Quarterly Activities Report
Released
Released
Announcement PDF
Sign up HERE to our Investor Hub
ASX ANNOUNCEMENT
30 OCTOBER 2023
ASX: TSO OTCQB: TSORF
QUARTERLY ACTIVITIES AND CASHFLOW REPORT
FOR THE PERIOD ENDED 30 SEPTEMBER 2023
Tesoro Gold Limited (ASX: TSO, OTCQB: TSORF) (Tesoro or the Company) is pleased to report
on its activities for the quarter ended 30 September 2023 (the Quarter).
HIGHLIGHTS
•
Surface sampling results indicated a significant southern extension to Ternera, with gold
mineralisation shown to extend up to 380m south from the existing Ternera Mineral
Resource Estimate (MRE) 1.
•
Initial eight holes at the Kitsune Target and one scout hole at Toro Blanco completed,
with all holes successfully intersecting the target target El Zorro Tonalite (EZT) lithology1.
•
Kitsune drilling program to be completed once a replacement drilling contractor is
engaged1.
•
El Zorro SCM (Tesoro 89.1%) granted exporter status allowing for historical Value Added
Tax (VAT) recovery and future VAT exemption1.
•
Value of outstanding qualifying, unrecovered VAT expenditure stands at CLP2.39 billion,
or approximately A$4.15 million1.
•
Tesoro’s underlying ownership in the El Zorro project increased to approximately 89.1%
via recognition of historical aggregate capital contribution of approximately A$22.4
million since March 2021 2.
•
Mr Alan Gibson appointed the Tesoro Board as nominee Non-Executive Director for
Gold Fields Ltd 3.
•
Cash balance of A$1.04 million and zero debt at 30 September 2023.
Tesoro Gold Managing Director, Zeff Reeves commented:
“During the September quarter we received some fantastic surface sampling results which
provided strong evidence that the Ternera gold bearing fault zones extend, at a minimum,
of up to 380m south of the existing deposit.
1 Refer ASX announcement 18 September 2023
2 Refer ASX announcement 3 July 2023
3 Refer ASX announcement 30 August 2032
ASX ANNOUNCEMENT 30 OCTOBER 2023
We completed eight first pass drill holes at Kitsune and one scout hole at Toro Blanco. All
holes drilled to date successfully intersected the target EZT lithology, indicating strong
potential for large scale extensions of the existing Ternera Resource and offering
exceptional exploration and resource growth potential.
We remain confident in the immense value inherent in Ternera and shall continue to
progress our efforts in growing the existing Tenera MRE and unlocking the potential of the
broader El Zorro District as a major emerging gold province in Chile.”
EL ZORRO GOLD PROJECT, CHILE
Ternera South Surface Sampling Results
The shallow, high-grade Ternera South drilling results announced in the previous quarter
(refer ASX Announcements 11 May 2023 and 21 June 2023) have been followed by
additional activities designed to better define the southern extensions of the Ternera
Deposit. These activities included detailed mapping and further continuous surface
channel sampling south of the existing Ternera MRE.
On 18 September, Tesoro announced that further assays received enabled the definition
of shallow, high-grade gold zones, with multiple mineralised fault zones returning highgrade results. Surface gold mineralisation has now been confirmed up to 380m south of
the existing MRE, validated by the previously announced drilling.
Results from surface sampling1 suggest a significant southern extension to Ternera, with
grades up to 30.80g/t Au returned, including;
•
4.00m @ 13.31g/t Au (EZTR004143);
•
13.00m @ 9.67g/t Au (EZTR004207) including;
─ 6.00m @ 20.02g/t Au; and
─ 3.00m @ 30.80g/t Au.
•
9.00m @ 4.60g/t Au (EZTR004208) including;
─ 3.00m @ 12.60g/t Au.
─ 3.00m @ 4.70g/t Au (EZTR004209).
•
Results demonstrate surface gold mineralisation extends up to 380m south of the
existing Ternera MRE.
•
Up to 15g/t Au returned from an initial scout hole completed at Toro Blanco.
Kitsune Target Drilling
First pass drilling at the Kitsune Target was put on hold while a replacement contractor is
engaged to complete the scheduled program. To date, eight holes are complete, and
TESOROGOLD.COM.AU
2
ASX ANNOUNCEMENT 30 OCTOBER 2023
drilling is planned to continue once a new drilling contractor has been secured to
complete the remaining program. All initial holes have intersected the EZT lithology which
is the main gold host at the Ternera Gold Deposit. Final assays and multielement XRF
analysis of pulverised core samples are outstanding, with results expected during Q4 2023.
Toro Blanco Drilling
One scout hole was completed at Toro Blanco which returned a shallow high-grade
intercept of 0.50m @ 15.00g/t Au from 35.00m within faulted EZT. This result confirmed the
continuation of the mineralising Dorado Fault System from Ternera to over 1,900m north to
Toro Blanco. Tesoro plans to further define gold mineralisation between Ternera and Toro
Blanco with additional drilling in the coming months, targeting extensions of the Ternera
Gold Deposit to the north.
El Zorro S.C.M. Granted Exporter Status
As previously announced on 25 August 2022, the Company received judicial approval for
provisional surface property easement rights at the El Zorro Gold Project, Chile. These
rights entitle Tesoro to recover VAT paid on previous expenditure on the acquisition of
fixed assets. As announced on 31 January 2023, approximately A$592,000 has been
received to date in its VAT recoveries.
Tesoro announced on 18 September 2023 that it had completed the relevant
requirements to be qualified as a future exporter. This permits the Company to receive the
full recovery of VAT already expended on the El Zorro Gold Project since 2017 and also
any future VAT generated by the Project.
The current balance of unrecovered VAT expenditure is CLP2.39B, or approximately
A$4.15M. The Company is working with the Chilean tax authority to have this credit
refunded as soon as possible.
New gold anomaly defined at Drone Hill
Post the end of the quarter on 18 October 2023, the Company announced positive
surface sampling results at Drone Hill, west of Ternera. This new large outcropping gold
anomaly returned intersections of up to 47m, including:
•
47m @ 1.40g/t Au (EZTR004255) including;
•
9m @ 4.66g/t Au
• 15m @ 0.53g/t Au (EZTR004132)
The surface sampling results have defined a number of high-priority drill targets for the next
stage of work at Drone Hill.
TESOROGOLD.COM.AU
3
ASX ANNOUNCEMENT 30 OCTOBER 2023
Increased Ownership Interest in El Zorro
Tesoro announced on 3 July 2023 that its 95%-owned Chilean subsidiary Tesoro Mining
Chile SpA (TMC) increased its ownership stake in El Zorro to approximately 93.8%.
At a shareholder meeting held on 7 June 2023, El Zorro S.C.M resolved to increase the
capital base via contribution on a pro-rated basis. TMC subscribed its pro-rata shares for
an amount equal to CLP12,120,334,847 (approximatelyA$22.4 million). This sum reflects
TMC’s funding of exploration and development activities at El Zorro since March 2021.
Wanaco SpA, the minority shareholder in El Zorro S.C.M., declined to participate in the
capital increase, resulting in TMC increasing its ownership in El Zorro S.C.M. to
approximately 93.8%. Tesoro now holds a total ownership position in El Zorro of
approximately 89.1%
CORPORATE
Board Changes
On 30 August 2023, Tesoro announced the appointment of Mr Alan Gibson to the Board as
a Non-Executive Director. Mr Gibson is a nominee of Corporate International Holdings BV,
a wholly owned subsidiary of Gold Fields Ltd, which currently owns approximately 15.49%
of Tesoro’s issued capital.
Alan Gibson is an experienced and skilled M&A lawyer, with more than 20 years’
experience in Corporate, Energy and Resources Law, including more than 10 years of that
as part of the Gold Fields Corporate Development team. Alan is currently Vice President:
Corporate Development – Head of Legal for Gold Fields and has played an important role
in a number of the group’s key growth transactions around the world.
Mr. Gibson is an admitted legal practitioner holding a Bachelor of Laws and Bachelor of
Economics from Murdoch University (WA).
Subsequent to quarter end, on 5 October 2023, Tesoro announced the resignation of Ms
Kristie Young as Non-Executive Director. Ms Young stepped down from the Tesoro board
to focus on her other commitments.
As part of an ongoing Board re-composition, the Company intends to make new
appointments in due course.
Salary Sacrifice Plan
On 19 October 2023, the Company issued 380,570 share rights to Executive Director, Mr
Linton Putland in lieu of approx. $7,500 of remuneration, pursuant to the Company’s Salary
Sacrifice Plan as approved by shareholders at the Annual General Meeting held on 25
TESOROGOLD.COM.AU
4
ASX ANNOUNCEMENT 30 OCTOBER 2023
November 2023. The Salary Sacrifice Plan enables executives, employees and directors of
the Company to receive share rights in the Company, in lieu of remuneration or fees. The
Salary Sacrifice Plan has been designed to further align participants (being executives,
employees and directors of the Company) with shareholder interests whilst being an
effective way for the Company to conserve capital.
Expenditure and Payments to Related Parties
During the Quarter, the Company spent approximately A$1.40 million on exploration
activities, which comprised primarily of diamond drilling programs, surface mapping and
sampling programs and ongoing mining studies at the Ternera Gold Deposit.
As outlined in the Appendix 5B for the quarter ending 30 September 2023 (sections 6.1 and
6.2), approximately A$221k in payments were made to related parties and/or their
associates as remuneration (inc. superannuation) for the Managing Director, NonExecutive Director fees and consulting fees.
Cash
Tesoro’s cash balance at 30 September 2023 was A$1.04 million and the Company had
zero debt (excluding typical trade creditors).
Authorised by the Board of Tesoro Gold Ltd.
For more information:
Company:
Zeff Reeves, Managing Director
Tesoro Gold Limited
info@tesorogold.com.au
TESOROGOLD.COM.AU
5
ASX ANNOUNCEMENT 30 OCTOBER 2023
Figure 1 – Ternera South surface sampling results and locations. Drilling results refer to previously announced
southern extension drilling (ASX Announcements 11 May 2023 and 21 June 2023)) Datum PSAD56 19S
TESOROGOLD.COM.AU
6
ASX ANNOUNCEMENT 30 OCTOBER 2023
Figure 2 – Ternera to Kitsune geology map showing completed drilling at Toro Blanco and Kitsune. Holes
ZDDH0244 and ZDDH0254A previously reported, refer ASX announcements 12 December 2021 and 4 February
2022. Datum PSDAD56 19S
TESOROGOLD.COM.AU
7
ASX ANNOUNCEMENT 30 OCTOBER 2023
Figure 3 – El Zorro Gold Project surface sampling results for the Ternera to Calderillas mineralised trend.
TESOROGOLD.COM.AU
8
ASX ANNOUNCEMENT 30 OCTOBER 2023
Table 1: Toro Blanco and Kitsune drillhole locations.
Hole Location
Hole Orientation
Drill Depth (m)
TARGET
Northing Easting Elevation
Dip
Azimuth
ZDDH00327 342290
7037884 890
-60
240
31.90
Toro Blanco (Abandoned)
ZDDH00327A 342290
7037883 890
-60
240
146.50
Toro Blanco
ZDDH00328 341359
7038855 690
-60
240
233.50
Kitsune
ZDDH00329 341724
7038695 699
-60
240
200.00
Kitsune
ZDDH00330 341788
7038750 745
-60
240
200.00
Kitsune
ZDDH00331 341828
7038480 830
-60
240
146.60
Kitsune
ZDDH00332 341426
7038921 642
-60
240
100.00
Kitsune
ZDDH00333 340938
7039755 791
-60
240
130.00
Kitsune
ZDDH00334 341249
7039400 684
-60
240
51.50
Kitsune (Abandoned)
ZDDH00335 340938
7039755 791
-60
0
140.10
Kitsune
Hole ID
TESOROGOLD.COM.AU
9
ASX ANNOUNCEMENT 30 OCTOBER 2023
About Tesoro
Future Performance
Tesoro Gold Limited was established with a strategy o
acquiring, exploring, and developing mining project
in the Coastal Cordillera region of Chile. The Coasta
Cordillera region is host to multiple world class coppe
and gold mines, has well established infrastructure
service providers and an experienced minin
workforce. Large areas of the Coastal Cordiller
remain unexplored due to the unconsolidated natur
of mining concession ownership, but Tesoro, via its in
country network and experience has been abl
secure rights to a district scale gold project in-line wit
the Company’s strategy. Tesoro’s 95% owned Chilea
subsidiary owns 85% of the El Zorro Gold Project.
This announcement may contain certain forwardlooking statements and opinion. Forward-looking
statements, including projections, forecasts and
estimates, are provided as a general guide only
and should not be relied on as an indication or
guarantee of future performance and involve
known
and
unknown
risks,
uncertainties,
assumptions, contingencies and other important
factors, many of which are outside the control of
the Company and which are subject to change
without notice and could cause the actual results,
performance or achievements of the Company to
be materially different from the future results,
performance or achievements expressed or implied
by such statements. Past performance is not
necessarily a guide to future performance and no
representation or warranty is made as to the
likelihood of achievement or reasonableness of any
forward-looking statements or other forecast.
Nothing contained in this announcement, nor any
information made available to you is, or and shall
be relied upon as, a promise, representation,
warranty or guarantee as to the past, present or the
future performance of Tesoro.
Competent Persons Statements
The information in this report that relates to
Exploration Results is based on information
compiled by Mr Zeffron Reeves (B App Sc (Hons)
Applied Geology) MBA, MAIG). Mr Reeves is a
member of the Australian Institute of Geoscientists
and a Director and shareholder of the Company.
Mr Reeves has sufficient experience that is relevant
to the style of mineralisation and type of deposit
under consideration and to the activity which he is
undertaking to qualify as a Competent Person as
defined in the 2012 Edition of the Australasian Code
for Reporting of Exploration Results, Mineral
Resources and Ore Reserves. Mr Reeves consents to
the inclusion in this report of the matters based on
this information in the form and context in which it
appears.
The information in this report that relates to Mineral
Resources is based on information compiled by Mr
Lynn Widenbar, a Competent Person who is a
Member of The Australasian Institute of Mining and
Metallurgy. Mr Widenbar is acting as an
independent consultant to Tesoro Gold Limited. Mr
Widenbar has sufficient experience that is relevant
to the style of mineralisation and type of deposit
under consideration, and to the activity being
undertaken to qualify as a Competent Person as
defined in the 2012 Edition of the ‘Australasian
Code for Reporting of Exploration Results, Mineral
Resources and Ore Reserves’.
The Company
confirms that the form and context in which the
Competent Person’s findings are presented have
not been materially modified from the original
announcement on 9 March 2023.
TESOROGOLD.COM.AU
10
ASX ANNOUNCEMENT 30 OCTOBER 2023
APPENDIX 1: CONCESSION SCHEDULE
EL ZORRO GOLD PROJECT EXPLORATION CONCESSIONS (93.8%* Tesoro Mining Chile
SpA)
10-august-2026
Size
(ha)
200
Concession
type
Exploration
ZORRO 2B
10-august-2026
200
Exploration
ZORRO 3B
10-august-2026
200
Exploration
ZORRO 4B
10-august-2026
100
Exploration
ZORRO 5B
10-august-2026
200
Exploration
ZORRO 6B
10-august-2026
200
Exploration
PUNTA DE DIAMENTE 1A
17-august-2025
200
Exploration
PUNTA DE DIAMENTE 2A
06-august-2025
300
Exploration
PUNTA DE DIAMENTE 3A
28-september-2025
300
Exploration
LA NEGRA COJA 1A
10-august-2025
200
Exploration
LA NEGRA COJA 2A
06-august-2025
300
Exploration
LA NEGRA COJA 3A
10-august-2025
300
Exploration
LA NEGRA COJA 4A
06-august-2025
200
Exploration
LA NEGRA COJA 5A
09-august-2025
300
Exploration
LA NEGRA COJA 6A
11-august-2025
200
Exploration
LA NEGRA COJA 7A
09-august-2025
300
Exploration
LA NEGRA COJA 8A
11-august-2025
300
Exploration
LA NEGRA COJA 9A
09-august-2025
200
Exploration
LA NEGRA COJA 10A
11-august-2025
300
Exploration
LA NEGRA COJA 11A
10-august-2025
300
Exploration
LA NEGRA COJA 12A
11-august-2025
200
Exploration
LA NEGRA COJA 13A
10-august-2025
300
Exploration
LA NEGRA COJA 14A
11-august-2025
300
Exploration
LA NEGRA COJA 15A
10-august-2025
300
Exploration
LA NEGRA COJA 16A
18-august-2025
200
Exploration
LA NEGRA COJA 17A
17-august-2025
300
Exploration
LA NEGRA COJA 18A
18-august-2025
300
Exploration
LA NEGRA COJA 19A
11-august-2025
200
Exploration
NICE BARREL 1
05-august-2025
200
Exploration
NICE BARREL 2
05-august-2025
300
Exploration
NICE BARREL 3
06-august-2025
200
Exploration
NICE BARREL 4
05-august-2025
200
Exploration
NICE BARREL 5
06-august-2025
200
Exploration
NICE BARREL 6
05-august-2025
200
Exploration
NICE BARREL 7
10-august-2025
200
Exploration
NICE BARREL 13
28-september-2025
300
Exploration
NICE BARREL 12
28-september-2025
200
Exploration
NICE BARREL 11
28-september-2025
300
Exploration
NICE BARREL 10
28-september-2025
200
Exploration
NICE BARREL 9
28-september-2025
300
Exploration
NICE BARREL 8
28-september-2025
200
Exploration
Concession Name
Date of Expiration
ZORRO 1B
TESOROGOLD.COM.AU
11
ASX ANNOUNCEMENT 30 OCTOBER 2023
Concession Name
Date of Expiration
Size
(ha)
Concession
type
SIERRA PATACONES 1
Replaced by SIERRA PATACONES 1A in process
300
Exploration
SIERRA PATACONES 2
Replaced by SIERRA PATACONES 2A in process
300
Exploration
SIERRA PATACONES 3
Replaced by SIERRA PATACONES 3A in process
300
Exploration
SIERRA PATACONES 4
Replaced by SIERRA PATACONES 4A in process
300
Exploration
SIERRA PATACONES 5
Replaced by SIERRA PATACONES 5A in process
300
Exploration
SIERRA PATACONES 6
Replaced by SIERRA PATACONES 6A in process
300
Exploration
SIERRA PATACONES 7
Replaced by SIERRA PATACONES 7A in process
300
Exploration
SIERRA PATACONES 8
Replaced by SIERRA PATACONES 8A in process
300
Exploration
SIERRA PATACONES 9
Replaced by SIERRA PATACONES 9A in process
300
Exploration
SIERRA PATACONES 10
Replaced by SIERRA PATACONES 10A in process
300
Exploration
SIERRA PATACONES 11
Replaced by SIERRA PATACONES 11A in process
300
Exploration
SIERRA PATACONES 12
Replaced by SIERRA PATACONES 12A in process
300
Exploration
SIERRA PATACONES 13
Replaced by SIERRA PATACONES 13A in process
300
Exploration
SIERRA PATACONES 14
Replaced by SIERRA PATACONES 14A in process
300
Exploration
SIERRA PATACONES 15
Replaced by SIERRA PATACONES 15A in process
300
Exploration
SIERRA PATACONES 20
Replaced by SIERRA PATACONES 20A in process
300
Exploration
SIERRA PATACONES 19
Replaced by SIERRA PATACONES 19A in process
300
Exploration
SIERRA PATACONES 18
Replaced by SIERRA PATACONES 18A in process
300
Exploration
SIERRA PATACONES 17
Replaced by SIERRA PATACONES 17A in process
300
Exploration
SIERRA PATACONES 16
Replaced by SIERRA PATACONES 16A in process
300
Exploration
SIERRA PATACONES 21
Replaced by SIERRA PATACONES 21A in process
300
Exploration
SIERRA PATACONES 22
Replaced by SIERRA PATACONES 22A in process
300
Exploration
SIERRA PATACONES 23
Replaced by SIERRA PATACONES 23A in process
300
Exploration
SIERRA PATACONES 24
Replaced by SIERRA PATACONES 24A in process
300
Exploration
SIERRA PATACONES 25
Replaced by SIERRA PATACONES 25A in process
300
Exploration
SIERRA PATACONES 26
Replaced by SIERRA PATACONES 26A in process
300
Exploration
SIERRA PATACONES 27
Replaced by SIERRA PATACONES 27A in process
300
Exploration
SIERRA PATACONES 28
Replaced by SIERRA PATACONES 28A in process
300
Exploration
SIERRA PATACONES 29
Replaced by SIERRA PATACONES 29A in process
300
Exploration
SIERRA PATACONES 30
Replaced by SIERRA PATACONES 30A in process
300
Exploration
SIERRA PATACONES 31
Replaced by SIERRA PATACONES 31A in process
300
Exploration
SIERRA PATACONES 32
Replaced by SIERRA PATACONES 32A in process
300
Exploration
SIERRA PATACONES 33
Replaced by SIERRA PATACONES 33A in process
300
Exploration
SIERRA PATACONES 34
Replaced by SIERRA PATACONES 34A in process
300
Exploration
SIERRA PATACONES 35
Replaced by SIERRA PATACONES 35A in process
300
Exploration
SIERRA PATACONES 42
Replaced by SIERRA PATACONES 42A in process
300
Exploration
SIERRA PATACONES 41
Replaced by SIERRA PATACONES 41A in process
300
Exploration
SIERRA PATACONES 40
Replaced by SIERRA PATACONES 40A in process
300
Exploration
SIERRA PATACONES 39
Replaced by SIERRA PATACONES 39A in process
300
Exploration
SIERRA PATACONES 38
Replaced by SIERRA PATACONES 38A in process
300
Exploration
TESOROGOLD.COM.AU
12
ASX ANNOUNCEMENT 30 OCTOBER 2023
Concession Name
Date of Expiration
Size
(ha)
Concession
type
SIERRA PATACONES 37
Replaced by SIERRA PATACONES 37A in process
300
Exploration
SIERRA PATACONES 36
Replaced by SIERRA PATACONES 36A in process
300
Exploration
SIERRA PATACONES 43
Replaced by SIERRA PATACONES 43A in process
300
Exploration
SIERRA PATACONES 44
Replaced by SIERRA PATACONES 44A in process
300
Exploration
SIERRA PATACONES 45
Replaced by SIERRA PATACONES 45A in process
300
Exploration
SIERRA PATACONES 46
Replaced by SIERRA PATACONES 46A in process
300
Exploration
SIERRA PATACONES 47
Replaced by SIERRA PATACONES 47A in process
300
Exploration
SIERRA PATACONES 48
Replaced by SIERRA PATACONES 48A in process
300
Exploration
SIERRA PATACONES 49
Replaced by SIERRA PATACONES 49A in process
300
Exploration
SIERRA PATACONES 50
Replaced by SIERRA PATACONES 50A in process
300
Exploration
SIERRA PATACONES 51
Replaced by SIERRA PATACONES 51A in process
300
Exploration
SIERRA PATACONES 53
Replaced by SIERRA PATACONES 53A in process
300
Exploration
SIERRA PATACONES 54
Replaced by SIERRA PATACONES 54A in process
300
Exploration
SIERRA PATACONES 55
Replaced by SIERRA PATACONES 55A in process
300
Exploration
SIERRA PATACONES 56
Replaced by SIERRA PATACONES 56A in process
300
Exploration
SIERRA PATACONES 57
Replaced by SIERRA PATACONES 57A in process
300
Exploration
SIERRA PATACONES 62
Replaced by SIERRA PATACONES 62A in process
300
Exploration
SIERRA PATACONES 61
Replaced by SIERRA PATACONES 61A in process
300
Exploration
SIERRA PATACONES 60
Replaced by SIERRA PATACONES 60A in process
300
Exploration
SIERRA PATACONES 59
Replaced by SIERRA PATACONES 59A in process
300
Exploration
SIERRA PATACONES 58
Replaced by SIERRA PATACONES 58A in process
300
Exploration
SIERRA PATACONES 63
Replaced by SIERRA PATACONES 63A in process
300
Exploration
SIERRA PATACONES 64
Replaced by SIERRA PATACONES 64A in process
300
Exploration
SIERRA PATACONES 65
Replaced by SIERRA PATACONES 65A in process
300
Exploration
SIERRA PATACONES 66
Replaced by SIERRA PATACONES 66A in process
300
Exploration
SIERRA PATACONES 67
Replaced by SIERRA PATACONES 67A in process
300
Exploration
SIERRA PATACONES 68
Replaced by SIERRA PATACONES 68A in process
300
Exploration
SIERRA PATACONES 69
Replaced by SIERRA PATACONES 69A in process
300
Exploration
SIERRA PATACONES 70
Replaced by SIERRA PATACONES 70A in process
300
Exploration
SIERRA PATACONES 71
Replaced by SIERRA PATACONES 71A in process
300
Exploration
SIERRA PATACONES 72
Replaced by SIERRA PATACONES 72A in process
300
Exploration
SIERRA PATACONES 73
Replaced by SIERRA PATACONES 73A in process
300
Exploration
SIERRA PATACONES 74
Replaced by SIERRA PATACONES 74A in process
300
Exploration
SIERRA PATACONES 75
Replaced by SIERRA PATACONES 75A in process
300
Exploration
SIERRA PATACONES 76
Replaced by SIERRA PATACONES 76A in process
300
Exploration
SIERRA PATACONES 77
Replaced by SIERRA PATACONES 77A in process
300
Exploration
SIERRA PATACONES 84
Replaced by SIERRA PATACONES 84A in process
300
Exploration
SIERRA PATACONES 83
Replaced by SIERRA PATACONES 83A in process
300
Exploration
SIERRA PATACONES 82
Replaced by SIERRA PATACONES 82A in process
300
Exploration
SIERRA PATACONES 81
Replaced by SIERRA PATACONES 81A in process
300
Exploration
TESOROGOLD.COM.AU
13
ASX ANNOUNCEMENT 30 OCTOBER 2023
Concession Name
Date of Expiration
Size
(ha)
Concession
type
SIERRA PATACONES 80
Replaced by SIERRA PATACONES 80A in process
300
Exploration
SIERRA PATACONES 79
Replaced by SIERRA PATACONES 79A in process
300
Exploration
SIERRA PATACONES 78
Replaced by SIERRA PATACONES 78A in process
300
Exploration
SIERRA PATACONES 52
Replaced by SIERRA PATACONES 52A in process
300
Exploration
GOLD STORE 72
Replaced by GOLD STORE 72A in process
300
Exploration
GOLD STORE 71
Replaced by GOLD STORE 71A in process
300
Exploration
GOLD STORE 70
Replaced by GOLD STORE 70A in process
300
Exploration
GOLD STORE 69
Replaced by GOLD STORE 69A in process
300
Exploration
GOLD STORE 68
Replaced by GOLD STORE 68A in process
300
Exploration
GOLD STORE 67
Replaced by GOLD STORE 67A in process
300
Exploration
GOLD STORE 66
Replaced by GOLD STORE 66A in process
300
Exploration
GOLD STORE 1
Replaced by GOLD STORE 1A in process
300
Exploration
GOLD STORE 2
Replaced by GOLD STORE 2A in process
300
Exploration
GOLD STORE 3
Replaced by GOLD STORE 3A in process
300
Exploration
GOLD STORE 4
Replaced by GOLD STORE 4A in process
300
Exploration
GOLD STORE 5
Replaced by GOLD STORE 5A in process
300
Exploration
GOLD STORE 6
Replaced by GOLD STORE 6A in process
300
Exploration
GOLD STORE 7
Replaced by GOLD STORE 7A in process
300
Exploration
GOLD STORE 8
Replaced by GOLD STORE 8A in process
300
Exploration
GOLD STORE 9
Replaced by GOLD STORE 9A in process
300
Exploration
GOLD STORE 10
Replaced by GOLD STORE 10A in process
300
Exploration
GOLD STORE 11
Replaced by GOLD STORE 11A in process
300
Exploration
GOLD STORE 12
Replaced by GOLD STORE 12A in process
300
Exploration
GOLD STORE 13
Replaced by GOLD STORE 13A in process
300
Exploration
GOLD STORE 14
Replaced by GOLD STORE 14A in process
300
Exploration
GOLD STORE 15
Replaced by GOLD STORE 15A in process
300
Exploration
GOLD STORE 16
Replaced by GOLD STORE 16A in process
300
Exploration
GOLD STORE 17
Replaced by GOLD STORE 17A in process
300
Exploration
GOLD STORE 18
Replaced by GOLD STORE 18A in process
300
Exploration
GOLD STORE 19
Replaced by GOLD STORE 19A in process
300
Exploration
GOLD STORE 20
Replaced by GOLD STORE 20A in process
300
Exploration
GOLD STORE 21
Replaced by GOLD STORE 21A in process
300
Exploration
GOLD STORE 22
Replaced by GOLD STORE 22A in process
300
Exploration
GOLD STORE 23
Replaced by GOLD STORE 23A in process
300
Exploration
GOLD STORE 24
Replaced by GOLD STORE 24A in process
300
Exploration
GOLD STORE 25
Replaced by GOLD STORE 25A in process
300
Exploration
GOLD STORE 26
Replaced by GOLD STORE 26A in process
300
Exploration
GOLD STORE 27
Replaced by GOLD STORE 27A in process
300
Exploration
GOLD STORE 28
Replaced by GOLD STORE 28A in process
300
Exploration
GOLD STORE 29
Replaced by GOLD STORE 29A in process
300
Exploration
GOLD STORE 30
Replaced by GOLD STORE 30A in process
300
Exploration
GOLD STORE 36
Replaced by GOLD STORE 36A in process
300
Exploration
GOLD STORE 35
Replaced by GOLD STORE 35A in process
300
Exploration
GOLD STORE 34
Replaced by GOLD STORE 34A in process
300
Exploration
GOLD STORE 33
Replaced by GOLD STORE 33A in process
300
Exploration
GOLD STORE 37
TESOROGOLD.COM.AU
Replaced by GOLD STORE 37A in process
300
Exploration
14
ASX ANNOUNCEMENT 30 OCTOBER 2023
Replaced by GOLD STORE 38A in process
Size
(ha)
300
Concession
type
Exploration
GOLD STORE 39
Replaced by GOLD STORE 39A in process
300
Exploration
GOLD STORE 40
Replaced by GOLD STORE 40A in process
300
Exploration
GOLD STORE 41
Replaced by GOLD STORE 41A in process
300
Exploration
GOLD STORE 42
Replaced by GOLD STORE 42A in process
300
Exploration
GOLD STORE 43
Replaced by GOLD STORE 43A in process
300
Exploration
GOLD STORE 44
Replaced by GOLD STORE 44A in process
300
Exploration
GOLD STORE 45
Replaced by GOLD STORE 45A in process
300
Exploration
GOLD STORE 46
Replaced by GOLD STORE 46A in process
300
Exploration
GOLD STORE 47
Replaced by GOLD STORE 47A in process
300
Exploration
GOLD STORE 48
Replaced by GOLD STORE 48A in process
300
Exploration
GOLD STORE 49
Replaced by GOLD STORE 49A in process
300
Exploration
GOLD STORE 50
Replaced by GOLD STORE 50A in process
300
Exploration
GOLD STORE 51
Replaced by GOLD STORE 51A in process
300
Exploration
GOLD STORE 52
Replaced by GOLD STORE 52A in process
300
Exploration
GOLD STORE 53
Replaced by GOLD STORE 53A in process
300
Exploration
GOLD STORE 54
Replaced by GOLD STORE 54A in process
300
Exploration
GOLD STORE 55
Replaced by GOLD STORE 55A in process
300
Exploration
GOLD STORE 56
Replaced by GOLD STORE 56A in process
200
Exploration
GOLD STORE 57
Replaced by GOLD STORE 57A in process
300
Exploration
GOLD STORE 58
Replaced by GOLD STORE 58A in process
300
Exploration
GOLD STORE 59
Replaced by GOLD STORE 59A in process
300
Exploration
GOLD STORE 60
Replaced by GOLD STORE 60A in process
300
Exploration
GOLD STORE 61
Replaced by GOLD STORE 61A in process
300
Exploration
GOLD STORE 62
Replaced by GOLD STORE 62A in process
300
Exploration
GOLD STORE 63
Replaced by GOLD STORE 63A in process
300
Exploration
GOLD STORE 64
Replaced by GOLD STORE 64A in process
300
Exploration
GOLD STORE 65
Replaced by GOLD STORE 65A in process
300
Exploration
VACAS FLACAS 1
26-October-2026
300
Exploration
VACAS FLACAS 2
26-October-2026
300
Exploration
VACAS FLACAS 5
26-October-2026
300
Exploration
VACAS FLACAS 6
26-October-2026
300
Exploration
VACAS FLACAS 7
26-October-2026
300
Exploration
VACAS FLACAS 8
26-October-2026
300
Explorati
Share your feedback