Tesoro Gold to advance Ternera to Definitive Feasibility
Released
Released
Announcement PDF
Tesoro Gold 1
ASX ANNOUNCEMENT
25 FEBRUARY 2026
ASX: TSO OTCQB: TSORF FSE: 5D7
TESORO GOLD TO ADVANCE THE TERNERA GOLD
PROJECT TO DEFINITIVE FEASIBILITY
Tesoro Gold Limited (Tesoro or the Company) (ASX: TSO, OTCQB: TSORF, FSE: 5D7) is pleased to advise
that, following completion of comprehensive technical trade off studies, the Company has decided
to progress directly to a Definitive Feasibility Study (DFS) for the 1.82 Moz Ternera Gold Deposit
(Ternera) at its El Zorro Gold Project in Chile (El Zorro, or the Project).
This decision reflects the level of technical definition achieved across critical engineering disciplines,
the conventional nature of the project and the Board’s assessment that the Project has reached a
stage of maturity appropriate for DFS-level evaluation.
PROJECT ADVANCEMENT HIGHLIGHTS
• Detailed programme of Project trade-off studies completed;
• Project at an advanced stage of technical maturity;
• Decision taken to advance directly to DFS, targeting delivery by end of CY2026;
• Deliberate strategy to advance critical technical workstreams in parallel preserving schedule
flexibility;
• DFS acceleration reflects disciplined and efficient capital allocation;
• Multiple DFS level workstreams complete or materially advanced;
• Permitting activities well advanced, with baseline studies 50% complete; and
• Project finance discussions ongoing.
NEW DISCOVERY AND INFILL DRILLING IS ONGOING
• 38,000m of diamond drilling scheduled as part of the current campaign; and
• Infill drilling >50% complete, updated Mineral Resource Estimate scheduled for Q2 2026 to
support the final DFS mine plan and initial Ore Reserve for Ternera.
Tesoro Managing Director, Zeff Reeves, commented:
“We are pleased to provide an update on the continued advancement of development activities at the
Ternera Gold Deposit. Since completion of the 2025 Scoping Study, substantial technical work has been
undertaken, enabling the Board to take the decision to progress directly to Definitive Feasibility Study.
“The completion of targeted trade-off studies has defined a clear, optimised development pathway
centred on a simple single open pit mining operation and a 3Mtpa processing plant, capable of delivering
over 110koz per annum of gold. Advancing directly to DFS is expected to shorten the overall development
timeline while maintaining technical rigour, positioning Ternera for a Final Investment Decision by the end
of CY2026.”
Tesoro Gold 2
ASX ANNOUNCEMENT
25 FEBRUARY 2026
Production target: The production target referred to in this announcement is based on a combination of
Indicated and Inferred Mineral Resources. There is a low level of geological confidence associated with
Inferred Mineral Resources and there is no certainty that further exploration work will result in the
determination of Indicated Mineral Resources or that the production target itself will be realised.
The Scoping Study is based on lower-level technical and economic assessments and is insufficient to
support estimation of Ore Reserves or to provide assurance of economic development.
DIRECT DFS ADVANCEMENT RATIONALE
Since completion of the 2025 Scoping Study (refer ASX announcement dated 11 September 2025),
Project activities have focused on defining the optimal configuration for a single open pit mine and
3Mtpa processing plant at Ternera.
A structured programme of trade-off studies has been completed by specialist consultants across
the principal technical aspects of the Project, including:
• Final process flowsheet selection and process design optimisation (see Appendix 1);
• Site layout, including confirmation of preferred power and water infrastructure corridors
(Figure 1);
• Evaluation and selection of tailing disposal method, including preferred dry stack options;
• Seismic risk assessment and associated structural design parameters; and
• Integration of major infrastructure and the mine interfaces.
These studies have determined the primary development alternatives typically addressed at Pre-
Feasibility (PFS) stage and materially reduced configuration risk. Outcomes have enabled Tesoro to
define a preferred project development pathway with sufficient engineering confidence to proceed
directly to DFS.
The Board considers that completing a PFS would not enhance project definition and that advancing
directly to DFS represents both a disciplined and efficient allocation of capital and resources.
DFS WORKSTREAMS UNDERWAY
Multiple DFS work programmes are currently well advanced, with critical engineering, mining and
infrastructure activities progressing in parallel to support delivery of the DFS and taking a Final
Investment Decision (FID) by the end of 2026.
Key DFS workstreams include:
• Additional metallurgical drilling and sampling to confirm the physical characteristics of the
ore from the Ternera pit and complete variability test work;
• Geotechnical drilling to finalise pit wall design parameters and slope stability assumptions;
• Detailed mining studies, with a South American mining contractor engaged to provide DFS-
level mine design, production schedules and cost estimates;
• Engineering design, scheduling and costing of power and water supply infrastructure;
• Civil engineering design for all site infrastructure;
Tesoro Gold 3
ASX ANNOUNCEMENT
25 FEBRUARY 2026
• Vendor quotations for the accommodation village, explosives storage facilities and onsite
assay laboratory;
• Key process equipment selection and vendor engagement;
• Design work for a dry stack tailings storage facility; and
• Identification and engagement with suppliers for Long Lead Items.
The level of definition across these workstreams is consistent with DFS standards, including capital
cost estimation, operating cost modelling, equipment specification and construction scheduling.
ENVIRONMENTAL AND PERMITTING PROGRESS
Permitting activities are advancing concurrently with technical workstreams. As announced on 22
April 2025, Tesoro commenced preparation for an Environmental Impact Study (EIA) to secure
Environmental Qualification (RCA) and the associated Sectorial Permits (PAS) required for
construction and operation of a gold mine at El Zorro.
Following initial environmental desktop assessments, baseline field studies commenced in August
2025. These programmes are now well advanced and are scheduled for completion in August 2026.
Completion of the baseline data collection will support preparation and submission of the EIA
documentation to the Chilean Environmental Impact Assessment System.
The EIA review process will continue into 2027.
Undertaking environmental baseline work in parallel with DFS engineering ensures that project design
parameters are aligned with permitting requirements and supports an integrated and coherent
development schedule.
DEVELOPMENT PATHWAY AND FUNDING
The decision to advance directly to DFS shortens the overall study timeline while maintaining
technical discipline. Major Project value drivers have been materially de-risked as part of the trade-
off analysis.
The Company is targeting:
• Completion of the DFS by the end of CY2026;
• Final Investment Decision following DFS completion; and
• Continued advancement of permitting through the EIA process in 2027.
The Board considers that direct progression to DFS reflects the maturity of the Ternera Gold Deposit,
the substantial engineering work already completed and the Company’s confidence in the defined
development pathway.
Further updates will be provided as DFS workstreams advance and key milestones are achieved.
Tesoro Gold 4
ASX ANNOUNCEMENT
25 FEBRUARY 2026
Figure 1: El Zorro Gold Project – Ternera Gold Deposit Estimated Development and Construction Schedule through
to first gold.
Figure 2: El Zorro Gold Project – Ternera Gold Deposit Proposed site layout.
Tesoro Gold 5
ASX ANNOUNCEMENT
25 FEBRUARY 2026
Table 1: El Zorro Gold project supporting consultants and service providers
Study Input Contributor
Study Compilation Tesoro, GRES
Geology Tesoro
Resource Estimation Lynn Widenbar and Associates
Geotechnical Peter O’Bryan and Associates
Mining Studies Tesoro, Stracon
Mining Costs Tesoro, Stracon
Metallurgical Test Work GRES, ALS Perth
Process Engineering and Design GRES
Operating Costs Tesoro, GRES, Stracon, Others
Infrastructure
Tesoro, Aguas CAP, TECNOCAP,
Servicios de Ingeniería IMA S.A.
Capital Costs
Tesoro, GRES, Aguas CAP,
TECNOCAP.
Environmental, Social and Permitting Tesoro, Parez & Alverez
Financial Modelling Tesoro
Table 2: Ternera Mineral Estimates for selected cut-off grades. Highlighted open pit Mineral Resource has been
constrained by an optimised pit shell using a gold price of US$3000/oz and process recovery of 94.5%. The
estimates in this table are rounded to reflect their precision; rounding errors are apparent.
Tenera Updated MRE Indicated Inferred Total
Au g/t cut-off Mt Au g/t Koz Mt Au g/t Koz Mt Au g/t Koz
Optimised Open Pit at 0.30 31.8 1.10 1,123 19.5 1.11 692 51.2 1.1 1,816
2.00 3.5 3.55 394 2.5 3.54 280 5.9 3.54 673
1.00 10.5 2.08 705 7.9 2.04 520 18.5 2.06 1,225
0.70 17.5 1.58 891 13 1.57 657 30.5 1.58 1,547
0.30 31.8 1.10 1,128 26.1 1.03 863 58.1 1.07 1,992
0.20 33.8 1.05 1,144 28.7 0.96 885 62.5 1.01 2,028
Refer ASX announcement dated 4 August 2025
Authorised by the Board of Tesoro Gold Ltd.
For more information:
Company:
Zeff Reeves, Managing Director
Tesoro Gold Limited
info@tesorogold.com.au
Tesoro Gold 6
ASX ANNOUNCEMENT
25 FEBRUARY 2026
About Tesoro
Tesoro Gold Limited has discovered and defined the
first Intrusive Related Gold System in Chile. The 1.82M
oz Ternera discovery is in the Coastal Cordillera region
of Chile. The Coastal Cordillera region is host to
multiple world-class copper and gold mines, has well
established infrastructure, service providers and an
experienced mining workforce. Large areas of the
Coastal Cordillera remain unexplored due to the
unconsolidated nature of mining concession
ownership, but Tesoro, via its in-country network and
experience has been able secure rights to the district-
scale El Zorro gold project in-line with the Company’s
strategy. Tesoro’s 95% owned Chilean subsidiary owns
95.4% of the El Zorro Gold Project (see ASX
announcement released 12 August 2025).
Future Performance
This announcement may contain certain forward-looking
statements and opinions. Forward-looking statements,
including projections, forecasts and estimates, are provided as
a general guide only and should not be relied on as an
indication or guarantee of future performance and involve
known and unknown risks, uncertainties, assumptions,
contingencies and other important factors, many of which are
outside the control of the Company and which are subject to
change without notice and could cause the actual results,
performance or achievements of the Company to be
materially different from the future results, performance or
achievements expressed or implied by such statements. Past
performance is not necessarily a guide to future performance,
and no representation or warranty is made as to the likelihood
of achievement or reasonableness of any forward-looking
statements or other forecast.
Nothing contained in this announcement, nor any information
made available to you is, or and shall be relied upon as, a
promise, representation, warranty or guarantee as to the past,
present or the future performance of Tesoro Gold.
Competent Persons Statements
The information in this report that relates to Mineral Resources
is based on information compiled by Mr Lynn Widenbar (B.Sc.
(Hons) Geology, M.Sc. FAusIMM, MAIG), a Competent Person
who is a Fellow of The Australasian Institute of Mining and
Metallurgy. Mr Widenbar is acting as an independent
consultant to Tesoro Gold Limited. Mr Widenbar has sufficient
experience that is relevant to the style of mineralisation and
type of deposit under consideration, and to the activity being
undertaken to qualify as a Competent Person as defined in the
2012 Edition of the ‘Australasian Code for Reporting of
Exploration Results, Mineral Resources and Ore Reserves’. The
Company confirms that it is not aware of any new information
or data that materially affects the information contained the
form and context in which the Competent Person’s findings
are presented have not been materially modified from in the
original announcement on 4 August 2025, and all material
assumptions and technical parameters underpinning the
estimates in that announcement continue to apply and have
not materially changed.
The information in this report that relates to the Production
Target, assumptions on Modifying Factors and evaluation of
other relevant factors are based on and fairly represents
information and supporting documentation that has been
compiled for this announcement and have been compiled
under the supervision of Mr Linton Putland BEng (Mining), MSc
(Mineral Economics) & Member AusIMM. Mr Putland is a
Director of the Company. Mr Putland is a Competent Person
as defined in the 2012 Edition of the Australasian Code for
Reporting of Exploration Results, Mineral Resources and Ore
Reserves (JORC Code 2012). The Company confirms that all
material assumptions underpinning the production target and
forecast financial information derived from the Scoping Study
released on 11 September 2025 continue to apply and have
not materially changed.
The information in this report that relates to Exploration Results
is based on information compiled by Mr Zeffron Reeves (B App
Sc (Hons) Applied Geology) MBA, MAIG). Mr Reeves is a
member of the Australian Institute of Geoscientists and a
Director and shareholder of the Company. Mr Reeves has
sufficient experience that is relevant to the style of
mineralisation and type of deposit under consideration and to
the activity which he is undertaking to qualify as a Competent
Person as defined in the 2012 Edition of the Australasian Code
for Reporting of Exploration Results, Mineral Resources and Ore
Reserves. Mr Reeves consents to the inclusion in this report of
the matters based on this information in the form and context
in which it appears.
APPENDIX 1 – PRELIMINARY EL ZORRO PROCESS PLANT FLOWSHEET