Quarterly Activities Report
Released
Released
Announcement PDF
Sign up HERE to our Investor Hub
ASX ANNOUNCEMENT
28 APRIL 2023
ASX:TSO OTCQB:TSORF
QUARTERLY ACTIVITIES AND CASHFLOW REPORT
FOR THE PERIOD ENDED 31 MARCH 2023
Tesoro Gold Limited (ASX: TSO, OTCQB: TSORF) (Tesoro or the Company) is pleased to report
on its activities for the quarter ended 31 March 2023 (the Quarter).
HIGHLIGHTS
● El Zorro Gold Project Phase 1 Scoping Study completed, confirming a technically and
financially robust initial stand-alone open pit mining and processing operation
(announced 4 April 2023).1
● Ternera Mineral Resource Estimate (MRE) increased by 17%, to 1.28 Moz at 1.18g/t Au
with a substantial upgrade to MRE confidence with 63% in Indicated (previously 46%).1
● Ternera unconstrained MRE increased to 1.46 Moz at 1.07g/t Au.1
● Initial Ternera Exploration Target (ET) defined indicating Ternera could potentially
contain between 1.6 Moz and 3.0 Moz Au.1
● Assay results from detailed channel sampling at the Toro Blanco and Kitsune targets,
highlights a potential northern extension of Ternera Gold Deposit.
● Drilling recommenced at El Zorro in January 2023, focusing on expanding the previously
discovered shallow gold mineralisation in the southern extension of Ternera.
● 11 diamond drill holes were completed in the quarter for 2,397m with assays remaining
outstanding for all holes.
● Initial assay results from the ongoing El Zorro drill program are expected to become
available Q2 CY2023.
● Updated Ternera MRE and Phase 2 Ternera Scoping Study targeted for Q4 2023.
● Cash balance of A$5.4 million and zero debt at 31 March 2023.
Cautionary Statement:
The ET has been prepared and reported in accordance with the 2012 edition of the JORC
Code. The potential quantity and grade are conceptual in nature and there has been
insufficient exploration to estimate a Mineral Resource. It is uncertain if further exploration
will result in the estimation of a JORC-compliant Mineral Resource.
1. Refer to Tesoro ASX releases dated 4 April 2023 and 9 March 2023. Tesoro is not aware of any new information or data that materially affects
the information included in these ASX releases, and the Company confirms that, to the best of its knowledge, all material assumptions and
technical parameters underpinning the estimates in these releases continue to apply and have not materially changed.
info@tesorogold.com.au
Level 48, 152-158 St Georges Terrace, Perth WA 6005
61 8 6311 9160
ASX ANNOUNCEMENT 28 APRIL 2023
Tesoro Gold Managing Director, Zeff Reeves commented:
“We are delighted to report on the significant activities and achievements made by Tesoro
during the March 2023 Quarter. The Company had a strong start to 2023, with a substantial
revision of the Ternera MRE and an initial ET delivered in March. The updated MRE has led
to a 17% increase in prospective gold resources to 1.28 Moz and an increase in resource
confidence with 63% now classified as Indicated. The ET range of 48.5 Mt at 0.91g/t Au to
101.0 Mt at 1.45g/t Au further highlights the exciting potential of the Ternera Gold Deposit,
which we believe could potentially contain between 1.6 Moz and 3.0 Moz of high-grade
gold.
“In addition, we concluded our work on a Phase 1 Scoping Study evidencing the standalone open pit gold mining and processing potential, whilst spotlighting the substantial
Project upside. We continue our dual-track strategy to advance the El Zorro Project through
the coming Quarter, including further revisions to the MRE for Ternera and additional drilling
activities in and around highly prospective El Zorro targets.”
EL ZORRO GOLD PROJECT, CHILE
Drilling Activity and Significant Assay Results at Ternera Gold Deposit
On 17 January 2023, the Company announced assay results from detailed channel
sampling undertaken at the Toro Blanco and Kitsune targets situated to the north of the
Ternera Gold Deposit (Ternera or the Deposit). Assay results defined a large 3.2km by 1.5km
anomalous gold zone in prospective host rocks, which highlights a potential northern
extension of Ternera.
The results were received from 798 channel samples taken as part of a detailed mapping
and sampling program at the Toro Blanco and Kitsune targets (see ASX announcement
dated 17 January 2023). Samples were taken as continuous rock chips, with prospective
rock types outcropping at surface as fresh or weakly-oxidised outcrops. Samples provided
high-level geological information about the nature and control of gold mineralisation
throughout the sampled areas.
Significant assay results include:
●
87.00m @ 0.49g/t Au including:
•
12.00m @ 1.23g/t Au; and
•
6.00m @ 4.17g/t Au.
●
30.00m @ 0.25g/t Au;
●
33.00m @ 0.36g/t Au including:
•
●
6.00m @ 1.23g/t Au.
3.00m @ 17.00g/t Au;
TESOROGOLD.COM.AU
2
ASX ANNOUNCEMENT 28 APRIL 2023
●
1.00m @ 1.94g/t Au; and
●
3.00m @ 1.38g/t Au.
At the same time, drilling commenced at Ternera to expand the Ternera Gold Deposit with
a focus on the near-surface southern extension discovered in the previous Quarter (see ASX
announcement dated 8 November 2022). The southern extension is a newly discovered
shallow zone of gold mineralisation which was intercepted in hole ZDDH0309.
The ongoing drill program is designed to delineate additional gold resources and continue
to extend the Deposit. Future results from this program will aid the Company in
understanding the geometry of this mineralised zone, which remains open to the south.
As at the end of the Quarter,11 diamond drill holes had been completed for 2,397m with
assays remaining outstanding for all holes, with results from the program expected to
become available Q2 CY2023.
Figure 1: Ternera Gold Deposit Drill Hole location map details for holes completed during the Q1 2023
TESOROGOLD.COM.AU
3
ASX ANNOUNCEMENT 28 APRIL 2023
Table 1: Drill Hole location details for holes completed during the Q1 2023
Mineral Resource Update and Ternera Exploration Target Defined
During the Quarter, Tesoro reported a significant MRE update and initial ET for the
Company’s El Zorro Gold Project in Chile.
The constrained Ternera MRE increased to 33.7 Mt at 1.18g/t Au for 1.28 Moz with 802 Koz
(63%) of the resource classified as Indicated (refer Table 1). The updated MRE has been
constrained to a US$1,800/oz optimised pit shell, with the underground resource reported at
a 1.50 g/t Au cut-off. The underground resource is reported at a cut-off where gold
mineralisation is consistently well-developed below the optimised pit shell.
Table 2: Constrained Ternera MRE.
Au g/t
Area
Open Pit
Resource
Underground
Resource
Total
Resources
cut off
0.30
1.50
Indicated
Inferred
Total
Mt
22.
5
Au g/t
Koz
Mt
Au g/t
Koz
Mt
Au g/t
Koz
1,17
5
1.10
795
10.0
1.18
379
32.5
1.13
0.1
2.64
7
1.2
2.64
100
1.3
2.64
107
22.
6
1.11
802
11.2
1.34
479
33.7
1.18
1,28
2
On an unconstrained basis, the Ternera MRE grew to 42.6 Mt at 1.07g/t Au for 1.46 Moz (refer
Table 2). The Ternera MRE update was undertaken utilising data from 310 diamond drill holes
for approximately 105km of drilling, completed between June 2022 and December 2022.
A detailed geological reinterpretation and 3D modelling program of Ternera demonstrated
a substantial improvement in gold grade and continuity throughout the Deposit. The
increased and upgraded MRE has been achieved in a capital efficient manner with a low
discovery cost of less than A$21/oz (US$14/oz), well below the global average greenfield
discovery cost of US$45/oz.
TESOROGOLD.COM.AU
4
ASX ANNOUNCEMENT 28 APRIL 2023
Table 3: Unconstrained Ternera MRE reported at various cut-offs to the 200mRL.
Indicated
Inferred
Total
Au g/t cut-off
2.00
Mt
2.6
Au g/t
3.75
Koz
317
Mt
2.0
Au g/t
3.71
Koz
241
Mt
4.7
Au g/t
3.73
Koz
558
1.00
7.2
2.25
523
5.6
2.24
400
12.8
2.24
923
0.50
16.3
1.39
727
12.8
1.37
561
29.1
1.38
1,288
0.30
23.2
1.09
815
19.4
1.03
645
42.6
1.07
1,459
The revised MRE was independently conducted by Mr Lynn Widenbar, a highly credentialed
and experienced resource consultant. The estimate was produced through 3D modelling
of the host lithology and mineralised fault systems and interpreted to control gold deposition
within Ternera. The 3D geological framework was utilised to produce a block model grade
estimation using Ordinary Kriging (OK).
The Ternera MRE was classified as Indicated or Inferred based on current drill spacing, and
drilling has been verified using the Company’s QAQC program which is undertaken to
normal industry standards.
Additionally, an initial ET has been estimated for Ternera of between 48.50Mt and 101.00 Mt
at between 0.91g/t Au and 1.45g/t Au. The ET is restricted to the area constrained by existing
drilling at Ternera (refer Figure 1) and indicates the drilled footprint could contain between
1.6Moz to 3.0 Moz of gold (refer Table 3).
Table 3: Ternera Exploration Target.
Tonnage (Mt)
Lower
48.5
Upper
101.0
Au Grade (g/t)
Lower
0.91
Upper
1.45
Contained Au (Moz)
Lower
1.6
Upper
3.0
For further details on the ET, see ASX Announcement dated 9 March 2023.
Completion of Phase 1 Scoping Study
On 4 April 2023, the Company presented the outcomes of a Phase 1 Scoping Study (the
Study), relating to the potential development of an initial, gold mining and processing
operation at the Deposit within the El Zorro Gold Project in Chile.
The Study was assessed on a 100% basis (Tesoro 85%) and confirmed that an initial starter
open pit at the El Zorro Gold Project presented a technically and commercially viable
development opportunity. It was prepared with input from a team of expert independent
consultants and provides a preliminary assessment of the potential viability of the Project
based on low-level technical and economic accuracy (± 35%).
The completed Study considers the initial development of a Phase 1 open pit mining
operation on the upper 200m of the Deposit to feed a 2.4 Mtpa gold processing plant. The
TESOROGOLD.COM.AU
5
ASX ANNOUNCEMENT 28 APRIL 2023
key outcomes also demonstrate the ability of the Deposit to support the estimated capital
required for the development of the Project at a scale that would result in an annual
average gold production of between 90 and 100 Koz per annum.
A summary of the initial physical and financial evaluation of the Project case at a 2.4 Mtpa
throughput rate is shown in Table 4, with additional details provided in the Scoping Study
Executive Summary presented below.
Table 4: Scoping Study evaluation period results and key assumptions (100% ownership basis)
Physicals and costs (± 35%)
Ore tonnage
Mt
17.1
Gold grade
g/t
1.25
Contained ounces
Koz
689
Plant throughput
Mtpa
2.4
Evaluation period (excluding pre-strip)
years
7.4
waste:ore
8.3:1
Process gold recovery (life of mine average)
%
94.5
Process production – total evaluation period
Koz
651
Process production – average annual steady state
Koz pa
93
Upfront capital – plant and process infrastructure
US$M
108.0
Upfront capital – open pit mining
US$M
13.5
Upfront capital – pre-strip
US$M
10.4
Operating costs – mining
US$/oz Au
585
Operating costs – processing
US$/oz Au
368
Operating costs – general and administration
US$/oz Au
102
Strip ratio
Financials and key assumptions (± 35%)
Gold price
Discount rate (real)
US$/oz
%
Base
Spot
1,750
1,950
5
5
AISC (life of mine average)
US$/oz
1,068
1,068
NPV5% (pre-tax)
US$M
201
300
%
27.5
37.1
Net cash flow (undiscounted, pre-tax)
US$M
312
442.5
Payback period (pre-tax)
years
3.4
2.8
IRR (pre-tax)
Post March 2023 Quarter, and as part of the future workstreams highlighted in the Scoping
Study, Tesoro plans to progress the following activities:
●
Phase 2 Ternera Scoping Study targeted for Q4 2023.
TESOROGOLD.COM.AU
6
ASX ANNOUNCEMENT 28 APRIL 2023
●
Commencement of select Pre-Feasibility level workstreams targeted for Q2 2023.
●
Extensional drilling of Ternera and near-deposit prospects, coupled with exploration
drilling of El Zorro district targets through 2023.
●
Updated MRE for Ternera (and El Zorro) scheduled for Q4 2023.
●
Continued environmental baseline and project approvals processes through 2023.
For the full details on the Phase 1 Scoping Study, refer to the ASX Announcement dated
4 April 2023.
CORPORATE
Completion of Share Buyback Following Termination of At-The-Market Financing Facility
In the previous Quarter, the Company advised that it had utilised and subsequently
terminated the At-the-Market Subscription Agreement (ATM) with Acuity Capital, raising
A$750,000 inclusive of costs. No fees or costs were associated with the termination and no
further subscriptions under the ATM will take place.
The Company successfully held a General Meeting of Shareholders on 22 February 2023 at
which all resolutions, including those pertaining to the buyback were approved by
Shareholders.
In accordance with the terms of the ATM, the Company completed the buyback for nil
cash consideration and cancelled the 42,000,000 fully paid ordinary TSO shares issued to
Acuity Capital as security for the ATM.
Expenditure and Payments to Related Parties
During the Quarter, the Company spent approximately A$1.5 million on exploration
activities, which consisted primarily of diamond drilling programs and surface mapping and
sampling programs.
As outlined in the Appendix 5B for the Quarter ending 31 March 2023 (sections 6.1 and 6.2),
approximately A$185,732 in payments were made to related parties and/or their associates
as remuneration (incl. superannuation) for the Managing Director, Non-Executive Director
fees and Consulting fees.
Cash
Tesoro’s cash balance at 31 March 2023 was A$5.4 million and the Company had zero debt
(excluding typical trade creditors).
TESOROGOLD.COM.AU
7
ASX ANNOUNCEMENT 28 APRIL 2023
Authorised by the Board of Tesoro Gold Ltd.
For more information:
Company:
Zeff Reeves, Managing Director
Tesoro Gold Limited
info@tesorogold.com.au
TESOROGOLD.COM.AU
8
ASX ANNOUNCEMENT 28 APRIL 2023
Figure 2: Ternera
MRE and ET boundaries showing significant scope for further MRE expansion.
TESOROGOLD.COM.AU
9
ASX ANNOUNCEMENT 28 APRIL 2023
Figure 3: Ternera Gold Deposit Block Model Section 7036175N (looking north) showing MRE block model and
USD1,800/oz optimised open pit shell. Red = indicated classification, green= inferred classification. Note
classified resources under the optimised pit shell. Grid is 100m x 100m.
Figure 4: Ternera Gold Deposit Block Model Section 7036175N (looking north) showing MRE block model and
US$1,800/oz optimised open pit shell. Block model coloured to gold grade. Grid is 100m x 100m.
TESOROGOLD.COM.AU
10
ASX ANNOUNCEMENT 28 APRIL 2023
Figure 5: Flitch plan (looking down) of the 450mRL showing the Ternera Gold Deposit block model and
US$1,800/oz optimised open pit shell outline.
TESOROGOLD.COM.AU
11
ASX ANNOUNCEMENT 28 APRIL 2023
Figure 6: Ternera Gold Deposit isometric view looking north-east showing high-grade resources (>1.50g/t Au)
below the US$1,800 optimised pit shell.
TESOROGOLD.COM.AU
12
ASX ANNOUNCEMENT 28 APRIL 2023
Drilled metres
120,000
Resource (kOz Au)
Ternera constrained MRE
3,500
3,000
100,000
3,000
2,500
80,000
2,000
60,000
1,096
40,000
20,000
661
586
0
75
July 2021 MRE
1,600
645
479
1,500
1,000
593
503
May 2022 MRE
Drilled metres
−
1,460
1,281
815
802
March 2023 MRE
March 2023
Ternera Gold
unconstrained MRE Deposit Exploration
Target
Indicated Resource
500
0
Inferred Resource
Figure 7: Ternera MRE growth updates and initial ET highlighting improved classification and consistent resource
growth with efficient drilling.
TESOROGOLD.COM.AU
13
ASX ANNOUNCEMENT 28 APRIL 2023
About Tesoro
Tesoro Gold Limited was established with a strategy
of acquiring, exploring, and developing mining
projects in the Coastal Cordillera region of Chile.
The Coastal Cordillera region is host to multiple
world class copper and gold mines, has well
established infrastructure, service providers and an
experienced mining workforce. Large areas of the
Coastal Cordillera remain unexplored due to the
unconsolidated nature of mining concession
ownership, but Tesoro, via its in-country network
and experience has been able secure rights to a
district scale gold project in-line with the
Company’s strategy. Tesoro’s 95% owned Chilean
subsidiary owns 85% of the El Zorro Gold Project.
Competent Persons Statements
The information in this report that relates to
Exploration Results and Exploration Target is based
on information compiled by Mr Zeffron Reeves
(B App Sc (Hons) Applied Geology) MBA, MAIG). Mr
Reeves is a member of the Australian Institute of
Geoscientists and a Director and shareholder of the
Company. Mr Reeves has sufficient experience that
is relevant to the style of mineralisation and type of
deposit under consideration and to the activity
which he is undertaking to qualify as a Competent
Person as defined in the 2012 Edition of the
Australasian Code for Reporting of Exploration
Results, Mineral Resources and Ore Reserves. Mr
Reeves consents to the inclusion in this report of the
matters based on this information in the form and
context in which it appears.
The information in this report that relates to Mineral
Resources is based on information compiled by Mr
Lynn Widenbar, a Competent Person who is a
Member of The Australasian Institute of Mining and
Metallurgy. Mr Widenbar is acting as an
independent consultant to Tesoro Gold Limited. Mr
Widenbar has sufficient experience that is relevant
to the style of mineralisation and type of deposit
under consideration, and to the activity being
undertaken to qualify as a Competent Person as
defined in the 2012 Edition of the ‘Australasian
Code for Reporting of Exploration Results, Mineral
Resources and Ore Reserves’.
The Company
confirms that the form and context in which the
Competent Person’s findings are presented have
not been materially modified from the original
announcement on 9 March 2023 .
Mr Putland has reviewed and approved the
technical content of this announcement. Mr
Putland is a Competent Person as defined in the
2012 Edition of the Australasian Code for Reporting
of Exploration Results, Mineral Resources and Ore
Reserves (JORC Code 2012). Mr Putland consents to
the inclusion in this announcement of the matters
based on his information in the form and context in
which it appears.
Future Performance
This announcement may contain certain forwardlooking statements and opinion. Forward-looking
statements, including projections, forecasts and
estimates, are provided as a general guide only
and should not be relied on as an indication or
guarantee of future performance and involve
known
and
unknown
risks,
uncertainties,
assumptions, contingencies and other important
factors, many of which are outside the control of
the Company and which are subject to change
without notice and could cause the actual results,
performance or achievements of the Company to
be materially different from the future results,
performance or achievements expressed or implied
by such statements. Past performance is not
necessarily a guide to future performance and no
representation or warranty is made as to the
likelihood of achievement or reasonableness of any
forward-looking statements or other forecast.
Nothing contained in this announcement, nor any
information made available to you is, or and shall
be relied upon as, a promise, representation,
warranty or guarantee as to the past, present or the
future performance of Tesoro.
The information in this report that relates to the
Production Target, assumptions on Modifying
Factors and evaluation of other relevant factors are
based on and fairly represents information and
supporting documentation that has been compiled
for this announcement and have been compiled
under the supervision of Mr Linton Putland BEng
(Mining), MSc (Mineral Economics) & Member
AusIMM. Mr Putland is a Director of the Company.
TESOROGOLD.COM.AU
14
ASX ANNOUNCEMENT 28 APRIL 2023
Appendix 1 – Concession Schedule as at 31 March 2023
El Zorro Gold Project Exploration Concessions (85%* Tesoro Mining Chile SpA)
10-august-2026
Size
(ha)
200
Concession
type
Exploration
ZORRO 2B
10-august-2026
200
Exploration
ZORRO 3B
10-august-2026
200
Exploration
ZORRO 4B
10-august-2026
100
Exploration
ZORRO 5B
10-august-2026
200
Exploration
ZORRO 6B
10-august-2026
200
Exploration
PUNTA DE DIAMENTE 1A
17-august-2025
200
Exploration
PUNTA DE DIAMENTE 2A
06-august-2025
300
Exploration
PUNTA DE DIAMENTE 3A
28-september-2025
300
Exploration
LA NEGRA COJA 1A
10-august-2025
200
Exploration
LA NEGRA COJA 2A
06-august-2025
300
Exploration
LA NEGRA COJA 3A
10-august-2025
300
Exploration
LA NEGRA COJA 4A
06-august-2025
200
Exploration
LA NEGRA COJA 5A
09-august-2025
300
Exploration
LA NEGRA COJA 6A
11-august-2025
200
Exploration
LA NEGRA COJA 7A
09-august-2025
300
Exploration
LA NEGRA COJA 8A
11-august-2025
300
Exploration
LA NEGRA COJA 9A
09-august-2025
200
Exploration
LA NEGRA COJA 10A
11-august-2025
300
Exploration
LA NEGRA COJA 11A
10-august-2025
300
Exploration
LA NEGRA COJA 12A
11-august-2025
200
Exploration
LA NEGRA COJA 13A
10-august-2025
300
Exploration
LA NEGRA COJA 14A
11-august-2025
300
Exploration
LA NEGRA COJA 15A
10-august-2025
300
Exploration
LA NEGRA COJA 16A
18-august-2025
200
Exploration
LA NEGRA COJA 17A
17-august-2025
300
Exploration
LA NEGRA COJA 18A
18-august-2025
300
Exploration
LA NEGRA COJA 19A
11-august-2025
200
Exploration
NICE BARREL 1
05-august-2025
200
Exploration
NICE BARREL 2
05-august-2025
300
Exploration
NICE BARREL 3
06-august-2025
200
Exploration
NICE BARREL 4
05-august-2025
200
Exploration
NICE BARREL 5
06-august-2025
200
Exploration
NICE BARREL 6
05-august-2025
200
Exploration
NICE BARREL 7
10-august-2025
200
Exploration
NICE BARREL 13
28-september-2025
300
Exploration
NICE BARREL 12
28-september-2025
200
Exploration
NICE BARREL 11
28-september-2025
300
Exploration
NICE BARREL 10
28-september-2025
200
Exploration
NICE BARREL 9
28-september-2025
300
Exploration
NICE BARREL 8
28-september-2025
200
Exploration
SIERRA PATACONES 1
Replaced by SIERRA PATACONES 1A in process
300
Exploration
SIERRA PATACONES 2
Replaced by SIERRA PATACONES 2A in process
300
Exploration
Concession Name
Date of Expiration
ZORRO 1B
TESOROGOLD.COM.AU
15
ASX ANNOUNCEMENT 28 APRIL 2023
Concession Name
Date of Expiration
Size
(ha)
Concession
type
SIERRA PATACONES 3
Replaced by SIERRA PATACONES 3A in process
300
Exploration
SIERRA PATACONES 4
Replaced by SIERRA PATACONES 4A in process
300
Exploration
SIERRA PATACONES 5
Replaced by SIERRA PATACONES 5A in process
300
Exploration
SIERRA PATACONES 6
Replaced by SIERRA PATACONES 6A in process
300
Exploration
SIERRA PATACONES 7
Replaced by SIERRA PATACONES 7A in process
300
Exploration
SIERRA PATACONES 8
Replaced by SIERRA PATACONES 8A in process
300
Exploration
SIERRA PATACONES 9
Replaced by SIERRA PATACONES 9A in process
300
Exploration
300
Exploration
300
Exploration
300
Exploration
300
Exploration
300
Exploration
300
Exploration
300
Exploration
300
Exploration
300
Exploration
300
Exploration
300
Exploration
300
Exploration
300
Exploration
300
Exploration
300
Exploration
300
Exploration
300
Exploration
300
Exploration
300
Exploration
300
Exploration
300
Exploration
300
Exploration
300
Exploration
300
Exploration
300
Exploration
SIERRA PATACONES 10
SIERRA PATACONES 11
SIERRA PATACONES 12
SIERRA PATACONES 13
SIERRA PATACONES 14
SIERRA PATACONES 15
SIERRA PATACONES 20
SIERRA PATACONES 19
SIERRA PATACONES 18
SIERRA PATACONES 17
SIERRA PATACONES 16
SIERRA PATACONES 21
SIERRA PATACONES 22
SIERRA PATACONES 23
SIERRA PATACONES 24
SIERRA PATACONES 25
SIERRA PATACONES 26
SIERRA PATACONES 27
SIERRA PATACONES 28
SIERRA PATACONES 29
SIERRA PATACONES 30
SIERRA PATACONES 31
SIERRA PATACONES 32
SIERRA PATACONES 33
SIERRA PATACONES 34
TESOROGOLD.COM.AU
Replaced by SIERRA PATACONES 10A in
process
Replaced by SIERRA PATACONES 11A in
process
Replaced by SIERRA PATACONES 12A in
process
Replaced by SIERRA PATACONES 13A in
process
Replaced by SIERRA PATACONES 14A in
process
Replaced by SIERRA PATACONES 15A in
process
Replaced by SIERRA PATACONES 20A in
process
Replaced by SIERRA PATACONES 19A in
process
Replaced by SIERRA PATACONES 18A in
process
Replaced by SIERRA PATACONES 17A in
process
Replaced by SIERRA PATACONES 16A in
process
Replaced by SIERRA PATACONES 21A in
process
Replaced by SIERRA PATACONES 22A in
process
Replaced by SIERRA PATACONES 23A in
process
Replaced by SIERRA PATACONES 24A in
process
Replaced by SIERRA PATACONES 25A in
process
Replaced by SIERRA PATACONES 26A in
process
Replaced by SIERRA PATACONES 27A in
process
Replaced by SIERRA PATACONES 28A in
process
Replaced by SIERRA PATACONES 29A in
process
Replaced by SIERRA PATACONES 30A in
process
Replaced by SIERRA PATACONES 31A in
process
Replaced by SIERRA PATACONES 32A in
process
Replaced by SIERRA PATACONES 33A in
process
Replaced by SIERRA PATACONES 34A in
process
16
ASX ANNOUNCEMENT 28 APRIL 2023
Concession Name
SIERRA PATACONES 35
SIERRA PATACONES 42
SIERRA PATACONES 41
SIERRA PATACONES 40
SIERRA PATACONES 39
SIERRA PATACONES 38
SIERRA PATACONES 37
SIERRA PATACONES 36
SIERRA PATACONES 43
SIERRA PATACONES 44
SIERRA PATACONES 45
SIERRA PATACONES 46
SIERRA PATACONES 47
SIERRA PATACONES 48
SIERRA PATACONES 49
SIERRA PATACONES 50
SIERRA PATACONES 51
SIERRA PATACONES 53
SIERRA PATACONES 54
SIERRA PATACONES 55
SIERRA PATACONES 56
SIERRA PATACONES 57
SIERRA PATACONES 62
SIERRA PATACONES 61
SIERRA PATACONES 60
SIERRA PATACONES 59
SIERRA PATACONES 58
SIERRA PATACONES 63
SIERRA PATACONES 64
SIERRA PATACONES 65
TESOROGOLD.COM.AU
Date of Expiration
Replaced by SIERRA PATACONES 35A in
process
Replaced by SIERRA PATACONES 42A in
process
Replaced by SIERRA PATACONES 41A in
process
Replaced by SIERRA PATACONES 40A in
process
Replaced by SIERRA PATACONES 39A in
process
Replaced by SIERRA PATACONES 38A in
process
Replaced by SIERRA PATACONES 37A in
process
Replaced by SIERRA PATACONES 36A in
process
Replaced by SIERRA PATACONES 43A in
process
Replaced by SIERRA PATACONES 44A in
process
Replaced by SIERRA PATACONES 45A in
process
Replaced by SIERRA PATACONES 46A in
process
Replaced by SIERRA PATACONES 47A in
process
Replaced by SIERRA PATACONES 48A in
process
Replaced by SIERRA PATACONES 49A in
process
Replaced by SIERRA PATACONES 50A in
process
Replaced by SIERRA PATACONES 51A in
process
Replaced by SIERRA PATACONES 53A in
process
Replaced by SIERRA PATACONES 54A in
process
Replaced by SIERRA PATACONES 55A in
process
Replaced by SIERRA PATACONES 56A in
process
Replaced by SIERRA PATACONES 57A in
process
Replaced by SIERRA PATACONES 62A in
process
Replaced by SIERRA PATACONES 61A in
process
Replaced by SIERRA PATACONES 60A in
process
Replaced by SIERRA PATACONES 59A in
process
Replaced by SIERRA PATACONES 58A in
process
Replaced by SIERRA PATACONES 63A in
process
Replaced by SIERRA PATACONES 64A in
process
Replaced by SIERRA PATACONES 65A in
process
Size
(ha)
Concession
type
300
Exploration
300
Exploration
300
Exploration
300
Exploration
300
Exploration
300
Exploration
300
Exploration
300
Exploration
300
Exploration
300
Exploration
300
Exploration
300
Exploration
300
Exploration
300
Exploration
300
Exploration
300
Exploration
300
Exploration
300
Exploration
300
Exploration
300
Exploration
300
Exploration
300
Exploration
300
Exploration
300
Exploration
300
Exploration
300
Exploration
300
Exploration
300
Exploration
300
Exploration
300
Exploration
17
ASX ANNOUNCEMENT 28 APRIL 2023
Concession Name
Date of Expiration
Size
(ha)
Concession
type
300
Exploration
300
Exploration
300
Exploration
300
Exploration
300
Exploration
300
Exploration
300
Exploration
300
Exploration
300
Exploration
300
Exploration
300
Exploration
300
Exploration
300
Exploration
300
Exploration
300
Exploration
300
Exploration
300
Exploration
300
Exploration
300
Exploration
300
Exploration
SIERRA PATACONES 52
Replaced by SIERRA PATACONES 66A in
process
Replaced by SIERRA PATACONES 67A in
process
Replaced by SIERRA PATACONES 68A in
process
Replaced by SIERRA PATACONES 69A in
process
Replaced by SIERRA PATACONES 70A in
process
Replaced by SIERRA PATACONES 71A in
process
Replaced by SIERRA PATACONES 72A in
process
Replaced by SIERRA PATACONES 73A in
process
Replaced by SIERRA PATACONES 74A in
process
Replaced by SIERRA PATACONES 75A in
process
Replaced by SIERRA PATACONES 76A in
process
Replaced by SIERRA PATACONES 77A in
process
Replaced by SIERRA PATACONES 84A in
process
Replaced by SIERRA PATACONES 83A in
process
Replaced by SIERRA PATACONES 82A in
process
Replaced by SIERRA PATACONES 81A in
process
Replaced by SIERRA PATACONES 80A in
process
Replaced by SIERRA PATACONES 79A in
process
Replaced by SIERRA PATACONES 78A in
process
Replaced by SIERRA PATACONES 52A in
process
GOLD STORE 72
Replaced by GOLD STORE 72A in process
300
Exploration
GOLD STORE 71
Replaced by GOLD STORE 71A in process
300
Exploration
GOLD STORE 70
Replaced by GOLD STORE 70A in process
300
Exploration
GOLD STORE 69
Replaced by GOLD STORE 69A in process
300
Exploration
GOLD STORE 68
Replaced by GOLD STORE 68A in process
300
Exploration
GOLD STORE 67
Replaced by GOLD STORE 67A in process
300
Exploration
GOLD STORE 66
Replaced by GOLD STORE 66A in process
300
Exploration
GOLD STORE 1
Replaced by GOLD STORE 1A in process
300
Exploration
GOLD STORE 2
Replaced by GOLD STORE 2A in process
300
Exploration
GOLD STORE 3
Replaced by GOLD STORE 3A in process
300
Exploration
GOLD STORE 4
Replaced by GOLD STORE 4A in process
300
Exploration
GOLD STORE 5
Replaced b
Share your feedback