Quarterly Activities Report
Released
Released
Announcement PDF
31 Cliff Street, Fremantle WA 6011 | +61 8 6383 7883 | info@tesorogold.com.au | tesorogold.com.au
ASX ANNOUNCEMENT
31 JULY 2026
ASX: TSO OTCQX: TSORF FSE: 5D7
QUARTERLY ACTIVITIES REPORT
FOR THE PERIOD ENDED 30 JUNE 2026
Tesoro Gold Limited (ASX: TSO, OTCQX: TSORF, FSE: 5D7) (Tesoro or the Company) is pleased to report
on its activities for the quarter ended 30 June 2026 (the Quarter).
During the Quarter, Tesoro materially advanced the development of its El Zorro Gold Project in Chile
(El Zorro, or the Project), progressing Definitive Feasibility Study (DFS) workstreams and associated
technical programmes in parallel with resource definition drilling at the Ternera Gold Deposit
(Ternera) and preparations for near-deposit growth and district-scale discovery drilling.
HIGHLIGHTS FROM THE QUARTER
Exploration and Drilling
• Completed all metallurgical testwork drill holes and materially advanced open-pit
geotechnical drilling and associated DFS technical workstreams.
• Resource-definition drilling continued to return wide, high-grade gold intercepts, including:
66.30m @ 1.71g/t Au from 375.00m (ZDDH0436) including:
23.30m @ 3.77g/t Au from 375.70m, and 8.50m @ 6.08g/t Au from 389.50m
62.28m @ 1.35g/t Au from 374.00m (ZDDH0430) including:
10.00m @ 2.68g/t Au from 374.00m, and 7.00m @ 4.97g/t Au from 403.00m
• The Ternera infill drilling programme was nearing completion at Quarter end, with the
additional drill density intended to support an updated Mineral Resource Estimate (MRE),
maiden Ore Reserve and DFS-level mine planning.
• Subsequent to Quarter end, Tesoro confirmed completion of the infill drilling programme and
the transition of drilling activities to Ternera expansion and regional discovery targets.
El Zorro Gold Project Advancement
• All core DFS workstreams materially advanced across mining, processing, tailings,
infrastructure, permitting, financing and execution planning.
• Non-binding strategic alliance framework executed with STRACON Chile SpA.1
• Appointed GR Engineering Services and Knight Piésold to key DFS engineering scopes.1
• Appointed BurnVoir Corporate Finance Limited as financial adviser; and expanded its in-
country team and operating presence in Chile.1
• Environmental baseline studies approximately 75% complete ahead of August 2026
completion in preparation for next-stage Project permitting activities.1
• The updated Ternera MRE, maiden Ore Reserve and DFS are due during the second half of
CY2026, with the DFS planned for completion by the end of CY2026.
1 Announced on 1 July 2026, post Quarter end.
Tesoro Gold 2
ASX ANNOUNCEMENT
31 JULY 2026
Corporate
• Completed the Unmarketable Parcel Share Sale Facility (SSF) launched on 19 January 2026.
• Strong balance sheet and existing work programmes fully funded with A$15.29 million in cash
and cash equivalents and zero debt as at 30 June 2026. 2
Tesoro Managing Director, Zeff Reeves, commented:
“We’ve made substantial progress during the June quarter across the technical programmes
required to advance El Zorro towards development. Resource-definition drilling at Ternera was
completed post Quarter end, metallurgical and geotechnical programmes progressed, and the
broader DFS continued to advance across mining, processing, infrastructure, permitting, financing
and execution planning.
Following Quarter end, we further strengthened the Project execution platform through additional
in-country capability. We launched our permanent Chilean office and engaged additional specialist
advisers and contractors tasked with bringing El Zorro to life. The alliance framework with STRACON,
together with the appointments of GRES, Knight Piésold and BurnVoir, provides experienced support
across key areas of project delivery and financing.
Our drilling focus has now moved to Ternera expansion and regional discovery targets. This next
phase is designed to pursue further Mineral Resource growth around Ternera while testing the
broader discovery potential across the massive and under-explored El Zorro Gold District.
With an updated MRE and maiden Ore Reserve targeted in the near-term, and the DFS on track for
completion by the end of CY2026, we enter the second half of the year with a clearly defined
programme and a strong set of deliverables.”
2 The Company held an A$8.03 million term deposit that had previously been classified as an investment because its maturity exceeded three
months. The term deposit matured on 5 June 2026.
Tesoro Gold 3
ASX ANNOUNCEMENT
31 JULY 2026
Figure 1: El Zorro Gold Project Location Relative to Major Infrastructure, Towns and Operations.
Tesoro Gold 4
ASX ANNOUNCEMENT
31 JULY 2026
EXPLORATION AND DRILLING: 2025-2026 DIAMOND DRILLING PROGRAMME
Infill Drilling Programme
During the Quarter, Tesoro progressed the resource-definition component of its fully funded 38,000m
diamond drilling programme, with six diamond drill rigs operating at Ternera, completing infill and
geotechnical drilling to increase drill density, enable an upgrade to Resource classification and
provide inputs for the updated Mineral Resource Estimate (MRE), maiden Ore Reserve and DFS-level
mine planning.
On 1 July 2026, subsequent to Quarter end, Tesoro confirmed the infill drilling programme was
complete.
Notable results returned during the Quarter included:
• 66.30m @ 1.71g/t Au from 375.00m (ZDDH0436) including:
23.30m @ 3.77g/t Au from 375.70m, and
8.50m @ 6.08g/t Au from 389.50m
• 62.28m @ 1.35g/t Au from 374.00m (ZDDH0430) including:
10.00m @ 2.68g/t Au from 374.00m, and
7.00m @ 4.97g/t Au from 403.00m
• 93.00m @ 1.21g/t Au from 572.00m (ZDDH0440) including:
18.00m @ 2.96g/t Au from 495.00m, and
4.00m @ 6.73g/t Au from 511.00m
• 35.00m @ 1.20g/t Au from 533.00m (ZDDH0440A) including:
4.00m @ 5.16g/t Au from 537.00m
• 137.72m @ 0.67g/t Au from 331.73m (ZDDH0455) including:
12.62m @ 4.70g/t Au from 364.38m, and
5.77m @ 10.27g/t Au from 370.50m
• 17.20m @ 1.53g/t Au from 387.00m (ZDDH0456) including:
5.95m @ 3.35g/t Au from 395.05m
Growth and New Discovery Drilling
Completion of infill and geotechnical drilling enabled diamond drilling rigs to be redeployed to
Ternera expansion and regional discovery drilling. Primary targets include Ternera East, Drone Hill and
extensions to the north and south of Ternera (see Figure 2). A second phase of drilling will be
undertaken at the La Brea and Pena Blanca district targets (see Figure 3).
Tesoro Gold 5
ASX ANNOUNCEMENT
31 JULY 2026
Figure 2: El Zorro Gold Project Near Deposit Targets. For further drill hole information refer to Tesoro ASX release dated 22 October 2025,
Tesoro ASX release dated 22 March 2025, Tesoro ASX release dated 28 October 2024, Tesoro ASX release dated 2 July 2024, Tesoro ASX release
dated 13 June 2024, Tesoro ASX release dated 1 December 2022, Tesoro ASX release dated 8 November 2022, Tesoro ASX release dated
3 November 2021, Tesoro ASX release dated 27 August 2021, Tesoro ASX release dated 6 July 2021, and Tesoro ASX release dated 25 June 2021.
Tesoro Gold 6
ASX ANNOUNCEMENT
31 JULY 2026
Figure 3: El Zorro Gold Project District Targets.
Tesoro Gold 7
ASX ANNOUNCEMENT
31 JULY 2026
EL ZORRO GOLD PROJECT ADVANCEMENT AND DEVELOPMENT READINESS
Subsequent to the end of the Quarter, an update on DFS workstreams and development readiness
at El Zorro was released. All core DFS-level activities have now commenced or are materially
advanced across engineering, mining, processing, infrastructure, permitting, financing and
execution planning.
Development team and in-country presence
Tesoro has expanded its development and execution team and established additional in-country
capability, including a new Chile office. The expanded presence is intended to support DFS
coordination, permitting, stakeholder engagement, logistics, consultant management and pre-
construction planning.
STRACON strategic alliance framework
Tesoro Mining Chile SpA signed a non-binding Letter of Intent with STRACON Chile SpA to establish
an alliance-style framework for the development of El Zorro. STRACON will be Tesoro’s preferred
contractor to support pre-construction activities, construction and future operation at the Project.
STRACON is an integrated, engineering-led and technology-enabled mining infrastructure and
services group operating across the Americas. Headquartered in Toronto, Canada, STRACON
provides end-to-end solutions across the mining lifecycle, including engineering and technology
solutions and industrial services.
Processing, tailings and site engineering
GR Engineering Services commenced DFS process design and engineering for the proposed 3.0Mtpa
gold processing plant and associated site infrastructure. The work builds on metallurgical testwork
supporting a conventional carbon-in-pulp flowsheet using project-relevant water sources. The
3.0Mtpa design capacity is an engineering design basis for the DFS and should not be construed as
a production target or forecast.
Knight Piésold was engaged to complete DFS-level engineering and design for a dry-stack tailings
storage facility over the life of the Project, together with geotechnical, civil and site infrastructure
inputs required for DFS capital and operating cost estimates.
Tesoro Gold 8
ASX ANNOUNCEMENT
31 JULY 2026
Figure 4: Proposed El Zorro CIP Flowsheet.
Figure 5: Proposed El Zorro Site Layout.
Power, water and infrastructure
Engineering design and cost estimation for grid power, process water, site layout and associated
infrastructure was materially advanced. Tesoro submitted a connection authorisation request to the
Chilean National Electricity Coordinator for a 21MW electrical connection to El Zorro, supporting the
proposed high-voltage power line from Totoralillo to the Project.
Tesoro Gold 9
ASX ANNOUNCEMENT
31 JULY 2026
Figure 6: Proposed El Zorro Powerline and Water Pipeline Routes.
Financing
BurnVoir Corporate Finance Limited was appointed as financial adviser to support development of
an optimised project funding strategy and to arrange debt facilities for development of El Zorro.
BurnVoir is a leading specialist corporate finance advisory firm with more than 25 years’ experience
and having advised on more than A$20 billion of project financing, capital structuring, and strategic
transactions for mining development companies. Most recently, BurnVoir secured project financing
for ASX-listed gold companies Rox Resources (ASX: RXL) and Brightstar Resources (ASX: BTR).
Environmental studies and permitting
As at 1 July 2026, environmental baseline studies were approximately 75% complete and scheduled
for completion in August 2026.
Following completion of the baseline programme, Tesoro expects to progress the preparation and
submission of environmental impact assessment documentation to the Chilean Environmental
Impact Assessment System in early 2027, with permitting activities to continue through 2027.
UPCOMING ACTIVITIES AND EXPLORATION CATALYSTS3
• Updated MRE for the Ternera Gold Deposit, targeted for August 2026.
3 Target dates and future activities are subject to study outcomes, approvals, funding and other matters described under Future Performance.
Tesoro Gold 10
ASX ANNOUNCEMENT
31 JULY 2026
• Publication of a maiden Ore Reserve scheduled for September 2026.
• Completion of environmental baseline studies, scheduled for August 2026.
• Continued near-deposit expansion drilling at Ternera East, Drone Hill and extensions north and
south of Ternera.
• District-scale new-discovery drilling, including planned testing of La Brea and Pena Blanca.
• Continued DFS engineering across mining, processing, dry-stack tailings, power, water and
site infrastructure.
• Advancement of the project funding strategy and prospective debt facilities with BurnVoir.
• Completion and publication of the El Zorro DFS, scheduled for late CY2026.
• Preparation and submission of environmental impact assessment documentation in early
2027, subject to completion of the supporting studies.
CORPORATE
Unmarketable Parcel
During the Quarter, Tesoro completed the Unmarketable Parcel Sale Facility (SSF) on the terms
announced on 19 January 2026.
The SSF enabled holders of Unmarketable Parcels (defined as a market value of less than A$500) to
sell their shares without incurring brokerage or handling costs that might otherwise make the sale
uneconomic or impractical. A total of 88,779 fully paid ordinary shares were sold on behalf of
512 shareholders at a price of A$0.9414 per share.
Completion of the SSF reduces the Company’s ongoing administrative and operating costs.
Annual General Meeting
The Company held its Annual General Meeting on 29 May 2026. All resolutions put to shareholders
were carried on a poll.
Expenditure and Payments to Related Parties
The Company deployed approximately A$7.13 million on exploration and development activities
during the Quarter, principally comprising DFS work, diamond drilling programmes and exploration
activities.
Payments to related parties and their associates (refer Appendix 5B sections 6.1 and 6.2) totalled
A$201,000 during the Quarter, comprising A$102,000 included in operating activities and A$99,000
included in investing activities. The payments related to remuneration, including superannuation, for
the Managing Director, Executive Director, Non-Executive Director fees and consulting fees.
Tesoro Gold 11
ASX ANNOUNCEMENT
31 JULY 2026
Cash Position
Cash and cash equivalents at 30 June 2026 were reported as A$15.29 million. The Company had no
debt, excluding ordinary-course trade creditors.
The Appendix 5B records that an A$8.03 million term deposit, previously classified as an investment
(due to maturity exceeded three months), matured on 5 June 2026 and was reclassified to cash and
cash equivalents.
Authorised by the Board of Tesoro Gold Ltd.
For more information:
Company
Zeff Reeves
Managing Director
info@tesorogold.com.au
Investor Relations & Media Enquiries
Grace Lauder
Fivemark Partners
Grace.lauder@fivemark.com.au
Follow Us
• Website
• LinkedIn
• X
Tesoro Gold 12
ASX ANNOUNCEMENT
31 JULY 2026
ABOUT TESORO
Tesoro Gold Limited has discovered and defined the first
Intrusive Related Gold System in Chile. The 1.82Moz
Ternera discovery is in the Coastal Cordillera region of
Chile. The Coastal Cordillera region is host to multiple
world-class copper and gold mines, has well established
infrastructure, service providers and an experienced
mining workforce. Large areas of the Coastal Cordillera
remain unexplored due to the unconsolidated nature of
mining concession ownership, but Tesoro, via its in-country
network and experience has been able secure rights to
the district-scale El Zorro gold project in-line with the
Company’s strategy. Tesoro’s 95% owned Chilean
subsidiary owns 95.4% of the El Zorro Gold Project (see ASX
announcement released 12 August 2025).
FUTURE PERFORMANCE
This announcement may contain certain forward-looking
statements and opinions. Forward-looking statements,
including projections, forecasts and estimates, are
provided as a general guide only and should not be relied
on as an indication or guarantee of future performance
and involve known and unknown risks, uncertainties,
assumptions, contingencies and other important factors,
many of which are outside the control of the Company
and which are subject to change without notice and
could cause the actual results, performance or
achievements of the Company to be materially different
from the future results, performance or achievements
expressed or implied by such statements. Past
performance is not necessarily a guide to future
performance, and no representation or warranty is made
as to the likelihood of achievement or reasonableness of
any forward-looking statements or other forecast.
Nothing contained in this announcement, nor any
information made available to you is, or and shall be
relied upon as, a promise, representation, warranty or
guarantee as to the past, present or the future
performance of Tesoro Gold.
COMPETENT PERSONS’ STATEMENT
The information in this report that relates to Mineral
Resources is based on information compiled by Mr Lynn
Widenbar (B.Sc.(Hons) Geology, M.Sc. FAusIMM, MAIG),
a Competent Person who is a Fellow of The Australasian
Institute of Mining and Metallurgy. Mr Widenbar is acting
as an independent consultant to Tesoro Gold Limited. Mr
Widenbar has sufficient experience that is relevant to the
style of mineralisation and type of deposit under
consideration, and to the activity being undertaken to
qualify as a Competent Person as defined in the 2012
Edition of the ‘Australasian Code for Reporting of
Exploration Results, Mineral Resources and Ore Reserves’.
The Company confirms that it is not aware of any new
information or data that materially affects the
information contained the form and context in which the
Competent Person’s findings are presented have not
been materially modified from in the original
announcement on 4 August 2025, and all material
assumptions and technical parameters underpinning the
estimates in that announcement continue to apply and
have not materially changed.
The information in this report that relates to Exploration
Results is based on information compiled by Mr Zeffron
Reeves (B App Sc (Hons) Applied Geology) MBA, MAIG).
Mr Reeves is a member of the Australian Institute of
Geoscientists and a Director and shareholder of the
Company. Mr Reeves has sufficient experience that is
relevant to the style of mineralisation and type of deposit
under consideration and to the activity which he is
undertaking to qualify as a Competent Person as defined
in the 2012 Edition of the Australasian Code for Reporting
of Exploration Results, Mineral Resources and Ore
Reserves. Mr Reeves consents to the inclusion in this report
of the matters based on this information in the form and
context in which it appears.
Tesoro Gold 13
ASX ANNOUNCEMENT
31 JULY 2026
APPENDIX 1: CONCESSION SCHEDULE AS AT 30 JUNE 2026
EL ZORRO GOLD PROJECT CONCESSIONS (95.4% Tesoro Mining Chile SpA)
N° CONCESSION NAME EXPIRATION DATE SIZE (HA) CONCESSION TYPE
1 ZORRO 1B 10/Aug/2026 200 Exploration
2 ZORRO 2B 10/Aug/2026 200 Exploration
3 ZORRO 3B 10/Aug/2026 200 Exploration
4 ZORRO 4B 10/Aug/2026 100 Exploration
5 ZORRO 5B 10/Aug/2026 200 Exploration
6 ZORRO 6B 10/Aug/2026 200 Exploration
7 GOLD STORE 72A 21/Sep/2026 300 Exploration
8 GOLD STORE 71A 21/Sep/2026 300 Exploration
9 GOLD STORE 70A 21/Sep/2026 300 Exploration
10 GOLD STORE 69A 21/Sep/2026 300 Exploration
11 GOLD STORE 68A 21/Sep/2026 300 Exploration
12 GOLD STORE 67A 21/Sep/2026 300 Exploration
13 GOLD STORE 66A 27/Sep/2026 300 Exploration
14 BLOODY GOOD SHOT 13B 27/Sep/2026 200 Exploration
15 BLOODY GOOD SHOT 12B 27/Sep/2026 200 Exploration
16 BLOODY GOOD SHOT 11B 27/Sep/2026 200 Exploration
17 BLOODY GOOD SHOT 10B 27/Sep/2026 300 Exploration
18 BLOODY GOOD SHOT 9B 28/Sep/2026 300 Exploration
19 BLOODY GOOD SHOT 8B 5/Oct/2026 200 Exploration
20 BLOODY GOOD SHOT 7B 28/Sep/2026 100 Exploration
21 BLOODY GOOD SHOT 6B 5/Oct/2026 200 Exploration
22 BLOODY GOOD SHOT 5B 29/Sep/2026 200 Exploration
23 BLOODY GOOD SHOT 4B 29/Sep/2026 300 Exploration
24 BLOODY GOOD SHOT 3B 3/Oct/2026 300 Exploration
25 BLOODY GOOD SHOT 2B 3/Oct/2026 300 Exploration
26 BLOODY GOOD SHOT 1B 3/Oct/2026 300 Exploration
27 SIERRA PATACONES 42A 24/Oct/2026 300 Exploration
28 SIERRA PATACONES 41A 24/Oct/2026 300 Exploration
29 SIERRA PATACONES 40A 25/Oct/2026 300 Exploration
30 SIERRA PATACONES 39A 25/Oct/2026 300 Exploration
31 SIERRA PATACONES 38A 25/Oct/2026 300 Exploration
32 SIERRA PATACONES 35A 25/Oct/2026 300 Exploration
33 SIERRA PATACONES 34A 25/Oct/2026 300 Exploration
34 SIERRA PATACONES 33A 25/Oct/2026 300 Exploration
35 SIERRA PATACONES 32A 25/Oct/2026 300 Exploration
36 SIERRA PATACONES 31A 25/Oct/2026 300 Exploration
37 SIERRA PATACONES 29A 25/Oct/2026 300 Exploration
38 SIERRA PATACONES 28A 25/Oct/2026 300 Exploration
39 SIERRA PATACONES 27A 25/Oct/2026 300 Exploration
Tesoro Gold 14
ASX ANNOUNCEMENT
31 JULY 2026
N° CONCESSION NAME EXPIRATION DATE SIZE (HA) CONCESSION TYPE
40 SIERRA PATACONES 26A 25/Oct/2026 300 Exploration
41 SIERRA PATACONES 25A 25/Oct/2026 300 Exploration
42 SIERRA PATACONES 24A 25/Oct/2026 300 Exploration
43 SIERRA PATACONES 23A 25/Oct/2026 300 Exploration
44 SIERRA PATACONES 21A 26/Oct/2026 300 Exploration
45 SIERRA PATACONES 20A 24/Oct/2026 300 Exploration
46 SIERRA PATACONES 19A 20/Oct/2026 300 Exploration
47 SIERRA PATACONES 18A 24/Oct/2026 300 Exploration
48 SIERRA PATACONES 17A 24/Oct/2026 300 Exploration
49 SIERRA PATACONES 16A 24/Oct/2026 300 Exploration
50 SIERRA PATACONES 14A 24/Oct/2026 300 Exploration
51 SIERRA PATACONES 13A 24/Oct/2026 300 Exploration
52 VACAS FLACAS 28A 26/Oct/2026 300 Exploration
53 VACAS FLACAS 27A 26/Oct/2026 300 Exploration
54 SIERRA PATACONES 2A 28/Oct/2026 300 Exploration
55 SIERRA PATACONES 3A 28/Oct/2026 300 Exploration
56 SIERRA PATACONES 4A 28/Oct/2026 300 Exploration
57 SIERRA PATACONES 5A 28/Oct/2026 300 Exploration
58 SIERRA PATACONES 6A 4/Nov/2026 300 Exploration
59 SIERRA PATACONES 7A 4/Nov/2026 300 Exploration
60 SIERRA PATACONES 9A 4/Nov/2026 300 Exploration
61 SIERRA PATACONES 10A 4/Nov/2026 300 Exploration
62 SIERRA PATACONES 11A 4/Nov/2026 300 Exploration
63 SIERRA PATACONES 12A 24/Nov/2026 300 Exploration
64 SIERRA PATACONES 45A 24/Nov/2026 300 Exploration
65 SIERRA PATACONES 46A 24/Nov/2026 300 Exploration
66 SIERRA PATACONES 47A 24/Nov/2026 300 Exploration
67 SIERRA PATACONES 48A 24/Nov/2026 300 Exploration
68 SIERRA PATACONES 51A 24/Nov/2026 300 Exploration
69 SIERRA PATACONES 52A 24/Nov/2026 300 Exploration
70 SIERRA PATACONES 55A 24/Nov/2026 300 Exploration
71 SIERRA PATACONES 56A 24/Nov/2026 300 Exploration
72 SIERRA PATACONES 60A 28/Oct/2026 300 Exploration
73 GOLD STORE 13A 22/Sep/2026 300 Exploration
74 GOLD STORE 12A 21/Sep/2026 300 Exploration
75 GOLD STORE 9A 22/Sep/2026 300 Exploration
76 GOLD STORE 7A 21/Sep/2026 300 Exploration
77 GOLD STORE 5A 21/Sep/2026 300 Exploration
78 GOLD STORE 4A 21/Sep/2026 300 Exploration
79 GOLD STORE 3A 21/Sep/2026 300 Exploration
80 GOLD STORE 2A 21/Sep/2026 300 Exploration
81 GOLD STORE 1A 21/Sep/2026 300 Exploration
Tesoro Gold 15
ASX ANNOUNCEMENT
31 JULY 2026
N° CONCESSION NAME EXPIRATION DATE SIZE (HA) CONCESSION TYPE
82 GOLD STORE 21A 21/Sep/2026 300 Exploration
83 GOLD STORE 19A 21/Sep/2026 300 Exploration
84 GOLD STORE 18A 21/Sep/2026 300 Exploration
85 GOLD STORE 17A 21/Sep/2026 300 Exploration
86 GOLD STORE 16A 21/Sep/2026 300 Exploration
87 GOLD STORE 8A 22/Sep/2026 300 Exploration
88 GOLD STORE 65A 18/Nov/2026 300 Exploration
89 GOLD STORE 64A 18/Nov/2026 300 Exploration
90 GOLD STORE 63A 18/Nov/2026 300 Exploration
91 GOLD STORE 62A 18/Nov/2026 300 Exploration
92 GOLD STORE 61A 18/Nov/2026 300 Exploration
93 GOLD STORE 60A 18/Nov/2026 300 Exploration
94 GOLD STORE 59A 21/Nov/2026 300 Exploration
95 GOLD STORE 58A 21/Nov/2026 300 Exploration
96 GOLD STORE 57A 21/Nov/2026 300 Exploration
97 GOLD STORE 56A 21/Nov/2026 200 Exploration
98 GOLD STORE 55A 21/Nov/2026 300 Exploration
99 GOLD STORE 54A 21/Nov/2026 300 Exploration
100 GOLD STORE 53A 21/Nov/2026 300 Exploration
101 GOLD STORE 52A 16/Nov/2026 300 Exploration
102 GOLD STORE 51A 14/Nov/2026 300 Exploration
103 GOLD STORE 50A 14/Nov/2026 300 Exploration
104 GOLD STORE 49A 14/Nov/2026 300 Exploration
105 GOLD STORE 48A 18/Nov/2026 300 Exploration
106 GOLD STORE 47A 4/Nov/2026 300 Exploration
107 GOLD STORE 46A 4/Nov/2026 300 Exploration
108 GOLD STORE 45A 4/Nov/2026 300 Exploration
109 GOLD STORE 44A 4/Nov/2026 300 Exploration
110 GOLD STORE 43A 4/Nov/2026 300 Exploration
111 GOLD STORE 42A 4/Nov/2026 300 Exploration
112 GOLD STORE 41A 4/Nov/2026 300 Exploration
113 GOLD STORE 40A 4/Nov/2026 300 Exploration
114 SIERRA PATACONES 61A 29/Nov/2026 300 Exploration
115 SIERRA PATACONES 62A 29/Nov/2026 300 Exploration
116 SIERRA PATACONES 63A 29/Nov/2026 300 Exploration
117 SIERRA PATACONES 67A 29/Nov/2026 300 Exploration
118 SIERRA PATACONES 71A 29/Nov/2026 300 Exploration
119 SIERRA PATACONES 76A 29/Nov/2026 300 Exploration
120 POTRERO 1 7/Dec/2026 300 Exploration
121 POTRERO 2 7/Dec/2026 300 Exploration
122 POTRERO 3 2/Dec/2026 300 Exploration
123 POTRERO 4 2/Dec/2026 300 Exploration
Tesoro Gold 16
ASX ANNOUNCEMENT
31 JULY 2026
N° CONCESSION NAME EXPIRATION DATE SIZE (HA) CONCESSION TYPE
124 POTRERO 5 2/Dec/2026 300 Exploration
125 POTRERO 6 6/Dec/2026 300 Exploration
126 POTRERO 7 6/Dec/2026 300 Exploration
127 POTRERO 9 9/Dec/2026 300 Exploration
128 POTRERO 12 5/Dec/2026 300 Exploration
129 POTRERO 23 6/Dec/2026 300 Exploration
130 POTRERO 24 6/Dec/2026 300 Exploration
131 POTRERO 25 6/Dec/2026 300 Exploration
132 POTRERO 26 6/Dec/2026 200 Exploration
133 POTRERO 27 6/Dec/2026 300 Exploration
134 POTRERO 29 6/Dec/2026 300 Exploration
135 POTRERO 67 16/Mar/2027 300 Exploration
136 POTRERO 68 16/Mar/2027 300 Exploration
137 POTRERO 69 16/Mar/2027 300 Exploration
138 POTRERO 70 16/Mar/2027 300 Exploration
139 POTRERO 71 16/Mar/2027 300 Exploration
140 POTRERO 72 16/Mar/2027 300 Exploration
141 POTRERO 73 14/Mar/2027 300 Exploration
142 POTRERO 77 14/Mar/2027 100 Exploration
143 POTRERO 78 14/Mar/2027 100 Exploration
144 POTRERO 32 26/Apr/2027 200 Exploration
145 POTRERO 33 19/Apr/2027 200 Exploration
146 POTRERO 34 26/Apr/2027 300 Exploration
147 POTRERO 37 19/Apr/2027 300 Exploration
148 POTRERO 40 26/Apr/2027 300 Exploration
149 POTRERO 41 19/Apr/2027 300 Exploration
150 POTRERO 42 21/Apr/2027 200 Exploration
151 POTRERO 43 18/Apr/2027 200 Exploration
152 POTRERO 50 21/Apr/2027 300 Exploration
153 POTRERO 53 19/Apr/2027 300 Exploration
154 POTRERO 58 21/Apr/2027 300 Exploration
155 PUNTA DE DIAMANTE 3B 6/Sep/2027 300 Exploration
156 PUNTA DE DIAMANTE 2B 6/Sep/2027 300 Exploration
157 PUNTA DE DIAMANTE 1B 6/Sep/2027 200 Exploration
158 LA NEGRA COJA 19B 5/Sep/2027 200 Exploration
159 LA NEGRA COJA 18B 5/Sep/2027 300 Exploration
160 LA NEGRA COJA 17B 5/Sep/2027 300 Exploration
161 LA NEGRA COJA 15B 5/Sep/2027 300 Exploration
162 LA NEGRA COJA 14B 5/Sep/2027 300 Exploration
163 LA NEGRA COJA 13B 5/Sep/2027 300 Exploration
164 LA NEGRA COJA 12B 5/Sep/2027 200 Exploration
165 LA NEGRA COJA 11B 5/Sep/2027 300 Exploration
Tesoro Gold 17
ASX ANNOUNCEMENT
31 JULY 2026
N° CONCESSION NAME EXPIRATION DATE SIZE (HA) CONCESSION TYPE
166 LA NEGRA COJA 8B 5/Sep/2027 300 Exploration
167 LA NEGRA COJA 7B 6/Sep/2027 300 Exploration
168 LA NEGRA COJA 6B 6/Sep/2027 200 Exploration
169 LA NEGRA COJA 5B 6/Sep/2027 300 Exploration
170 LA NEGRA COJA 4B 6/Sep/2027 200 Exploration
171 LA NEGRA COJA 3B 6/Sep/2027 300 Exploration
172 LA NEGRA COJA 2B 6/Sep/2027 300 Exploration
173 LA NEGRA COJA 1B 6/Sep/2027 200 Exploration
174 Buzzard 1, 1 al 300 N/A Constituted 300 Exploitation
175 Buzzard 2, 1 al 300 N/A Constituted 300 Exploitation
176 Buzzard 3, 1 al 300 N/A Constituted 300 Exploitation
177 Buzzard 4, 1 al 300 N/A Constituted 300 Exploitation
178 LEON DOS 1-30 N/A Constituted 300 Exploitation
179 LEON UNO 1-30 N/A Constituted 300 Exploitation
180 LAS COQUETAS 1/10 N/A Constituted 100 Exploitation
181 PATON DOS 1/29 N/A Constituted 230 Exploitation
182 PATON UNO 1/29 N/A Constituted 240 Exploitation
183 CALDERILLA 1, 1 AL 10 N/A Constituted 100 Exploitation
184 CALDERILLA 2, 1 AL 10 N/A Constituted 100 Exploitation
185 CALDERILLA 3, 1 AL 10 N/A Constituted 100 Exploitation
186 CALDERILLA 4, 1 AL 10 N/A Constituted 100 Exploitation
187 CALDERILLA 5, 1 AL 10 N/A Constituted 100 Exploitation
188 CALDERILLA 6, 1 AL 10 N/A Constituted 100 Exploitation
189 CALDERILLA 7, 1 AL 10 N/A Constituted 100 Exploitation
190 CALDERILLA 8, 1 AL 10 N/A Constituted 100 Exploitation
191 CALDERILLA 9, 1 AL 10 N/A Constituted 100 Exploitation
192 CALDERILLA 10, 1 AL 10 N/A Constituted 100 Exploitation
193 CALDERILLA 11, 1 AL 10 N/A Constituted 100 Exploitation
194 CALDERILLA 12, 1 AL 10 N/A Constituted 100 Exploitation
195 CALDERILLA 13, 1 AL 10 N/A Constituted 100 Exploitation
196 CALDERILLA 14, 1 AL 10 N/A Constituted 100 Exploitation
197 CALDERILLA 15, 1 AL 10 N/A Constituted 100 Exploitation
198 CALDERILLA 16, 1 AL 10 N/A Constituted 100 Exploitation
199 CALDERILLA 17, 1 AL 10 N/A Constituted 76 Exploitation
200 CALDERILLA 18, 1 AL 10 N/A Constituted 36 Exploitation
201 CALDERILLA 19, 1 AL 10 N/A Constituted 100 Exploitation
202 CALDERILLA 20, 1 AL 10 N/A Constituted 91 Exploitation
203 CALDERILLA 21, 1 AL 10 N/A Constituted 76 Exploitation
204 CALDERILLA 22, 1 AL 10 N/A Constituted 100 Exploitation
205 CALDERILLA 23, 1 AL 10 N/A Constituted 100 Exploitation
206 TAKEO SEGUNDA 1 AL 20 N/A Constituted 100 Exploitation
207 TAKEO TERCERA 1 AL 20 N/A Constituted 100 Exploitation
Tesoro Gold 18
ASX ANNOUNCEMENT
31 JULY 2026
Notes:
1. Concessions 1 to 134 are those exploration concessions that are expiring this year. They are already under a
renewal process for a further term of up to four years and there is no legal impediment to the extension being
granted.
2. Constituted exploitation concessions have no expiry.