ASX ANNOUNCEMENT
30 October 2026
ASX: TSO OTCQX: TSORF FSE: 5D7
31 Cliff Street, Fremantle WA 6011 | +61 8 6383 7883 | info@tesorogold.com.au | tesorogold.com.au
QUARTERLY ACTIVITIES REPORT
for the period ended 30 September 2026
Tesoro Gold Limited (Tesoro or the Company) (ASX: TSO, OTCQX: TSORF, FSE: 5D7) is pleased
to report on activities for the three months ended 30 September 2026 (Quarter).
Tesoro’s September Quarter culminated in delivery of major milestones at the El Zorro Gold Project
(El Zorro or the Project), with completion of the Ternera resource-definition drilling programme
enabling a material increase in confidence level of the Project’s Mineral Resource Estimate (MRE)
and subsequent declaration of a maiden 1.28Moz Ore Reserve1
for the Ternera Gold Deposit
(Ternera).
The updated MRE increased the Measured and Indicated component to approximately 1.47Moz of
gold, representing approximately 80% of total contained gold within the pit-constrained MRE,
providing the higher-confidence Mineral Resource base required to support the subsequent Ore
Reserve. The maiden Ore Reserve is contained entirely within a single open pit and supports a
project production life of more than 13 years at the planned 3.0Mtpa processing rate.
In parallel, Tesoro continued to progress the Definitive Feasibility Study (DFS) and broader
development-readiness activities across mining, processing, tailings, infrastructure, environmental
approvals, project execution and financing. With the resource-definition programme complete,
drilling also transitioned towards opportunities for further Mineral Resource growth around Ternera
and broader new discoveries across El Zorro.
HIGHLIGHTS FROM THE QUARTER
Ternera MRE upgraded to 51.6Mt at 1.10g/t Au for 1.82Moz2
, reported at a 0.30g/t Au cut-
off grade and constrained within a US$3,500/oz optimised open-pit shell.
Approximately 1.47Moz, representing approximately 80% of total contained gold,
classified as Measured and Indicated, an increase of approximately 348koz compared with
the August 2025 MRE, including a 95koz Measured Mineral Resource defined for the
first time.
The updated MRE followed completion of the 80 hole, 27,162m Ternera infill drilling
programme, with final assays received during the Quarter and incorporated into the updated
model.
Maiden Ore Reserve of 42.8Mt at 0.93g/t Au for 1.28Moz declared, comprising 93koz
Proved and 1.190Moz Probable Ore Reserves, contained entirely within a single open pit.
The maiden Ore Reserve represents approximately 87% of the 1.47Moz of gold within the
Measured and Indicated Mineral Resource and supports a 13+ year project production
1 See ASX Announcement released on 18 September 2026: Maiden 1.28Moz Ore Reserve at Ternera – title correction
2 See ASX Announcement released on 27 August 2026: Upgrade to Ternera 1.8Moz Mineral Resource
ASX Announcement
30 October 2026
Tesoro Gold 2
life at the planned 3.0Mtpa processing rate.
PFS-level Modifying Factor work supporting the Ore Reserve further advanced the
technical basis for the DFS, alongside continued progress across mining, processing,
tailings, infrastructure, environmental approvals, project execution and financing
workstreams.
Environmental baseline fieldwork was completed during the Quarter, with the
Environmental Impact Assessement (EIA) and Sectorial Permit documentation continuing to
progress.
Following completion of the infill programme, drilling shifted towards near-deposit Mineral
Resource growth and broader discovery targets, with drilling initially focussed to
extensional targets around Ternera.
Quarter-end net cash and cash equivalents of A$9.28 million.
Figure 1: El Zorro Gold Project Location Relative to Major Infrastructure and Operations.
ASX Announcement
30 October 2026
Tesoro Gold 3
EL ZORRO GOLD PROJECT
El Zorro is located in Chile’s Coastal Cordillera and hosts the Ternera Gold Deposit. Ternera is being
rapidly advanced towards development through DFS-level technical studies, permitting and project
planning in parallel with ongoing exploration.
Tesoro’s 95%-owned Chilean subsidiary, Tesoro Mining Chile SpA, currently holds 94.54% of
El Zorro.
During the Quarter, activities at Ternera flowed from the completion of resource-definition drilling
through an upgraded MRE to enable the calculation of a maiden Ore Reserve. At the same time, the
Company continued to advance the broader technical and development workstreams required to
define the proposed development configuration and advance technical studies.
UPDATED TERNERA MINERAL RESOURCE ESTIMATE
On 27 August 2026, Tesoro reported an updated MRE for Ternera of 51.6Mt at 1.10g/t Au for 1.82Moz
of contained gold, reported at a 0.30g/t Au cut-off grade and constrained within a US$3,500/oz
optimised open-pit shell.
The key outcome of the update was the substantial increase in confidence within the Mineral
Resource. Measured and Indicated Mineral Resources now total 40.3Mt containing approximately
1.47Moz of gold, representing approximately 78% of pit-constrained Mineral Resource tonnes and
approximately 80% of contained gold.
This represents an increase of approximately 348koz in Measured and Indicated contained gold
compared with the August 2025 MRE and includes a 95koz Measured Mineral Resource defined for
the first time.
Table 1: Ternera Mineral Resource Estimate
CLASSIFICATION TONNES AU GRADE CONTAINED GOLD
Measured 2.4Mt 1.24g/t 95koz
Indicated 37.9Mt 1.13g/t 1,371koz
Inferred 11.3Mt 0.98g/t 356koz
Total 51.6Mt 1.10g/t 1,822koz
Note: Mineral Resources are reported at a 0.30g/t Au cut-off grade and constrained within a US$3,500/oz optimised open-
pit shell. Totals may not add up due to rounding.
ASX Announcement
30 October 2026
Tesoro Gold 4
The unconstrained global MRE was reported at 1.93Moz at 1.07g/t Au.
This update followed completion of the Ternera infill drilling programme, comprising 80 diamond drill
holes for 27,162m3
. Assays from the final holes were received during the Quarter returning multiple
thick, high-grade intercepts, with seven holes returning intercepts >50g/m and 1 hole returning an
intercept >100g/m.
Notable assay results included:
10.00m @ 6.14g/t Au from 14.00m (ZDDH0461) including:
o 3.25m @ 15.96g/t Au from 16.49m
96.40m @ 0.86g/t Au from 351.00m (ZDDH0464) including:
o 37.54m @ 1.50g/t Au from 409.06m
60.50m @ 1.01g/t Au from 197.00m (ZDDH0466)
34.05m @ 1.56g/t Au from 331.00m (ZDDH0467) including:
o 6.14m @ 5.78g/t Au fron 331.86m
9.21m @ 5.76g/t Au from 370.59m (ZDDH0468)
40.61m @ 1.32g/t Au from 322.10m (ZDDH0469)
51.63m @ 1.23g/t Au from 328.77m (ZDDH0471) and:
o 25.00m @ 1.55g/t from 444.00m
101.00m @ 1.12g/t Au from 320.00m (ZDDH0475).
3 3 See ASX Announcement released on 20 August 2026: Ternera Infill Returns Wide, High-Grade Gold Intercepts
ASX Announcement
30 October 2026
Tesoro Gold 5
Completion of the infill programme and the resulting increase in Mineral Resource confidence
provided the geological basis for calculation of the maiden Ore Reserve announced subsequently
during the Quarter.
Figure 2: Isometric view of the Ternera Gold Deposit block model looking north-west. Showing Measured (yellow), indicated
(red) and Inferred (green) classified resources and US$3500/oz pit shell. Datum PSAD56 19S.
MAIDEN TERNERA ORE RESERVE
On 18 September 2026, Tesoro declared a maiden Ore Reserve for Ternera of 42.8Mt at 0.93g/t
Au for 1.28Moz of contained gold, contained entirely within a single open pit.
ASX Announcement
30 October 2026
Tesoro Gold 6
Table 2: Ternera Maiden Ore Reserve
CLASSIFICATION TONNES AU GRADE CONTAINED GOLD
Proved 2.8Mt 1.05g/t 93koz
Probable 40.1Mt 0.92g/t 1,190koz
Total 42.8Mt 0.93g/t 1,283koz
Note: Ore Reserves are reported above an economic cut-off grade of 0.30g/t Au. Totals may not add up due to rounding.
The Ore Reserve includes only Measured and Indicated Mineral Resources, with no Inferred Mineral
Resources included. It represents approximately 87% of the 1.47Moz of gold contained within the
Measured and Indicated components of the August 2026 MRE, demonstrating a high level of
conversion following application of the relevant Modifying Factors.
The Reserve pit was designed based on a pit shell selected from optimisation using a US$3,000/oz
gold price and supports a project production life of more than 13 years at the planned 3.0Mtpa
processing rate.
The Ore Reserve is underpinned by PFS-level mine designs, schedules and Modifying Factors
informed by work across mining, geotechnical, metallurgy, processing, infrastructure, environmental
and cost workstreams. This work provides the technical foundation from which the DFS can further
refine the proposed mine design, processing configuration, infrastructure requirements, economics
and execution strategy.
The maiden Ore Reserve represents an important progression in the definition of Ternera,
establishing the first mineable inventory for the Project and providing a more defined technical basis
for DFS-level mine planning and optimisation.
ASX Announcement
30 October 2026
Tesoro Gold 7
Figure 3: Ternera Deposit Ore Reserve Final Pit – Plan View
ASX Announcement
30 October 2026
Tesoro Gold 8
Figure 4: Ternera Deposit Ore Reserve Pit Section 7036200N (looking North)
DFS AND DEVELOPMENT READINESS
Tesoro continued to advance the El Zorro DFS and broader development-readiness programme
throughout the Quarter, with work progressing across mining, processing, tailings, infrastructure,
environmental approvals, project execution and financing.
Development work undertaken during the Quarter included advancement of process design and
engineering for the proposed 3.0Mtpa processing plant, mine design and scheduling, engineering
for the proposed dry-stack tailings storage facility, power and water infrastructure planning and
project execution activities.
Tesoro also continued to progress the proposed grid power connection and its project financing
strategy.
The PFS-level work completed to support the maiden Ore Reserve materially advanced a number
of these workstreams and provides the technical foundation from which the DFS can further refine
the proposed mine design, processing configuration, infrastructure requirements, economics and
execution strategy.
The DFS remains targeted for completion during CY2026.
Environmental and Permitting
Environmental and permitting work continued in parallel with the engineering programme.
Environmental baseline fieldwork was completed during the Quarter, with reporting and preparation
of the relevant environmental and Sectorial Permit documentation continuing as part of the Project’s
permitting pathway.
ASX Announcement
30 October 2026
Tesoro Gold 9
EXPLORATION AND MINERAL RESOURCE GROWTH
Completion of the Ternera infill programme allowed Tesoro to redirect drilling from Resource
definition towards potential Mineral Resource extensions and newdiscovery opportunities.
Drilling was initially redeployed to near-deposit targets around Ternera, including holes designed to
test extensions to the existing mineralised system. This work provides the potential to add to the
Mineral Resource beyond the area supporting the current Ore Reserve while the existing
development case continues to be advanced.
In parallel, Tesoro continued to progress its new-discovery programme across high-priority targets
within El Zorro, with geological, geophysical and geochemical information being used to refine and
prioritise the next phase of regional drilling.
ASX Announcement
30 October 2026
Tesoro Gold 10
CORPORATE
During the Quarter, Tesoro continued its investor engagement programme in parallel with the
advancement of El Zorro, attending and presenting at the Noosa Mining Conference, Precious
Metals Summit in Beaver Creek, and the Denver Gold Group Mining Forum Americas.
Figure 5: Executive Director – Mining & Development Linton Putland and Non-Executive Chair Mark Connelly at the Precious
Metals Summit in Beaver Creek.
ASX Announcement
30 October 2026
Tesoro Gold 11
Financial Position
During the Quarter, Tesoro committed A$5.64 million towards exploration and evaluation activities,
principally associated with drilling, technical studies and development-readiness activities at
El Zorro.
At 30 September 2026, the Company held A$9.28 million in net cash and cash equivalents.
Payments to related parties and their associates during the Quarter totalled A$209,000 comprising
A$110,000 included in operating activities and A$99,000 included in investing activities. The
payments related to remuneration, including superannuation for the Managing Director, Executive
Director, Non-Executive Director fees and consutling fees.
Corporate
During the September Quarter, 630,000 Performance Rights and 46,508 Share Rights were
converted into Fully Paid Ordinary Shares, 360,000 Performance Rights and 2,183,500 Performance
Rights were issued to employees pursuant to the Employee Incentive Securities Plan.
Upcoming Activities and Outlook
Following the substantial advancement of Ternera during the September Quarter, Tesoro’s focus for
the December Quarter is expected to centre on completion and integration of the remaining DFS
workstreams and continued advancement of the Project’s development-readiness programme.
Key activities are expected to include continued mine planning and optimisation, process and
infrastructure engineering, environmental and permitting work, project execution and financing
activities, together with ongoing near-deposit drilling targeting potential Mineral Resource growth
and continued testing of priority new-discovery targets across El Zorro.
The DFS remains targeted for completion during CY2026.
EVENTS SUBSEQUENT TO QUARTER END
Growth drilling beyond Ternera Resource
Tesoro reported initial assay results from extensional drilling at the Ternera Gold Deposit, with
multiple zones of gold mineralisation identified up to 300m beyond the existing Mineral Resource
Estimate and planned open pit.
The encouraging results prompted an expansion of the drilling programme to test over 1km of
prospective strike at Ternera East. Drilling continued across near-deposit growth targets, including
northern extensions of Ternera and new discovery drilling at Drone Hill, with further district-scale
exploration planned across the broader El Zorro gold corridor.
ASX Announcement
30 October 2026
Tesoro Gold 12
A$40 Million Placement
On 29 October 2026, Tesoro announced firm commitments to raise approximately A$40 million
(before costs) through a placement of approximately 54.8 million new fully paid ordinary shares at
A$0.73 per share.
The Placement comprises two tranches, with approximately A$32.8 million to be raised under the
Company's existing placement capacity and the remaining A$7.2 million subject to shareholder
approval at an Extraordinary General Meeting expected to be held in December 2026.
Proceeds from the Placement will be used to advance development and permitting activities at
Ternera, including completion of the DFS, Resource expansion drilling and broader exploration
across the El Zorro District, together with general working capital and costs associated with the
Placement.
Acquisition of Minority Interest
On 29 October 2026, Tesoro announced that its wholly owned subsidiary, Tesoro Australia Pty Ltd,
had entered into a binding Term Sheet to acquire Inversiones Marlin Limitada's remaining 5% free-
carried interest in Tesoro Mining Chile SpA (TMC).
The acquisition will increase Tesoro's ownership of TMC from 95% to 100%, bringing its direct
ownership of the El Zorro Gold Project from 90.63% to 95.4%.
Consideration comprises the issue of approximately 11.7 million Tesoro shares, of which 50% will be
subject to voluntary escrow for six months. Completion remains subject to shareholder approval at
the Extraordinary General Meeting expected to be held in December 2026 and other customary
closing conditions.
Authorised by the Board of Tesoro Gold Ltd.
For more information:
Company
Zeff Reeves
Managing Director
info@tesorogold.com.au
Investor Relations & Media Enquiries
Grace Lauder
Fivemark Partners
Grace.lauder@fivemark.com.au
Follow Us
Website
LinkedIn
X
ASX Announcement
30 October 2026
Tesoro Gold 13
About Tesoro
Tesoro Gold Limited has discovered and defined the first Intrusive
Related Gold System in Chile. The 1.82Moz Ternera discovery is
in the Coastal Cordillera region of Chile. The Coastal Cordillera
region is host to multiple world-class copper and gold mines, has
well established infrastructure, service providers and an
experienced mining workforce. Large areas of the Coastal
Cordillera remain unexplored due to the unconsolidated nature of
mining concession ownership, but Tesoro, via its in-country
network and experience has been able secure rights to the district-
scale El Zorro gold project in-line with the Company’s strategy.
Tesoro’s 95% owned Chilean subsidiary owns 95.4% of the El
Zorro Gold Project (see ASX announcement released 12 August
2025).
Future Performance
This announcement may contain certain forward-looking
statements and opinions. Forward-looking statements,
including projections, forecasts and estimates, are provided as
a general guide only and should not be relied on as an
indication or guarantee of future performance and involve
known and unknown risks, uncertainties, assumptions,
contingencies and other important factors, many of which are
outside the control of the Company and which are subject to
change without notice and could cause the actual results,
performance or achievements of the Company to be materially
different from the future results, performance or achievements
expressed or implied by such statements. Past performance is
not necessarily a guide to future performance, and no
representation or warranty is made as to the likelihood of
achievement or reasonableness of any forward-looking
statements or other forecast.
Nothing contained in this announcement, nor any information
made available to you is, or and shall be relied upon as, a
promise, representation, warranty or guarantee as to the past,
present or the future performance of Tesoro Gold.
Competent Persons’ Statement
Mineral Resources – Ternera Gold Deposit
The information in this report that relates to the Mineral
Resource Estimate for the Ternera Gold Deposit was
previously reported by the Company in its ASX announcement
dated 27 August 2026 titled “Upgrade to Ternera 1.8Moz
Mineral Resource”. The Company confirms that it is not aware
of any new information or data that materially affects the
information included in that announcement and that all material
assumptions and technical parameters underpinning the
Mineral Resource Estimate continue to apply and have not
materially changed. The Company confirms that the form and
context in which the Competent Person’s findings are
presented have not been materially modified from the original
market announcement.
Ore Reserves and Production Target – Ternera Gold
Deposit
The information in this report that relates to the Ore Reserve
and Production Target for the Ternera Gold Deposit was
previously reported by the Company in its ASX announcement
dated 18 September 2026 titled “Maiden 1.28Moz Ore Reserve
at Ternera”. The Company confirms that it is not aware of any
new information or data that materially affects the information
included in that announcement and that all material
assumptions and technical parameters underpinning the Ore
Reserve estimate continue to apply and have not materially
changed. The Company further confirms that all material
assumptions underpinning the Production Target continue to
apply and have not materially changed. The Company
confirms that the form and context in which the Competent
Person’s findings are presented have not been materially
modified from the original market announcement.
Exploration Results
The information in this report that relates to Exploration Results
was previously reported by the Company in its ASX
announcement dated 20 August 2026 titled “Ternera Infill
Returns Wide, High-Grade Gold Intercepts”. The Company
confirms that it is not aware of any new information or data that
materially affects the information included in that
announcement. The Company confirms that the form and
context in which the Competent Person’s findings are
presented have not been materially modified from the original
market announcement.
ASX Announcement
30 October 2026
Tesoro Gold 14
APPENDIX 1: CONCESSION SCHEDULE AS AT 30 SEPTEMBER 2026
EL ZORRO GOLD PROJECT CONCESSIONS (95.4% Tesoro Mining Chile SpA)
N° CONCESSION NAME EXPIRATION DATE SIZE (HA) CONCESSION TYPE
1 ZORRO 1B 10/Aug/2030* 200 Exploration
2 ZORRO 2B 10/Aug/2030* 200 Exploration
3 ZORRO 3B 10/Aug/2030* 200 Exploration
4 ZORRO 4B 10/Aug/2030* 100 Exploration
5 ZORRO 5B 10/Aug/2030* 200 Exploration
6 ZORRO 6B 10/Aug/2026 200 Exploration
7 GOLD STORE 72A 21/Sep/2026 300 Exploration
8 GOLD STORE 71A 21/Sep/2026 300 Exploration
9 GOLD STORE 70A 21/Sep/2026 300 Exploration
10 GOLD STORE 69A 21/Sep/2026 300 Exploration
11 GOLD STORE 68A 21/Sep/2026 300 Exploration
12 GOLD STORE 67A 21/Sep/2026 300 Exploration
13 GOLD STORE 66A 27/Sep/2026 300 Exploration
14 BLOODY GOOD SHOT 13B 27/Sep/2026 200 Exploration
15 BLOODY GOOD SHOT 12B 27/Sep/2026 200 Exploration
16 BLOODY GOOD SHOT 11B 27/Sep/2026 200 Exploration
17 BLOODY GOOD SHOT 10B 27/Sep/2026 300 Exploration
18 BLOODY GOOD SHOT 9B 28/Sep/2026 300 Exploration
19 BLOODY GOOD SHOT 8B 5/Oct/2026 200 Exploration
20 BLOODY GOOD SHOT 7B 28/Sep/2026 100 Exploration
21 BLOODY GOOD SHOT 6B 5/Oct/2026 200 Exploration
22 BLOODY GOOD SHOT 5B 29/Sep/2026 200 Exploration
23 BLOODY GOOD SHOT 4B 29/Sep/2026 300 Exploration
24 BLOODY GOOD SHOT 3B 3/Oct/2026 300 Exploration
25 BLOODY GOOD SHOT 2B 3/Oct/2026 300 Exploration
26 BLOODY GOOD SHOT 1B 3/Oct/2026 300 Exploration
27 SIERRA PATACONES 42A 24/Oct/2026 300 Exploration
28 SIERRA PATACONES 41A 24/Oct/2026 300 Exploration
29 SIERRA PATACONES 40A 25/Oct/2026 300 Exploration
30 SIERRA PATACONES 39A 25/Oct/2026 300 Exploration
31 SIERRA PATACONES 38A 25/Oct/2026 300 Exploration
32 SIERRA PATACONES 35A 25/Oct/2026 300 Exploration
33 SIERRA PATACONES 34A 25/Oct/2026 300 Exploration
34 SIERRA PATACONES 33A 25/Oct/2026 300 Exploration
35 SIERRA PATACONES 32A 25/Oct/2026 300 Exploration
36 SIERRA PATACONES 31A 25/Oct/2026 300 Exploration
37 SIERRA PATACONES 29A 25/Oct/2026 300 Exploration
38 SIERRA PATACONES 28A 25/Oct/2026 300 Exploration
39 SIERRA PATACONES 27A 25/Oct/2026 300 Exploration
ASX Announcement
30 October 2026
Tesoro Gold 15
N° CONCESSION NAME EXPIRATION DATE SIZE (HA) CONCESSION TYPE
40 SIERRA PATACONES 26A 25/Oct/2026 300 Exploration
41 SIERRA PATACONES 25A 25/Oct/2026 300 Exploration
42 SIERRA PATACONES 24A 25/Oct/2026 300 Exploration
43 SIERRA PATACONES 23A 25/Oct/2026 300 Exploration
44 SIERRA PATACONES 21A 26/Oct/2026 300 Exploration
45 SIERRA PATACONES 20A 24/Oct/2026 300 Exploration
46 SIERRA PATACONES 19A 20/Oct/2026 300 Exploration
47 SIERRA PATACONES 18A 24/Oct/2026 300 Exploration
48 SIERRA PATACONES 17A 24/Oct/2026 300 Exploration
49 SIERRA PATACONES 16A 24/Oct/2026 300 Exploration
50 SIERRA PATACONES 14A 24/Oct/2026 300 Exploration
51 SIERRA PATACONES 13A 24/Oct/2026 300 Exploration
52 VACAS FLACAS 28A 26/Oct/2026 300 Exploration
53 VACAS FLACAS 27A 26/Oct/2026 300 Exploration
54 SIERRA PATACONES 2A 28/Oct/2026 300 Exploration
55 SIERRA PATACONES 3A 28/Oct/2026 300 Exploration
56 SIERRA PATACONES 4A 28/Oct/2026 300 Exploration
57 SIERRA PATACONES 5A 28/Oct/2026 300 Exploration
58 SIERRA PATACONES 6A 4/Nov/2026 300 Exploration
59 SIERRA PATACONES 7A 4/Nov/2026 300 Exploration
60 SIERRA PATACONES 9A 4/Nov/2026 300 Exploration
61 SIERRA PATACONES 10A 4/Nov/2026 300 Exploration
62 SIERRA PATACONES 11A 4/Nov/2026 300 Exploration
63 SIERRA PATACONES 12A 24/Nov/2026 300 Exploration
64 SIERRA PATACONES 45A 24/Nov/2026 300 Exploration
65 SIERRA PATACONES 46A 24/Nov/2026 300 Exploration
66 SIERRA PATACONES 47A 24/Nov/2026 300 Exploration
67 SIERRA PATACONES 48A 24/Nov/2026 300 Exploration
68 SIERRA PATACONES 51A 24/Nov/2026 300 Exploration
69 SIERRA PATACONES 52A 24/Nov/2026 300 Exploration
70 SIERRA PATACONES 55A 24/Nov/2026 300 Exploration
71 SIERRA PATACONES 56A 24/Nov/2026 300 Exploration
72 SIERRA PATACONES 60A 28/Oct/2026 300 Exploration
73 GOLD STORE 13A 22/Sep/2030* 300 Exploration
74 GOLD STORE 12A 21/Sep/2030* 300 Exploration
75 GOLD STORE 9A 22/Sep/2030* 300 Exploration
76 GOLD STORE 7A 21/Sep/230*6 300 Exploration
77 GOLD STORE 5A 21/Sep/2030* 300 Exploration
78 GOLD STORE 4A 21/Sep/2030* 300 Exploration
79 GOLD STORE 3A 21/Sep/2026 300 Exploration
80 GOLD STORE 2A 21/Sep/2026 300 Exploration
81 GOLD STORE 1A 21/Sep/2026 300 Exploration
ASX Announcement
30 October 2026
Tesoro Gold 16
N° CONCESSION NAME EXPIRATION DATE SIZE (HA) CONCESSION TYPE
82 GOLD STORE 21A 21/Sep/2030* 300 Exploration
83 GOLD STORE 19A 21/Sep/2030* 300 Exploration
84 GOLD STORE 18A 21/Sep/2030* 300 Exploration
85 GOLD STORE 17A 21/Sep/2030* 300 Exploration
86 GOLD STORE 16A 21/Sep/2030* 300 Exploration
87 GOLD STORE 8A 22/Sep/2030* 300 Exploration
88 GOLD STORE 39A 22/Nov/2026 300 Exploration
89 GOLD STORE 38A 21/Nov/2026 300 Exploration
90 GOLD STORE 37A 21/Nov/2026 300 Exploration
91 GOLD STORE 34A 21/Nov/2026 300 Exploration
92 GOLD STORE 33A 21/Nov/2026 300 Exploration
93 GOLD STORE 30A 21/Nov/2026 300 Exploration
94 GOLD STORE 29A 21/Nov/2026 300 Exploration
95 GOLD STORE 26A 22/Nov/2026 300 Exploration
96 GOLD STORE 25A 22/Nov/2026 300 Exploration
97 GOLD STORE 65A 18/Nov/2026 300 Exploration
98 GOLD STORE 64A 18/Nov/2026 300 Exploration
99 GOLD STORE 63A 18/Nov/2026 300 Exploration
100 GOLD STORE 62A 18/Nov/2026 300 Exploration
101 GOLD STORE 61A 18/Nov/2026 300 Exploration
102 GOLD STORE 60A 18/Nov/2026 300 Exploration
103 GOLD STORE 59A 21/Nov/2026 300 Exploration
104 GOLD STORE 58A 21/Nov/2026 300 Exploration
105 GOLD STORE 57A 21/Nov/2026 300 Exploration
106 GOLD STORE 56A 21/Nov/2026 200 Exploration
107 GOLD STORE 55A 21/Nov/2026 300 Exploration
108 GOLD STORE 54A 21/Nov/2026 300 Exploration
109 GOLD STORE 53A 21/Nov/2026 300 Exploration
110 GOLD STORE 52A 16/Nov/2026 300 Exploration
111 GOLD STORE 51A 14/Nov/2026 300 Exploration
112 GOLD STORE 50A 14/Nov/2026 300 Exploration
113 GOLD STORE 49A 14/Nov/2026 300 Exploration
114 GOLD STORE 48A 18/Nov/2026 300 Exploration
115 GOLD STORE 47A 4/Nov/2026 300 Exploration
116 GOLD STORE 46A 4/Nov/2026 300 Exploration
117 GOLD STORE 45A 4/Nov/2026 300 Exploration
118 GOLD STORE 44A 4/Nov/2026 300 Exploration
119 GOLD STORE 43A 4/Nov/2026 300 Exploration
120 GOLD STORE 42A 4/Nov/2026 300 Exploration
121 GOLD STORE 41A 4/Nov/2026 300 Exploration
122 GOLD STORE 40A 4/Nov/2026 300 Exploration
123 SIERRA PATACONES 61A 29/Nov/2026 300 Exploration
ASX Announcement
30 October 2026
Tesoro Gold 17
N° CONCESSION NAME EXPIRATION DATE SIZE (HA) CONCESSION TYPE
124 SIERRA PATACONES 62A 29/Nov/2026 300 Exploration
125 SIERRA PATACONES 63A 29/Nov/2026 300 Exploration
126 SIERRA PATACONES 67A 29/Nov/2026 300 Exploration
127 SIERRA PATACONES 71A 29/Nov/2026 300 Exploration
128 SIERRA PATACONES 76A 29/Nov/2026 300 Exploration
129 POTRERO 1 7/Dec/2026 300 Exploration
130 POTRERO 2 7/Dec/2026 300 Exploration
131 POTRERO 3 2/Dec/2026 300 Exploration
132 POTRERO 4 2/Dec/2026 300 Exploration
133 POTRERO 5 2/Dec/2026 300 Exploration
134 POTRERO 6 6/Dec/2026 300 Exploration
135 POTRERO 7 6/Dec/2026 300 Exploration
136 POTRERO 9 9/Dec/2026 300 Exploration
137 POTRERO 12 5/Dec/2026 300 Exploration
138 POTRERO 23 6/Dec/2026 300 Exploration
139 POTRERO 24 6/Dec/2026 300 Exploration
140 POTRERO 25 6/Dec/2026 300 Exploration
141 POTRERO 26 6/Dec/2026 200 Exploration
142 POTRERO 27 6/Dec/2026 300 Exploration
143 POTRERO 29 6/Dec/2026 300 Exploration
144 POTRERO 67 16/Mar/2027 300 Exploration
145 POTRERO 68 16/Mar/2027 300 Exploration
146 POTRERO 69 16/Mar/2027 300 Exploration
147 POTRERO 70 16/Mar/2027 300 Exploration
148 POTRERO 71 16/Mar/2027 300 Exploration
149 POTRERO 72 16/Mar/2027 300 Exploration
150 POTRERO 73 14/Mar/2027 300 Exploration
151 POTRERO 77 14/Mar/2027 100 Exploration
152 POTRERO 78 14/Mar/2027 100 Exploration
153 POTRERO 32 26/Apr/2027 200 Exploration
154 POTRERO 33 19/Apr/2027 200 Exploration
155 POTRERO 34 26/Apr/2027 300 Exploration
156 POTRERO 37 19/Apr/2027 300 Exploration
157 POTRERO 40 26/Apr/2027 300 Exploration
158 POTRERO 41 19/Apr/2027 300 Exploration
159 POTRERO 42 21/Apr/2027 200 Exploration
160 POTRERO 43 18/Apr/2027 200 Exploration
161 POTRERO 50 21/Apr/2027 300 Exploration
162 POTRERO 53 19/Apr/2027 300 Exploration
163 POTRERO 58 21/Apr/2027 300 Exploration
164 PUNTA DE DIAMANTE 3B 6/Sep/2027 300 Exploration
165 PUNTA DE DIAMANTE 2B 6/Sep/2027 300 Exploration
ASX Announcement
30 October 2026
Tesoro Gold 18
N° CONCESSION NAME EXPIRATION DATE SIZE (HA) CONCESSION TYPE
166 PUNTA DE DIAMANTE 1B 6/Sep/2027 200 Exploration
167 LA NEGRA COJA 19B 5/Sep/2027 200 Exploration
168 LA NEGRA COJA 18B 5/Sep/2027 300 Exploration
169 LA NEGRA COJA 17B 5/Sep/2027 300 Exploration
170 LA NEGRA COJA 15B 5/Sep/2027 300 Exploration
171 LA NEGRA COJA 14B 5/Sep/2027 300 Exploration
172 LA NEGRA COJA 13B 5/Sep/2027 300 Exploration
173 LA NEGRA COJA 12B 5/Sep/2027 200 Exploration
174 LA NEGRA COJA 11B 5/Sep/2027 300 Exploration
175 LA NEGRA COJA 8B 5/Sep/2027 300 Exploration
176 LA NEGRA COJA 7B 6/Sep/2027 300 Exploration
177 LA NEGRA COJA 6B 6/Sep/2027 200 Exploration
178 LA NEGRA COJA 5B 6/Sep/2027 300 Exploration
179 LA NEGRA COJA 4B 6/Sep/2027 200 Exploration
180 LA NEGRA COJA 3B 6/Sep/2027 300 Exploration
181 LA NEGRA COJA 2B 6/Sep/2027 300 Exploration
182 LA NEGRA COJA 1B 6/Sep/2027 200 Exploration
183 Buzzard 1, 1 al 300 N/A Constituted 300 Exploitation
184 Buzzard 2, 1 al 300 N/A Constituted 300 Exploitation
185 Buzzard 3, 1 al 300 N/A Constituted 300 Exploitation
186 Buzzard 4, 1 al 300 N/A Constituted 300 Exploitation
187 LEON DOS 1-30 N/A Constit