable
quotations. All costs have been benchmarked against existing Chilean operations.
TESOROGOLD.COM.AU
11
ASX ANNOUNCEMENT 4 APRIL 2023
Table 6: El Zorro Gold Project operating cost estimate (rounded)
Area
Operating cost estimate
(US$/t Au processed)
Operating cost estimate
(US$/oz Au produced)
Mining
22.2
585
Processing
14.0
368
General and administration
3.9
102
FUNDING
The Project is considered to be relatively low risk and technically simple, with strong economics that
provide a robust platform for Tesoro to access traditional financing through debt and equity markets.
There is, however, no certainty that Tesoro will be able to source funding as and when required. To
achieve the various outcomes indicated in the Study, pre‐production funding in excess of US$132M
may be required.
Typical project development financing would involve a combination of debt and equity and Tesoro
has formed the view that there is a reasonable basis to believe that requisite future funding for
development of the El Zorro Gold Project will be available when required.
There are grounds on which this reasonable basis is provided including:
•
Project is in a Tier One jurisdiction, with simple non‐refractory metallurgy allowing for an industry
standard CIP processing plant and has a rapid payback of only 3.4 years from commercial
process production (pre-tax basis);
•
Very strong pre‐tax cashflows of US$312M and rapid payback would support a significant level
of conventional debt financing for the Project development;
•
There is significant potential to grow the Project’s Mineral Resource base which is the basis of this
Scoping Study;
•
Release of the Study allows the Company to discuss outcomes with potential financiers; and
•
Tesoro Board and management have extensive experience in mine development, financing
and production in the resources industry in Chile.
Authorised by the Board of Tesoro Gold Ltd.
For more information:
Company:
Zeff Reeves, Managing Director
Tesoro Gold Limited
info@tesorogold.com.au
TESOROGOLD.COM.AU
12
ASX ANNOUNCEMENT 4 APRIL 2023
ABOUT TESORO
Tesoro Gold Limited was established with a strategy of acquiring, exploring, and developing mining projects in
the Coastal Cordillera region of Chile. The Coastal Cordillera region is host to multiple world class copper and
gold mines, has well established infrastructure, service providers and an experienced mining workforce. Large
areas of the Coastal Cordillera remain unexplored due to the unconsolidated nature of mining concession
ownership, but Tesoro, via its in-country network and experience has been able secure rights to a district scale
gold project in-line with the Company’s strategy. Tesoro’s 95% owned Chilean subsidiary owns 85% of the El Zorro
Gold Project.
COMPETENT PERSONS STATEMENTS
The information in this report that relates to Exploration Results and Exploration Target is based on information
compiled by Mr Zeffron Reeves (B App Sc (Hons) Applied Geology) MBA, MAIG). Mr Reeves is a member of the
Australian Institute of Geoscientists and a Director and shareholder of the Company. Mr Reeves has sufficient
experience that is relevant to the style of mineralisation and type of deposit under consideration and to the
activity which he is undertaking to qualify as a Competent Person as defined in the 2012 Edition of the
Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves. Mr Reeves consents
to the inclusion in this report of the matters based on this information in the form and context in which it appears.
The information in this report that relates to Mineral Resources is based on information compiled by Mr Lynn
Widenbar, a Competent Person who is a Member of The Australasian Institute of Mining and Metallurgy. Mr
Widenbar is acting as an independent consultant to Tesoro Gold Limited. Mr Widenbar has sufficient experience
that is relevant to the style of mineralisation and type of deposit under consideration, and to the activity being
undertaken to qualify as a Competent Person as defined in the 2012 Edition of the ‘Australasian Code for
Reporting of Exploration Results, Mineral Resources and Ore Reserves’. The Company confirms that Mr Widenbar
consents to the inclusion in the report of the matters based on his information in the form and context in which
it appears.
The information in this report that relates to the Production Target, assumptions on Modifying Factors and
evaluation of other relevant factors are based on and fairly represents information and supporting
documentation that has been compiled for this announcement and have been compiled under the supervision
of Mr Linton Putland BEng (Mining), MSc (Mineral Economics) & Member AusIMM. Mr Putland is a Director of the
Company. Mr Putland has reviewed and approved the technical content of this announcement. Mr Putland is
a Competent Person as defined in the 2012 Edition of the Australasian Code for Reporting of Exploration Results,
Mineral Resources and Ore Reserves (JORC Code 2012). Mr Putland consents to the inclusion in this
announcement of the matters based on his information in the form and context in which it appears.
FUTURE PERFORMANCE
This announcement may contain certain forward-looking statements and opinion. Forward-looking statements,
including projections, forecasts and estimates, are provided as a general guide only and should not be relied
on as an indication or guarantee of future performance and involve known and unknown risks, uncertainties,
assumptions, contingencies and other important factors, many of which are outside the control of the Company
and which are subject to change without notice and could cause the actual results, performance or
achievements of the Company to be materia