Tesoro Advances El Zorro DFS and Development
Released
Released
Announcement PDF
31 Cliff Street, Fremantle WA 6160 | +61 8 6383 7883 | info@tesorogold.com.au | tesorogold.com.au
ASX ANNOUNCEMENT
1 JULY 2026
ASX: TSO OTCQX: TSORF FSE: 5D7
TESORO GOLD ACCELERATES DFS WORKSTREAMS AND
DEVELOPMENT READINESS ACTIVITIES FOR EL ZORRO
Tesoro Gold Limited (Tesoro or the Company) (ASX: TSO, OTCQX: TSORF, FSE: 5D7) is pleased to
provide the following update on Definitive Feasibility Study (DFS) workstreams and development
readiness activities for the 1.82Moz Ternera Gold Deposit (Ternera) at its El Zorro Gold Project in
Chile (El Zorro, or the Project).
DFS workstreams and development readiness activities have accelerated, with all core activities
now underway or materially advanced across engineering, mining, processing, infrastructure,
permitting, financing, and execution planning.
DFS AND DEVELOPMENT READINESS WORKSTREAMS
• All DFS workstreams materially advanced, with technical, engineering, permitting,
financing and execution-readiness activities progressing in parallel.
• Expanded people and in-country presence established, including a strengthened
development and execution team, additional in-country capability in Chile and a new
Chile office to support project coordination, permitting, stakeholder engagement and
pre-construction planning.
• Strategic Alliance Partnership formed with STRACON Chile SpA (STRACON), to act as
Tesoro’s preferred contractor to support pre-construction activities, construction and
operation of El Zorro.
• GR Engineering Services (GRES) has commenced DFS process design and engineering
work for a proposed 3.0Mtpa gold processing plant and associated site infrastructure.
• Knight Piésold Pty Ltd (KP) engaged to complete DFS-level dry-stack tailings storage
facility engineering and design for life-of-project requirements.
• Power, water and site infrastructure workstreams are materially advanced, including
engineering design and cost estimates for grid power and process water infrastructure,
together with submission of a 21MW electrical connection request to the Chilean
National Electricity Coordinator.
• BurnVoir Corporate Finance Limited (BurnVoir) appointed as financial adviser to support
development of an optimal project financing mix and secure key debt facilities.
• Environmental baseline studies are 75% complete ahead of August 2026 delivery, before
preparation of Environmental Impact Study (EIS) documentation.
RESOURCE DEFINITION AND NEW DISCOVERY DRILLING
• Infill drilling is complete, in support of the upcoming Mineral Resource update and
delivery of a maiden Ore Reserve for Ternera.
Tesoro Gold 2
ASX ANNOUNCEMENT
1 JULY 2026
• Exploration drilling has now focused on Ternera expansion and regional new discovery
targets, which are set to be tested over the coming months.
Tesoro Managing Director, Zeff Reeves, commented:
“Significant progress has been made across multiple fronts towards delivering the planned DFS by
year end, in parallel with key development readiness activities required to move Ternera towards
development.
“We have materially strengthened the execution platform around El Zorro, including an expanded
project development team, additional in-country capability in Chile and the establishment of a new
Chile office, which provides Tesoro with a stronger operational presence as activity levels increase
across project coordination, permitting, stakeholder engagement and pre-construction planning.
“We have formed an important commercial relationship with STRACON, a highly credentialled
mining and construction contracting firm with a proven track record of project delivery and
operations throughout South America, including Chile. This alliance provides a framework for us to
work with a highly credentialled mining and construction contractor while we develop and refine
the practical execution pathway for pre-construction, construction and future operations.
“BurnVoir Corporate Finance has been appointed to assist the Company with arranging an
appropriate financing structure and putting the associated facilities in place. BurnVoir has deep
relationships across lenders and strategic investors, and a strong track record in successfully arranging
project financing solutions in the resources sector.
“In parallel, a range of specialist advisers are advancing the processing, tailings, infrastructure,
financing and permitting workstreams needed to support a disciplined DFS and development
pathway.
“With infill drilling now complete and drilling shifting to Ternera expansion and regional discovery
targets, Tesoro is advancing both the near-term development pathway for Ternera and the broader
discovery opportunity across the El Zorro Gold District.”
PEOPLE, PRESENCE AND DEVELOPMENT READINESS
Tesoro has expanded its execution team and in-country presence to support the transition from
study definition into development readiness. This includes additional management and
technical capability in Chile, supported by the establishment of a new Chile office as a
dedicated operating base for DFS coordination, permitting, stakeholder engagement, logistics
and pre-construction planning.
The expanded Chile presence is intended to provide stronger local management of critical
workstreams, infrastructure, consultant coordination, government and community
engagement, and preparation for future construction execution.
This in-country platform is supported by Tesoro’s Australian executive and technical team,
together with specialist consultants and contractors across mining, processing, tailings,
infrastructure, environmental, and financing disciplines.
Tesoro Gold 3
ASX ANNOUNCEMENT
1 JULY 2026
STRACON ALLIANCE
Tesoro’s 95% owned subsidiary, Tesoro Mining Chile SpA (TMC), has signed a non-binding Letter
of Intent (LOI) with STRACON Chile SpA to establish an alliance-style framework. STRACON and
Tesoro have agreed to work together as a single, integrated team, dedicated to exceeding
common objectives and goals and creating value through exceptional and disciplined
performance delivered against agreed targets, for the development of the El Zorro Gold Project.
STRACON is a subsidiary of STRACON Group Holding Inc., an integrated, engineering-led mining
infrastructure services group operating across the Americas, providing end-to-end solutions
across the mining lifecycle. The proposed alliance structure is intended to support continuity,
alignment and efficient management of the Project across key phases, with each phase to be
initiated through separate Notices to Proceed at Tesoro’s discretion.
The LOI is non-binding and either party may withdraw from contract negotiations at any time
without liability to the other party.
ABOUT STRACON
STRACON is an integrated, engineering-led and technology-enabled mining infrastructure and
services group operating across the Americas. Headquartered in Toronto, Canada, STRACON
provides end-to-end solutions across the mining lifecycle, including engineering and technology
solutions, industrial services.
APPOINTMENT OF DEBT ADVISOR
BurnVoir has been appointed to support the development of an optimised El Zorro funding
strategy and to arrange debt facilities for development of the El Zorro Project.
BurnVoir is a leading specialist corporate finance advisory firm with more than 25 years’
experience having advised on over A$20 billion of project financing, capital structuring, and
strategic transactions for mining development companies. Most recently, BurnVoir has secured
project financing for ASX listed gold companies Rox Resources (ASX: RXL) and Brightstar
Resources (ASX: BTR).
PROJECT ADVANCEMENT AND DEVELOPMENT READINESS WORKSTREAMS
All DFS and several development readiness workstreams are underway, or materially advanced
to support the completion of a DFS by the end of CY2026.
Mining and construction readiness
Mining options, execution strategy and cost inputs are being advanced with STRACON,
including review and confirmation of the optimal mining configuration, fleet selection, pre-
construction planning and the proposed pathway for future construction and operations
support.
Tesoro Gold 4
ASX ANNOUNCEMENT
1 JULY 2026
Process plant and metallurgy
GRES has commenced DFS process design and engineering for a proposed 3.0Mtpa gold
processing plant and associated infrastructure, building on metallurgical testwork that
confirmed strong recoveries from a conventional CIP flowsheet using project-relevant water
sources.
Figure 1 – Proposed CIP flowsheet for Ternera 3Mtpa throughput processing plant
Tailings, geotechnical and civil engineering
KP is advancing dry-stack tailings storage facility engineering and design for life-of-project
requirements, alongside geotechnical, civil and site infrastructure inputs required for DFS capital
and operating cost estimates.
Power, water and site infrastructure
Engineering designs and estimates are well-advanced for grid power, process water, site layout
and associated infrastructure. Tesoro has submitted a Solicitud de Autorización de Conexión
(SUCTD) to Coordinador Eléctrico Nacional (CEN) for a 21MW power connection to El Zorro,
supporting the proposed high-voltage power line from Totoralillo to El Zorro.
Tesoro Gold 5
ASX ANNOUNCEMENT
1 JULY 2026
Figure 2: Ternera Gold Deposit Site layout diagram
Figure 3: El Zorro Gold Project proposed powerline and water pipeline routes
Tesoro Gold 6
ASX ANNOUNCEMENT
1 JULY 2026
Environmental and permitting progress
Permitting activities are advancing concurrently with technical workstreams. As announced on
22 April 2025, Tesoro commenced preparation for an EIS to secure Environmental Qualification
(RCA) and the associated Sectorial Permits (PAS) required for construction and operation of a
gold mine at El Zorro.
Following initial environmental desktop assessments, baseline field studies commenced in
August 2025. Baseline study programmes are now approximately 75% complete and are
scheduled for completion in August 2026, after which Tesoro expects to progress preparation
and submission of EIA documentation to the Chilean Environmental Impact Assessment System
in late 2026 to early 2027.
Table 1: El Zorro Gold Project Supporting consultants and service providers
Study Input Contributor
Study Compilation Tesoro, GRES
Geology Tesoro
Resource Estimation Lynn Widenbar and Associates
Geotechnical Peter O’Bryan and Associates
Mining Studies Tesoro, STRACON
Mining Costs Tesoro, STRACON
Metallurgical Test Work GRES, ALS Perth
Process Engineering and Design GRES
Tailings Disposal and Design Knight Piésold
Operating Costs Tesoro, GRES, STRACON, Others
Infrastructure
Tesoro, Aguas CAP, TECNOCAP,
Servicios de Ingeniería IMA S.A.
Capital Costs
Tesoro, GRES, Knight Piésold,
Aguas CAP, TECNOCAP.
Environmental, Social and Permitting Tesoro, Parez & Alverez
Financial Modelling Tesoro
Tesoro Gold 7
ASX ANNOUNCEMENT
1 JULY 2026
DEVELOPMENT PATHWAY
Major project value drivers have been materially de-risked through completed trade-off analysis
and the continued advancement of DFS workstreams.
Key upcoming target milestones include:
• Updated MRE for the Ternera Gold Deposit in late July to early August 2026.
• Publication of a maiden Ore Reserve and supporting modifying factor updates in August
2026.
• Completion and publication of the DFS by the end of CY2026.
• Submission of EIA permitting documentation in late 2026 to early 2027.
• Continued advancement of permitting through the EIA process during 2027.
These milestones are intended to reinforce the clearly established pathway towards reaching
an FID and future development of Ternera1.
RESOURCE DEFINITION AND NEW DISCOVERY DRILLING
The Ternera infill drilling programme is now complete and is expected to support the planned
Mineral Resource update and maiden Ore Reserve workstreams for Ternera.
Drilling has now shifted towards Ternera expansion and regional discovery targets, with multiple
near-deposit and district-scale targets to be tested over the coming months.
Near-deposit drilling will include targets at Ternera East, Drone Hill and extensions to the north
and south of the existing Ternera Deposit.
In parallel, new access is being established at the La Brea and Pena Blanca district targets,
which are scheduled to be drill tested in the coming weeks. These programmes form part of
Tesoro’s broader strategy to test multiple high-priority gold targets across the 30km long El Zorro
mineralised corridor (Figure 4).
Together, this work is designed to assess additional Mineral Resource growth opportunities
around Ternera and deliver new discoveries from the broader pipeline of opportunities across
the El Zorro Gold District.
1 Which remains subject to DFS outcomes, approvals and funding.
Tesoro Gold 8
ASX ANNOUNCEMENT
1 JULY 2026
Figure 4: El Zorro Gold Project showing priority targets over a >40km corridor. Refer to ASX Announcement dated
19 March 2026 for geophysics results.
Tesoro Gold 9
ASX ANNOUNCEMENT
1 JULY 2026
Authorised by the Board of Tesoro Gold Ltd.
For more information:
Company
Zeff Reeves
Managing Director
info@tesorogold.com.au
Investor Relations & Media Enquiries
Grace Lauder
Fivemark Partners
Grace.lauder@fivemark.com.au
Follow Us
• Website
• LinkedIn
• X
Table 2: Ternera Mineral Estimates for selected cut-off grades. Highlighted open pit Mineral Resource has been
constrained by an optimised pit shell using a gold price of US$3000/oz and process recovery of 94.5%. The
estimates in this table are rounded to reflect their precision; rounding errors are apparent.
Tenera Updated MRE Indicated Inferred Total
Au g/t cut-off Mt Au g/t Koz Mt Au g/t Koz Mt Au g/t Koz
Optimised Open Pit at 0.30 31.8 1.10 1,123 19.5 1.11 692 51.2 1.1 1,816
2.00 3.5 3.55 394 2.5 3.54 280 5.9 3.54 673
1.00 10.5 2.08 705 7.9 2.04 520 18.5 2.06 1,225
0.70 17.5 1.58 891 13 1.57 657 30.5 1.58 1,547
0.30 31.8 1.10 1,128 26.1 1.03 863 58.1 1.07 1,992
0.20 33.8 1.05 1,144 28.7 0.96 885 62.5 1.01 2,028
Refer ASX announcement dated 4 August 2025.
Tesoro Gold 10
ASX ANNOUNCEMENT
1 JULY 2026
About Tesoro
Tesoro Gold Limited has discovered and defined the first
Intrusive Related Gold System in Chile. The 1.82M oz Ternera
discovery is in the Coastal Cordillera region of Chile. The
Coastal Cordillera region is host to multiple world-class
copper and gold mines, has well established infrastructure,
service providers and an experienced mining workforce.
Large areas of the Coastal Cordillera remain unexplored due
to the unconsolidated nature of mining concession
ownership, but Tesoro, via its in-country network and
experience has been able secure rights to the district-scale El
Zorro gold project in-line with the Company’s strategy.
Tesoro’s 95% owned Chilean subsidiary owns 95.4% of the El
Zorro Gold Project (see ASX announcement released 12
August 2025).
Future Performance
This announcement may contain certain forward-looking
statements and opinions. Forward-looking statements, including
projections, forecasts and estimates, are provided as a general
guide only and should not be relied on as an indication or
guarantee of future performance and involve known and
unknown risks, uncertainties, assumptions, contingencies and
other important factors, many of which are outside the control
of the Company and which are subject to change without
notice and could cause the actual results, performance or
achievements of the Company to be materially different from
the future results, performance or achievements expressed or
implied by such statements. Past performance is not necessarily
a guide to future performance, and no representation or
warranty is made as to the likelihood of achievement or
reasonableness of any forward-looking statements or other
forecast. Nothing contained in this announcement, nor any
information made available to you is, or and shall be relied
upon as, a promise, representation, warranty or guarantee as
to the past, present or the future performance of Tesoro Gold
Competent Persons Statements
The information in this report that relates to Mineral Resources is
based on information compiled by Mr Lynn Widenbar (B.Sc.
(Hons) Geology, M.Sc. FAusIMM, MAIG), a Competent Person
who is a Fellow of The Australasian Institute of Mining and
Metallurgy. Mr Widenbar is acting as an independent
consultant to Tesoro Gold Limited. Mr Widenbar has sufficient
experience that is relevant to the style of mineralisation and
type of deposit under consideration, and to the activity being
undertaken to qualify as a Competent Person as defined in the
2012 Edition of the ‘Australasian Code for Reporting of
Exploration Results, Mineral Resources and Ore Reserves’. The
Company confirms that it is not aware of any new information
or data that materially affects the information contained the
form and context in which the Competent Person’s findings are
presented have not been materially modified from in the
original announcement on 4 August 2025, and all material
assumptions and technical parameters underpinning the
estimates in that announcement continue to apply and have
not materially changed.
The information in this report that relates to Exploration Results
and Metallurgical Results is based on information compiled by
Mr Zeffron Reeves (B App Sc (Hons) Applied Geology) MBA,
MAIG). Mr Reeves is a member of the Australian Institute of
Geoscientists and a Director and shareholder of the Company.
Mr Reeves has sufficient experience that is relevant to the style
of mineralisation and type of deposit under consideration and
to the activity which he is undertaking to qualify as a
Competent Person as defined in the 2012 Edition of the
Australasian Code for Reporting of Exploration Results, Mineral
Resources and Ore Reserves. Mr Reeves consents to the
inclusion in this report of the matters based on this information
in the form and context in which it appears.
The information in this report that relates to Geophysical Results
is based on information compiled by Dr Alexander Costall. Dr
Costall is a Member of the Australian Institute of Geoscientists
(AIG) and the Australian Society of Exploration Geophysics
(ASEG). Dr Costall is a consultant to Tesoro Gold Limited. Dr
Costall has sufficient experience which is relevant to the style of
mineralisation and type of deposit under consideration and to
the activity which he is undertaking to qualify as a Competent
Person as defined in the 2012 Edition of the Australasian Code
for Reporting of Exploration Results, Mineral Resources & Ore
Reserves. The Company confirms that it is not aware of any new
information or data that materially affects the historical
geophysical results included in the original reports.