Quarterly Activities Report
Released
Released
Announcement PDF
31 Cliff Street, Fremantle WA 6011 | +61 8 6383 7883 | info@tesorogold.com.au | tesorogold.com.au
ASX ANNOUNCEMENT
23 APRIL 2026
ASX: TSO OTCQB: TSORF FSE: 5D7
QUARTERLY ACTIVITIES REPORT
FOR THE PERIOD ENDED 31 MARCH 2026
Tesoro Gold Limited (ASX: TSO, OTCQB: TSORF, FSE: 5D7) (Tesoro or the Company) is pleased to report
on its activities for the quarter ended 31 March 2026 (the Quarter), during which the Company
delivered strong exploration results, completed key technical studies, and advanced the El Zorro
Gold Project towards a development decision.
HIGHLIGHTS FROM THE QUARTER
Exploration and Drilling
Three concurrent, fully-funded, diamond drilling programmes continued throughout the Quarter:
• Extensional Drilling Programme (approx. 6,000m total): Outstanding grades of over 27g/t Au
from new depth extensions at the Ternera Deposit. Substantial extensions confirmed in two
holes, with mineralisation intersected 400m down plunge, or approximately 200 vertical
metres below the 2025 Scoping Study open pit shell.
• Notable results included:
• 8.84m @ 3.54g/t Au from 576.00m (ZDDH0411) including; 1.00m @ 27.70g/t Au from
576.00m.
• 7.09m @ 1.31g/t Au from 670.45m including; 0.54m @ 9.89g/t Au from 677.00m.
• A further high-grade intercept from extensional drilling to the north of the MRE returned:
4.26m @ 3.4 g/t Au from 217.45m (ZDDH0398B), including 0.68m @ 19.45g/t Au.
• New Discovery Drilling Programme (approx. 12,000m total): Geophysical surveying and soil
sampling campaigns were undertaken to define further high-priority drill targets across the
broader El Zorro concession holding. Outcomes included:
• Completion of a high-resolution helicopter magnetic and radiometric survey across
the entire El Zorro concession area, which increased the extent of the prospective
north-south gold corridor to over 40km long.
• Multiple new intrusive bodies and structural features identified.
• Infill Drilling Programme (approx. 20,000m total): Now 80% complete, with assay results
returned from 38 infill holes during the Quarter, with 30 holes still outstanding at Quarter end.
El Zorro Gold Project Advancement
• Technical trade-off studies completed, confirming optimal development configuration.
• Decision taken to advance directly to DFS, targeting completion by end of CY2026.
• DFS metallurgical and pit geotechnical drilling commenced; PFS-level process design and
dry stack tailings storage facility design completed; site infrastructure geotechnical
investigations commenced.
Tesoro Gold 2
ASX ANNOUNCEMENT
23 APRIL 2026
• Environmental baseline studies well advanced and scheduled for completion in September
2026, in preparation for project permitting
Site Tour
• An Institutional Investor and Analyst Site Tour in conjunction with Rio2 Limited (TSX: RIO) and
Flagship Minerals Ltd. (ASX: FLG) was hosted in January 2026.
• Investors and analysts met operating teams on the ground and assessed each asset within
the context of regional infrastructure and permitting frameworks.
Corporate
• Strong balance sheet with A$22.58 million cash (includes long term deposits with >3 month
term) and zero debt as at 31 March 2026.
• Unmarketable parcel Share Sale Facility (SSF) s launched on 19 January 2026 and completed
post Quarter end on 9 April 2026.
Tesoro Managing Director, Zeff Reeves, commented:
“Exploration success during the March Quarter was highlighted by outstanding depth extensions at
Ternera, with grades exceeding 27g/t Au returned and mineralisation intersected approximately 400
metres down plunge of the current open pit shell. This confirms the substantial growth potential we
see beyond the current open pit resource.
“We also have completed 80% of the infill drilling component of our programme, including drilling
required to support several key technical workstreams. Following completion of the infill programme,
the three rigs will transition to our new discovery programme, which includes 12,000 meters of
diamond drilling, targeting multiple high-priority prospects across our extensive over 40 kilometre
prospective gold corridor.
“Project development activities are also advancing rapidly, with the completion of targeted trade-
off studies defining a clear, optimised development pathway. This is centred on a simple, single open
pit mining operation and a 3 Mtpa processing plant, capable of delivering more than 110 koz per
annum of gold. Given the quality and level of accuracy achieved in the completed work, the
decision to advance directly to Definitive Feasibility Study (DFS) was an easy one. This is expected to
shorten the overall development timeline, while maintaining technical rigour, positioning Ternera for
a target Final Investment Decision (FID) by the end of CY2026.
“With drilling advancing at multiple, new discovery targets in the coming months, the Company is
well-positioned to deliver a strong pipeline of great results through the remainder of Q2 CY2026.”
Production target: The production target referred to in this announcement is based on a combination of
Indicated and Inferred Mineral Resources. There is a low level of geological confidence associated with Inferred
Mineral Resources and there is no certainty that further exploration work will result in the determination of
Indicated Mineral Resources or that the production target itself will be realised. The Scoping Study is based on
lower-level technical and economic assessments and is insufficient to support estimation of Ore Reserves or to
provide assurance of economic development.
Tesoro Gold 3
ASX ANNOUNCEMENT
23 APRIL 2026
Figure 1: El Zorro Gold Project showing priority targets over a greater than 40km corridor.
Tesoro Gold 4
ASX ANNOUNCEMENT
23 APRIL 2026
EL ZORRO GOLD PROJECT, CHILE
Exploration and Drilling: 2025-2026 Diamond Drilling Programme
Tesoro has three major, fully-funded diamond drilling programmes underway concurrently across the
El Zorro Gold Project. These programmes are designed to grow the Ternera Deposit, provide the
necessary data for advanced technical studies, and deliver new district-scale discoveries.
Together, these three programmes are planned for a total of 38,000m of drilling:
• Infill Drilling Programme: 20,900m completed to date in support of advanced technical
workstreams.
• Extensional Drilling Programme: Approximately 6,000m to define and grow shallow extensions
to the north and south and test depth extensions to the existing Ternera Deposit.
• New Discovery Drilling Programme: District-scale drilling of approximately 12,000m focused
on priority undrilled targets and follow-up on previous results.
Infill Drilling Programme
The infill drilling programme is designed to upgrade Mineral Resource classification within areas of
the proposed Ternera open pit. This work supports initial Ore Reserve estimation and technical study
workstreams. Drilling targeted areas of existing mineralisation within the current Mineral Resource
Estimate (MRE) to improve confidence in grade continuity and geometry.
The infill programme is approximately 80% complete and is scheduled to finish at the end of April
2026.
• Notable results returned during the Quarter included:
• 2.94m @ 17.74g/t Au from 286.120m (ZDDH0424) and
• 21.00m @ 1.44g/t Au from 385.00m including:
• 5.54m @ 3.24g/t Au from 386.16m
• 26.00m @ 2.27g/t Au from 278.00m (ZDDH0432) including;
• 4.59m @ 9.10g/t Au from 287.60m
• 11.15m @ 0.94g/t Au from 109.50m (ZDDH0429) including:
• 4.70m @ 1.66g/t Au from 113.60m and:
• 2.77m @ 9.35g/t Au from 162.00m
• 11.00m @ 1.38g/t Au from 30.00m (ZDDH0431) including:
• 5.18m @ 2.44g/t Au from 30.00m and:
• 19.00m @ 0.91g/t Au from 287.00m including:
• 9.00m @ 1.44g/t Au from 288.00m
• 5.50m @ 1.95g/t Au from 50.00m (ZDDH0407A)
• 7.00m @ 2.05g/t Au from 51.40m (ZDDH0410)
• 17.50m @ 1.01g/t Au from 190.00m (ZDDH0412)
Tesoro Gold 5
ASX ANNOUNCEMENT
23 APRIL 2026
• 0.47m @ 24.90g/t Au from 130.93m (ZDDH0413)
• 4.20m @ 5.17g/t Au from 56.88m (ZDDH0422)
• 5.87m @ 7.86g/t Au from 510.88m
Extensional Drilling Programme
During the Quarter, several holes were drilled to test the depth extent of the Deposit. An initial two
holes (ZDDH00409 and ZDDH00411) were both collared between 300m and 400m southeast of the
existing MRE (see Figure 2) and targeting the down plunge, deep southern extensions of the Deposit
(see Figure 3).
Both holes returned wide zones of anomalous gold results and several high-grade results at the
projected position of the down plunge extension, indicating that the Deposit continues, and remains
open at depth.
Results included:
• 8.84m @ 3.54g/t Au from 576.00m (ZDDH0411) including; 1.00m @ 27.70g/t Au from
576.00m.
• 7.09m @ 1.31g/t Au from 670.45m including; 0.54m @ 9.89g/t Au from 677.00m.
Results have also been received for an additional extensional hole to the north of the Deposit
(ZDDH00398B, Figure 2), targeting down dip extensions of shallow high-grade mineralisation. The hole
returned 4.26m @ 3.40g/t Au from 217.45m, which included a peak assay of 0.68m @ 19.45g/t Au from
217.45m.
Tesoro Gold 6
ASX ANNOUNCEMENT
23 APRIL 2026
Figure 2: El Zorro Gold Project – Ternera Gold Deposit. Drill locations and results received for this announcement.
Section shown at Figure 2 located at A-A’. Datum PSAD56 19S.
Tesoro Gold 7
ASX ANNOUNCEMENT
23 APRIL 2026
Figure 3: El Zorro Gold Project – Deep Drilling section. Showing holes ZDDH0409 and ZDDH0411 with mineralised
intercepts relative to 2025 MRE and Scoping Study open pit shell. Looking west and holes projected onto section.
Previous drilling shown as grey lines. Datum PSAD56 19S.
New Discovery Drilling Programme
With the completion of the infill component of drilling in late April 2026, rigs will be redeployed to
Tesoro’s 12,000m New Discovery Drilling Programme. Several key targeting activities concluded
during the Quarter, to define further high-priority drill targets across the broader El Zorro concession
holding.
Geophysical Survey Analysis
During the Quarter, Tesoro’s geophysical consultants, Resource Potentials Pty Ltd, carried out final
data processing and imaging of the previously completed high-resolution, helicopter-borne
magnetic and gamma-ray radiometric geophysical survey flown over the entirety of the El Zorro
area. A suite of magnetic and radiometric images was produced, for ongoing interpretation and
gold targeting, in conjunction with geological and geochemical datasets.
Preliminary interpretation of the survey data identified several structural trends that may be
associated with gold mineralisation along the El Zorro Corridor, as well as multiple intrusive
occurrences that remain unexplored (see Figure 4).
Further processing, modelling and interpretation of the survey data is ongoing to assist target
generation across the broader project area.
Tesoro Gold 8
ASX ANNOUNCEMENT
23 APRIL 2026
Soil Sampling
Three orientation programmes of systematic gridded soil sampling were undertaken at the La Brea,
Drone Hill and Pena Blanca Targets to assess this technique for defining new gold targets.
These areas were selected due to the already confirmed location of surface gold mineralisation.
A total of 331 samples were collected on a nominal 50m x 50m grid across areas previously identified
from first-pass rock chip and channel sampling as being prospective for gold mineralisation.
Samples were analysed for low-level gold and 47 multi-element indicators to assist with drill targeting
and identify the most gold-fertile zones for follow-up exploration work, including drilling.
Results have successfully defined geochemical anomalies at all three targets aligning well with
mapped mineralised fault zones and favourable host lithologies.
Additional soil sampling programmes are planned at multiple targets to identify new and expand
existing drill targets.
Tesoro Gold 9
ASX ANNOUNCEMENT
23 APRIL 2026
Figure 4: El Zorro Gold Project High-resolution Geophysical Survey Preliminary Interpretation. Magnetic
susceptibility map (TMIRTP-1VDAGC). The 200m spaced flight line area is outlined in red, 100m spaced flight line
area outlined in blue. The underlying image is 500m spaced regional data. Datum PSAD56 19S.
Tesoro Gold 10
ASX ANNOUNCEMENT
23 APRIL 2026
EL ZORRO GOLD PROJECT ADVANCEMENT
Direct Advancement to DFS
A structured programme of trade-off studies was completed by specialist consultants with the
objective of defining the optimal configuration for a single open pit mine and 3Mtpa processing
plant. This work focused on the principal technical aspects of El Zorro, and included:
• Final process flowsheet selection and process design optimisation;
• Site layout (see Figure 5), including confirmation of preferred power and water infrastructure
corridors;
• Evaluation and selection of tailing disposal method, including preferred dry stack options;
• Seismic risk assessment and associated structural design parameters; and
• Integration of major infrastructure and the mine interfaces.
Outcomes from this work enabled the definition of the preferred project development pathway, with
sufficient engineering confidence for the Tesoro Board to take the decision on 25 February 2026 to
proceed directly to DFS.
Figure 5: El Zorro Gold Project Proposed Site Layout.
Tesoro Gold 11
ASX ANNOUNCEMENT
23 APRIL 2026
DFS Workstreams
Key ongoing DFS workstreams include:
• Additional metallurgical drilling and sampling to confirm the physical characteristics of the
ore from the Ternera pit and complete ore variability test work;
• Geotechnical drilling to finalise pit wall design parameters and slope stability assumptions;
• Detailed mining studies, with a South American mining contractor engaged to provide DFS-
level mine design, production schedules and cost estimates;
• Engineering design, scheduling and costing of power and water supply infrastructure;
• Civil engineering design for all site infrastructure;
• Vendor quotations for the accommodation village, explosives storage facilities and onsite
assay laboratory;
• Key process equipment selection and vendor engagement;
• Design work for a dry stack tailings storage facility; and
• Identification and engagement with suppliers for Long Lead Items.
The level of definition across these workstreams is consistent with DFS standards, including capital cost
estimation, operating cost modelling, equipment specification and construction scheduling.
Environmental and Permitting Progress
Permitting activities are advancing concurrently with technical workstreams. As announced on
22 April 2025, Tesoro commenced preparation for an Environmental Impact Study (EIS) to secure
Environmental Qualification (RCA) and the associated Sectorial Permits (PAS) required for
construction and operation of a gold mine at El Zorro.
Baseline field studies commenced in August 2025. These programmes are now well-advanced and
are scheduled for completion in August 2026.
Completion of the baseline data collection will support preparation and submission of the EIA
documentation to the Chilean Environmental Impact Assessment System.
The EIA review process is expected to continue into 2027, in line with current permitting timelines in
Chile.
Undertaking environmental baseline work in parallel with DFS engineering ensures that project design
parameters are aligned with permitting requirements and supports an integrated and coherent
development schedule.
Development Pathway and Funding
The decision to advance directly to DFS, shortens the overall study timeline while maintaining
technical discipline (see Figure 6). Major Project value drivers have been materially de-risked as part
of the trade-off analysis.
Tesoro Gold 12
ASX ANNOUNCEMENT
23 APRIL 2026
The Company remains on track for:
• Completion of the DFS by the end of CY2026;
• FID following DFS completion; and
• Continued advancement of permitting through the EIA process in 2027.
Figure 6: El Zorro Gold Project Estimated Development and Construction Schedule to Target First Gold.
SITE TOUR
Institutional Investor and Analyst Site Tour
During January 2026, Tesoro, together with Rio2 Ltd and Flagship Minerals Ltd, hosted an institutional
investor and analyst site tour to Chile.
Participants visited the El Zorro, Fenix (Rio2) and Pantanillo (Flagship) projects, met operating teams
on the ground and assessed each asset in the context of regional infrastructure, permitting
frameworks and prevailing macroeconomic conditions. Attendees also had the opportunity to
engage with key government officials, Australian trade representatives and Chilean mining industry
bodies.
Tesoro Gold 13
ASX ANNOUNCEMENT
23 APRIL 2026
Figure 7: El Zorro Gold Project Institutional Investors and Analyst Site Tour Attendees
Figure 8: El Zorro Gold Project Institutional Investors and Analyst Site Tour
Tesoro Gold 14
ASX ANNOUNCEMENT
23 APRIL 2026
CORPORATE
Unmarketable Parcel SSF
On 19 January 2026, Tesoro announced that it has established a SSF for holders of shares in the
Company with a market value of less than A$500 (Unmarketable Parcel). Post Quarter end, Tesoro
advised that it had completed its Unmarketable Parcel SSF, on the terms and conditions announced
to the ASX on 19 January 2026.
The SSF enabled holders of Unmarketable Parcels to sell their shares without incurring brokerage or
handling costs that might otherwise make the sale uneconomic or impractical. A total of 88,779 fully
paid ordinary shares were sold on behalf of 512 shareholders at a price of A$0.9414 per share.
Completion of the SSF reduces the Company’s ongoing administrative and operating costs.
Annual General Meeting (AGM) Date
The AGM is scheduled for 10.00am (WST) on Friday 29 May 2026 at 31-33 Cliff Street, Fremantle, WA
6160.
Expenditure and Payments to Related Parties
The Company deployed approximately A$6.67 million on exploration and development activities
during the Quarter, which primarily comprised feasibility study work, diamond drilling programmes
and exploration activities.
For the Quarter ending 31 March 2026 (sections 6.1 and 6.2), approximately A$231,000 in payments
were made to related parties and/or their associates as remuneration (inc. superannuation) for the
Managing Director, Non-Executive Director fees and Consulting fees (refer Appendix 5B for March
2026).
Cash balance
Tesoro’s cash balance including deposits greater than 3 months was A$22.575 million as at 31 March
2026 and the Company had zero debt (excluding typical trade creditors).
Authorised by the Board of Tesoro Gold Ltd.
For more information:
Company:
Zeff Reeves, Managing Director
Tesoro Gold Limited
info@tesorogold.com.au
Investor Relations and Media Enquiries:
Grace Lauder
Fivemark
grace.lauder@fivemark.com.au
Follow Us
• Website
• LinkedIn
• X
Tesoro Gold 15
ASX ANNOUNCEMENT
23 APRIL 2026
About Tesoro
Tesoro Gold Limited has discovered and defined
the first Intrusive Related Gold System in Chile. The
1.82M oz Ternera discovery is in the Coastal
Cordillera region of Chile. The Coastal Cordillera
region is host to multiple world-class copper and
gold mines, has well established infrastructure,
service providers and an experienced mining
workforce. Large areas of the Coastal Cordillera
remain unexplored due to the unconsolidated
nature of mining concession ownership, but Tesoro,
via its in-country network and experience has been
able secure rights to the district-scale El Zorro gold
project in-line with the Company’s strategy.
Tesoro’s 95% owned Chilean subsidiary owns 95.4%
of the El Zorro Gold Project (see ASX
announcement released 12 August 2025).
Future Performance
This announcement may contain certain forward-looking
statements and opinions. Forward-looking statements,
including projections, forecasts and estimates, are
provided as a general guide only and should not be relied
on as an indication or guarantee of future performance
and involve known and unknown risks, uncertainties,
assumptions, contingencies and other important factors,
many of which are outside the control of the Company
and which are subject to change without notice and
could cause the actual results, performance or
achievements of the Company to be materially different
from the future results, performance or achievements
expressed or implied by such statements. Past
performance is not necessarily a guide to future
performance, and no representation or warranty is made
as to the likelihood of achievement or reasonableness of
any forward-looking statements or other forecast.
Nothing contained in this announcement, nor any
information made available to you is, or and shall be
relied upon as, a promise, representation, warranty or
guarantee as to the past, present or the future
performance of Tesoro Gold.
Competent Persons Statement
The information in this report that relates to Mineral
Resources is based on information compiled by Mr Lynn
Widenbar (B.Sc.(Hons) Geology, M.Sc. FAusIMM, MAIG),
a Competent Person who is a Fellow of The Australasian
Institute of Mining and Metallurgy. Mr Widenbar is acting
as an independent consultant to Tesoro Gold Limited. Mr
Widenbar has sufficient experience that is relevant to the
style of mineralisation and type of deposit under
consideration, and to the activity being undertaken to
qualify as a Competent Person as defined in the 2012
Edition of the ‘Australasian Code for Reporting of
Exploration Results, Mineral Resources and Ore Reserves’.
The Company confirms that it is not aware of any new
information or data that materially affects the
information contained the form and context in which the
Competent Person’s findings are presented have not
been materially modified from in the original
announcement on 4 August 2025, and all material
assumptions and technical parameters underpinning the
estimates in that announcement continue to apply and
have not materially changed.
The information in this report that relates to the
Production Target, assumptions on Modifying Factors and
evaluation of other relevant factors are based on and
fairly represents information and supporting
documentation that has been compiled for this
announcement and have been compiled under the
supervision of Mr Linton Putland BEng (Mining), MSc
(Mineral Economics) & Member AusIMM. Mr Putland is a
Director of the Company. Mr Putland is a Competent
Person as defined in the 2012 Edition of the Australasian
Code for Reporting of Exploration Results, Mineral
Resources and Ore Reserves (JORC Code 2012). The
Company confirms that all material assumptions
underpinning the production target and forecast
financial information derived from the Scoping Study
released on 11 September 2025 continue to apply and
have not materially changed.
The information in this report that relates to Exploration
Results is based on information compiled by Mr Zeffron
Reeves (B App Sc (Hons) Applied Geology) MBA, MAIG).
Mr Reeves is a member of the Australian Institute of
Geoscientists and a Director and shareholder of the
Company. Mr Reeves has sufficient experience that is
relevant to the style of mineralisation and type of deposit
under consideration and to the activity which he is
undertaking to qualify as a Competent Person as defined
in the 2012 Edition of the Australasian Code for Reporting
of Exploration Results, Mineral Resources and Ore
Reserves. Mr Reeves consents to the inclusion in this report
of the matters based on this information in the form and
context in which it appears.
Tesoro Gold 16
ASX ANNOUNCEMENT
23 APRIL 2026
Ternera Mineral Estimates for selected cut-off grades. Highlighted open pit Mineral Resource has been
constrained by an optimised pit shell using a gold price of US$3000/oz and process recovery of 94.5%. The
estimates in this table are rounded to reflect their precision; rounding errors are apparent.
Tenera Updated MRE Indicated Inferred Total
Au g/t cut-off Mt Au g/t Koz Mt Au g/t Koz Mt Au g/t Koz
Optimised Open Pit at 0.30 31.8 1.10 1,123 19.5 1.11 692 51.2 1.1 1,816
2.00 3.5 3.55 394 2.5 3.54 280 5.9 3.54 673
1.00 10.5 2.08 705 7.9 2.04 520 18.5 2.06 1,225
0.70 17.5 1.58 891 13 1.57 657 30.5 1.58 1,547
0.30 31.8 1.10 1,128 26.1 1.03 863 58.1 1.07 1,992
0.20 33.8 1.05 1,144 28.7 0.96 885 62.5 1.01 2,028
Refer ASX announcement dated 4 August 2025
APPENDIX 1: CONCESSION SCHEDULE AS AT 31 MARCH 2026
EL ZORRO GOLD PROJECT EXPLORATION CONCESSIONS (95.4%* Tesoro Mining Chile SpA)
N° Concession name Date of Expiration
Size (ha) Concession
type
1 ZORRO 1B 10/Aug/2026 200 Exploration
2 ZORRO 2B 10/Aug/2026 200 Exploration
3 ZORRO 3B 10/Aug/2026 200 Exploration
4 ZORRO 4B 10/Aug/2026 100 Exploration
5 ZORRO 5B 10/Aug/2026 200 Exploration
6 ZORRO 6B 10/Aug/2026 200 Exploration
7 GOLD STORE 72A 21/Sep/2026 300 Exploration
8 GOLD STORE 71A 21/Sep/2026 300 Exploration
9 GOLD STORE 70A 21/Sep/2026 300 Exploration
10 GOLD STORE 69A 21/Sep/2026 300 Exploration
11 GOLD STORE 68A 21/Sep/2026 300 Exploration
12 GOLD STORE 67A 21/Sep/2026 300 Exploration
13 GOLD STORE 66A 27/Sep/2026 300 Exploration
14 BLOODY GOOD SHOT 13B 27/Sep/2026 200 Exploration
15 BLOODY GOOD SHOT 12B 27/Sep/2026 200 Exploration
16 BLOODY GOOD SHOT 11B 27/Sep/2026 200 Exploration
17 BLOODY GOOD SHOT 10B 27/Sep/2026 300 Exploration
18 BLOODY GOOD SHOT 9B 28/Sep/2026 300 Exploration
19 BLOODY GOOD SHOT 8B 5/Oct/2026 200 Exploration
20 BLOODY GOOD SHOT 7B 28/Sep/2026 100 Exploration
21 BLOODY GOOD SHOT 6B 5/Oct/2026 200 Exploration
22 BLOODY GOOD SHOT 5B 29/Sep/2026 200 Exploration
23 BLOODY GOOD SHOT 4B 29/Sep/2026 300 Exploration
24 BLOODY GOOD SHOT 3B 3/Oct/2026 300 Exploration
Tesoro Gold 17
ASX ANNOUNCEMENT
23 APRIL 2026
25 BLOODY GOOD SHOT 2B 3/Oct/2026 300 Exploration
26 BLOODY GOOD SHOT 1B 3/Oct/2026 300 Exploration
27 SIERRA PATACONES 42A 24/Oct/2026 300 Exploration
28 SIERRA PATACONES 41A 24/Oct/2026 300 Exploration
29 SIERRA PATACONES 40A 25/Oct/2026 300 Exploration
30 SIERRA PATACONES 39A 25/Oct/2026 300 Exploration
31 SIERRA PATACONES 38A 25/Oct/2026 300 Exploration
32 SIERRA PATACONES 35A 25/Oct/2026 300 Exploration
33 SIERRA PATACONES 34A 25/Oct/2026 300 Exploration
34 SIERRA PATACONES 33A 25/Oct/2026 300 Exploration
35 SIERRA PATACONES 32A 25/Oct/2026 300 Exploration
36 SIERRA PATACONES 31A 25/Oct/2026 300 Exploration
37 SIERRA PATACONES 29A 25/Oct/2026 300 Exploration
38 SIERRA PATACONES 28A 25/Oct/2026 300 Exploration
39 SIERRA PATACONES 27A 25/Oct/2026 300 Exploration
40 SIERRA PATACONES 26A 25/Oct/2026 300 Exploration
41 SIERRA PATACONES 25A 25/Oct/2026 300 Exploration
42 SIERRA PATACONES 24A 25/Oct/2026 300 Exploration
43 SIERRA PATACONES 23A 25/Oct/2026 300 Exploration
44 SIERRA PATACONES 21A 26/Oct/2026 300 Exploration
45 SIERRA PATACONES 20A 24/Oct/2026 300 Exploration
46 SIERRA PATACONES 19A 20/Oct/2026 300 Exploration
47 SIERRA PATACONES 18A 24/Oct/2026 300 Exploration
48 SIERRA PATACONES 17A 24/Oct/2026 300 Exploration
49 SIERRA PATACONES 16A 24/Oct/2026 300 Exploration
50 SIERRA PATACONES 14A 24/Oct/2026 300 Exploration
51 SIERRA PATACONES 13A 24/Oct/2026 300 Exploration
52 VACAS FLACAS 28A 26/Oct/2026 300 Exploration
53 VACAS FLACAS 27A 26/Oct/2026 300 Exploration
54 SIERRA PATACONES 2A 28/Oct/2026 300 Exploration
55 SIERRA PATACONES 3A 28/Oct/2026 300 Exploration
56 SIERRA PATACONES 4A 28/Oct/2026 300 Exploration
57 SIERRA PATACONES 5A 28/Oct/2026 300 Exploration
58 SIERRA PATACONES 6A 4/Nov/2026 300 Exploration
59 SIERRA PATACONES 7A 4/Nov/2026 300 Exploration
60 SIERRA PATACONES 9A 4/Nov/2026 300 Exploration
61 SIERRA PATACONES 10A 4/Nov/2026 300 Exploration
62 SIERRA PATACONES 11A 4/Nov/2026 300 Exploration
63 SIERRA PATACONES 12A 24/Nov/2026 300 Exploration
64 SIERRA PATACONES 45A 24/Nov/2026 300 Exploration
65 SIERRA PATACONES 46A 24/Nov/2026 300 Exploration
66 SIERRA PATACONES 47A 24/Nov/2026 300 Exploration
67 SIERRA PATACONES 48A 24/Nov/2026 300 Exploration
Tesoro Gold 18
ASX ANNOUNCEMENT
23 APRIL 2026
68 SIERRA PATACONES 51A 24/Nov/2026 300 Exploration
69 SIERRA PATACONES 52A 24/Nov/2026 300 Exploration
70 SIERRA PATACONES 55A 24/Nov/2026 300 Exploration
71 SIERRA PATACONES 56A 24/Nov/2026 300 Exploration
72 SIERRA PATACONES 60A 28/Oct/2026 300 Exploration
73 GOLD STORE 13A 22/Sep/2026 300 Exploration
74 GOLD STORE 12A 21/Sep/2026 300 Exploration
75 GOLD STORE 9A 22/Sep/2026 300 Exploration
76 GOLD STORE 7A 21/Sep/2026 300 Exploration
77 GOLD STORE 5A 21/Sep/2026 300 Exploration
78 GOLD STORE 4A 21/Sep/2026 300 Exploration
79 GOLD STORE 3A 21/Sep/2026 300 Exploration
80 GOLD STORE 2A 21/Sep/2026 300 Exploration
81 GOLD STORE 1A 21/Sep/2026 300 Exploration
82 GOLD STORE 21A 21/Sep/2026 300 Exploration
83 GOLD STORE 19A 21/Sep/2026 300 Exploration
84 GOLD STORE 18A 21/Sep/2026 300 Exploration
85 GOLD STORE 17A 21/Sep/2026 300 Exploration
86 GOLD STORE 16A 21/Sep/2026 300 Exploration
87 GOLD STORE 8A 22/Sep/2026 300 Exploration
88 GOLD STORE 65A 18/Nov/2026 300 Exploration
89 GOLD STORE 64A 18/Nov/2026 300 Exploration
90 GOLD STORE 63A 18/Nov/2026 300 Exploration
91 GOLD STORE 62A 18/Nov/2026 300 Exploration
92 GOLD STORE 61A 18/Nov/2026 300 Exploration
93 GOLD STORE 60A 18/Nov/2026 300 Exploration
94 GOLD STORE 59A 21/Nov/2026 300 Exploration
95 GOLD STORE 58A 21/Nov/2026 300 Exploration
96 GOLD STORE 57A 21/Nov/2026 300 Exploration
97 GOLD STORE 56A 21/Nov/2026 200 Exploration
98 GOLD STORE 55A 21/Nov/2026 300 Exploration
99 GOLD STORE 54A 21/Nov/2026 300 Exploration
100 GOLD STORE 53A 21/Nov/2026 300 Exploration
101 GOLD STORE 52A 16/Nov/2026 300 Exploration
102 GOLD STORE 51A 14/Nov/2026 300 Exploration
103 GOLD STORE 50A 14/Nov/2026 300 Exploration
104 GOLD STORE 49A 14/Nov/2026 300 Exploration
105 GOLD STORE 48A 18/Nov/2026 300 Exploration
106 GOLD STORE 47A 4/Nov/2026 300 Exploration
107 GOLD STORE 46A 4/Nov/2026 300 Exploration
108 GOLD STORE 45A 4/Nov/2026 300 Exploration
109 GOLD STORE 44A 4/Nov/2026 300 Exploration
110 GOLD STORE 43A 4/Nov/2026 300 Exploration
Tesoro Gold 19
ASX ANNOUNCEMENT
23 APRIL 2026
111 GOLD STORE 42A 4/Nov/2026 300 Exploration
112 GOLD STORE 41A 4/Nov/2026 300 Exploration
113 GOLD STORE 40A 4/Nov/2026 300 Explorat
Share your feedback
Discover