Quarterly Activities Report
Released
Released
Announcement PDF
Sign up HERE to our Investor Hub
ASX ANNOUNCEMENT
31 January 2023
ASX: TSO OTCQB: TSORF
DECEMBER 2022 QUARTERLY ACTIVITIES REPORT
Tesoro Gold Limited (ASX: TSO, OTCQB: TSORF) (Tesoro or the Company) is pleased to report
on its activities for the quarter ended 31 December 2022 (the Quarter).
HIGHLIGHTS
•
Assay results from the Ternera infill and extensional drill program identified high-grade
southern extension with 53.50m @ 1.17g/t Au, including 13.50m @ 3.63g/t Au.
•
New regional discoveries identified at Animas Viejas and Calderillas provide
confirmation of El Zorro’s potential as a significant new Chilean Gold District.
•
Drilling recommenced at Ternera in January 2023 focusing on the recently identified
southern extension.
•
Updated Mineral Resource Estimate expected to be completed during Q1 2023.
•
A$8.00 million new equity raised for the continued identification, definition and drill
testing of district and regional targets within the El Zorro Gold Project, including
≈A$5.71 million strategic investment from a subsidiary of Gold Fields Limited (JSE:GFI,
NYSE:GFI), Corporate International Holdings BV.
•
At-the-Market equity facility utilised and subsequently terminated, raising A$0.75 million.
•
Cash balance of A$7.21 million and zero debt as at 31 December 2022.
Tesoro Gold Managing Director, Zeff Reeves commented: “We are delighted with the
significant exploration and strategic progress made by the Tesoro team during the
December quarter. Assay results from our infill and extensional drilling program at Ternera
demonstrate huge potential with significant intercepts of gold mineralisation occurring in all
holes drilled. The new, shallow, high-grade zones observed to the south, offer material
potential to grow our existing 1.1Moz Mineral Resource Estimate1. Further, our regional
exploration at both Animas Viejas and Calderillas has returned some truly exciting results,
further evidencing the El Zorro gold system’s potential to evolve into a new, world-class,
Chilean Gold District.
Gold Fields cornerstoned and underwrote a strategic investment into the Company during
the quarter. This significant investment validates the quality of the El Zorro project and the
potential scale as we continue to explore the El Zorro system.”
1. For full details of the Ternera MRE, refer to ASX Announcement dated 23 May 2022. The Company confirms that it is not
aware of any new information or data that materially affects the information in that release and that the material assumptions
and technical parameters underpinning this estimate continue to apply and have not materially changed.
Level 48, 152-158 St Georges Terrace, Perth
+61 8 6311 9160
info@tesorogold.com.au
1
ASX ANNOUNCEMENT 31 JANUARY 2023
EL ZORRO GOLD PROJECT, CHILE
Ternera Infill and Extensional Drilling
The Company received assay results for 7 drill holes from infill and extensional drilling at
Ternera (refer ASX Announcement, 8 November 2022). Best results include:
• 53.50m @ 1.17g/t Au from 57.00m including;
• 13.50m @ 3.63g/t Au from 70.50m;
• 8.50m @ 1.17g/t Au from 275.50m; and
• 6.37m @ 1.14g/t Au from 344.00m.
Multiple gold zones were intersected well outside of the existing 1.1Moz Mineral Resource
Estimate (MRE) envelope (refer Table 1 and ASX announcement 23 May 2022). Hole
ZDDH0309 also provides a new, shallow, high-grade gold zone, approximately 200m south
of the existing MRE area, commencing at approximately 30m below surface adding
another 200m of strike to the potential resource area.
Figure 1 – Ternera Gold Deposit Drilling Plan on geology and results reported during the quarter. Red outline
shows MRE USD1800/oz optimised pit location. Datum PSAD56 19S
TESOROGOLD.COM.AU
2
ASX ANNOUNCEMENT 31 JANUARY 2023
Calderillas Drilling
During the December quarter, the Company commenced a scout drilling program at the
Calderillas target, where mineralisation was encountered in both holes. The holes were
drilled approximately 1.35km apart, testing the western and eastern end of the surface
mineralised zone.
Figure 2 - El Zorro Gold Project Ternera District Map and targets showing large scale gold anomalism and location
of Calderillas scout drill holes. Datum PSAD56 19S. Ternera Mineral Resource - refer to ASX announcement 23 May
2022.
The scout program was very encouraging as it recognises the potential for the El Zorro Gold
Project to comprise multiple gold deposits. The Calderillas target occurs approximately 5km
north of Ternera with the Kitsune target potentially linking the two areas, with widespread
outcropping gold occurrences having been identified.
Results from holes ZDDH0310 and ZDDH0308 (refer ASX Announcement, 1 December 2022)
include:
TESOROGOLD.COM.AU
3
ASX ANNOUNCEMENT 31 JANUARY 2023
21.00m @ 0.55g/t Au from 128.00m (ZDDH0310) including;
− 7.20m @ 1.43g/t Au from 141.00m; and
− 1.70m @ 3.92g/t Au from 147.30m.
1.00m @ 2.38g/t Au from 15.00m (ZDDH0308): and
1.90m @ 0.59g/t Au from 62.00m.
Figure 3 - Calderillas simplified geology, drill hole locations and surface gold channel samples showing large
scale gold anomalism associated with EZT outcrops within a northwest trending fault system. Datum PSAD56
19S.
Animas Viejas Channel Sampling
Results from first pass mapping and sampling at the Animas Viejas target were returned
during the quarter (refer ASX Announcement, 31 October 2022). Widespread outcropping
gold mineralisation hosted within favourable geology was identified approximately 35km
north of the 1.1Moz Ternera Gold Deposit.
The Company has now successfully identified prospective geology and outcropping gold
occurring within a north south trending corridor over 50km long and up to 15km wide.
Mapping and sampling of outcropping mineralisation has defined prospective geology
over an area spanning approximately 7km x 2km. Best results include:
• 2.00m @ 2.78g/t Au;
• 2.00m @ 2.33g/t Au;
• 2.00m @ 1.72g/t Au; and
• 2.00m @ 1.28g/t Au.
Further detailed work is planned over this area to define future drill targets.
TESOROGOLD.COM.AU
4
ASX ANNOUNCEMENT 31 JANUARY 2023
Figure 4 - El Zorro Gold Project concession map. Yellow indicates mapped intrusions (EZT) prospective for gold
mineralisation and the location of the Animas Viejas target.
Indicated
Cutoff Au g/t
Mt
2.00
1.00
0.50
0.30
Au g/t
1.8
4.4
9.3
13.3
3.93
2.41
1.51
1.18
Inferred
koz
Mt
223
341
453
503
Au g/t
2.0
5.2
12.0
17.2
3.63
2.23
1.36
1.07
Total
koz
230
373
527
593
Mt
3.7
9.6
21.4
30.5
Au g/t
koz
3.77
2.31
1.43
1.12
453
715
980
1,096
Table 1 – El Zorro Gold Project, Ternera Gold Deposit updated MRE reported at various cut-offs within a USD1,800
per ounce optimised pit shell.
CORPORATE
Strategic Investment and Capital Raise
As announced on 17 November 2022, Corporate International Holdings BV, a wholly-owned
subsidiary of Gold Fields Limited (JSE:GFI, NYSE:GFI) (Gold Fields) invested in Tesoro by way
of a A$4.20 million equity placement, and committed to sub-underwrite up to A$3.46 million
of the non-renounceable entitlement offer. Pursuant to the terms of the subscription
agreement between the Company and Gold Fields, it was agreed amongst other things
that:
TESOROGOLD.COM.AU
5
ASX ANNOUNCEMENT 31 JANUARY 2023
• 80% of the funds raised under the Placement are to be deployed towards
assessing regional targets of Tesoro’s El Zorro Gold Project (specifically excluding
Ternera);
• For so long as Gold Fields has a relevant interest in the Company above 5%, it will
have 50% representation on an advisory technical committee to be formed by
Tesoro in respect of the El Zorro Gold Project (Technical Committee);
• A program of work to deploy the Placement funds will be agreed upon by the
Technical Committee;
• Whilst Gold Fields has a relevant interest in the Company above 5%:
−
Gold Fields will maintain a right to nominate a Director to the Board;
−
Gold Fields will maintain a right to match any proposed third-party participation in
the Company’s mineral assets; and
−
Gold Fields will maintain a participation right in respect of future equity capital raisings
conducted by the Company.
Placement
An equity placement was made to Gold Fields comprising 120,000,000 new fully paid
ordinary shares at an issue price of A$0.035 per share to raise A$4.20 million. The placement
shares were issued on 24 November 2022 and rank equally with existing shares from their
date of issue.
Gold Fields will also receive one (1) free attaching option for every two (2) placement shares
issued, exercisable at A$0.07 per option on or before 13 December 2025. The issue of the
options is subject to shareholder approval at a General Meeting to be held on 22 February
2023.
Entitlement Offer
The non-renounceable pro-rata entitlement offer to eligible shareholders announced to the
ASX on 17 November 2022, closed on 6 December 2022, with one free attaching option for
every two shares issued via the offer, exercisable at A$0.07 per option on or before
13 December 2025.
The Company received valid applications from eligible shareholders for 27,957,156 new
shares (and 13,978,649 attaching options), representing approximately A$979,000 in
proceeds. This included valid applications received under the shortfall facility detailed in
the entitlement offer prospectus, dated 17 November 2022. The remaining shortfall was
allocated pursuant to the Underwriting Agreement and Sub-Underwriting Agreement (refer
ASX Announcement, 17 November 2022).
All new shares and attaching options under the offer were issued on 13 December 2022 and
commenced trading on 14 December 2022. The attaching options are trading under ticker
code ASX:TSOOA.
TESOROGOLD.COM.AU
6
ASX ANNOUNCEMENT 31 JANUARY 2023
At-The-Market Financing Facility
During the quarter, the Company advised that it had utilised and subsequently terminated
the At-the-Market Subscription Agreement (ATM) with Acuity Capital, raising A$750,000
inclusive of costs. No fees or costs were associated with the termination and no further
subscriptions under the ATM will take place.
In accordance with the terms of the ATM, the Company plans to buy back for nil cash
consideration (and cancel) the 42,000,000 fully paid ordinary TSO shares issued to Acuity
Capital as security for the ATM (subject to shareholder approval at a General Meeting to
be held on 22 February 2023).
Board Changes
Mr John Toll resigned as Non-Executive Chairperson on 26 October 2022. The Company is
currently conducting a search for a suitable replacement for Mr Toll.
Ms Shannon Coates resigned as Joint Company Secretary effective 31 January 2023. Ms
Sarah Wilson remains as sole Company Secretary.
Administrative Matters
The Company successfully held its Annual General Meeting of shareholders on
25 November 2022 at which all resolutions put to shareholders were approved.
The Registered Address and Principal Place of Business were updated on 1 November 2022
to c/- Source Services, Level 48, 152–158 St Georges Terrace, Perth WA 6000. The Company’s
website and email addresses remain unchanged.
During the quarter, the Company received approximately $592,000 from the Chilean tax
authority as partial refund of Value Added Tax (VAT) rebate claim. The balance of
approximately AUD3,000,000 remains under assessment by the tax authority.
Expenditure and Payments to Related Parties
During the quarter, the Company spent approximately A$2.01 million on exploration
activities, which comprised primarily of diamond drilling and sampling programs.
As outlined in the Appendix 5B for the quarter ending 31 December 2022 (sections 6.1 and
6.2), approximately A$455K in payments were made to related parties and/or their
associates as remuneration (inc. salary, superannuation and bonus) for the Managing
Director, Non-Executive Director fees and Consulting fees.
Cash
Tesoro’s cash balance as at 31 December 2022 was A$7.21 million and the Company had
zero debt (excluding typical trade creditors).
TESOROGOLD.COM.AU
7
ASX ANNOUNCEMENT 31 JANUARY 2023
Authorised by the Board of Tesoro Gold Ltd.
For more information:
Contact:
Zeff Reeves Managing Director
Tesoro Gold Limited
info@tesorogold.com.au
About Tesoro
Tesoro Gold Limited was established with a strategy
of acquiring, exploring, and developing mining
projects in the Coastal Cordillera region of Chile.
The Coastal Cordillera region is host to multiple
world class copper and gold mines, has well
established infrastructure, service providers and an
experienced mining workforce. Large areas of the
Coastal Cordillera remain unexplored due to the
unconsolidated nature of mining concession
ownership, but Tesoro, via its in-country network
and experience has been able secure rights to a
district scale gold project in-line with the
Company’s strategy. Tesoro’s 95% owned Chilean
subsidiary owns 85% of the El Zorro Gold Project.
Competent Persons Statements
The information in this report that relates to
Exploration Results is based on information
compiled by Mr Zeffron Reeves (B App Sc (Hons)
Applied Geology) MBA, MAIG). Mr Reeves is a
member of the Australian Institute of Geoscientists
and a Director and shareholder of the Company.
Mr Reeves has sufficient experience that is relevant
to the style of mineralisation and type of deposit
under consideration and to the activity which he is
undertaking to qualify as a Competent Person as
defined in the 2012 Edition of the Australasian Code
for Reporting of Exploration Results, Mineral
Resources and Ore Reserves. Mr Reeves consents to
the inclusion in this report of the matters based on
this information in the form and context in which it
appears.
Future Performance
This announcement may contain certain forwardlooking statements and opinion. Forward-looking
statements, including projections, forecasts and
estimates, are provided as a general guide only
and should not be relied on as an indication or
guarantee of future performance and involve
known
and
unknown
risks,
uncertainties,
assumptions, contingencies and other important
factors, many of which are outside the control of
the Company and which are subject to change
without notice and could cause the actual results,
performance or achievements of the Company to
be materially different from the future results,
performance or achievements expressed or implied
by such statements. Past performance is not
necessarily a guide to future performance and no
representation or warranty is made as to the
likelihood of achievement or reasonableness of any
forward-looking statements or other forecast.
Nothing contained in this announcement, nor any
information made available to you is, or and shall
be relied upon as, a promise, representation,
warranty or guarantee as to the past, present or the
future performance of Tesoro.
The information in this report that relates to Mineral
Resources is based on information compiled by Mr
Lynn Widenbar, a Competent Person who is a
Member of The Australasian Institute of Mining and
Metallurgy. Mr Widenbar is acting as an
independent consultant to Tesoro Gold Limited. Mr
Widenbar has sufficient experience that is relevant
to the style of mineralisation and type of deposit
under consideration, and to the activity being
undertaken to qualify as a Competent Person as
defined in the 2012 Edition of the ‘Australasian
Code for Reporting of Exploration Results, Mineral
Resources and Ore Reserves’.
The Company
confirms that the form and context in which the
Competent Person’s findings are presented have
not been materially modified from the original
announcement on 23 May 2022.
TESOROGOLD.COM.AU
8
ASX ANNOUNCEMENT 31 JANUARY 2023
Appendix 2 – Concession Schedule
El Zorro Gold Project Exploration Concessions (85%* Tesoro Mining Chile SpA)
10-august-2026
Size
(ha)
200
Concession
type
Exploration
ZORRO 2B
10-august-2026
200
Exploration
ZORRO 3B
10-august-2026
200
Exploration
ZORRO 4B
10-august-2026
100
Exploration
ZORRO 5B
10-august-2026
200
Exploration
ZORRO 6B
10-august-2026
200
Exploration
PUNTA DE DIAMENTE 1A
17-august-2025
200
Exploration
PUNTA DE DIAMENTE 2A
06-august-2025
300
Exploration
PUNTA DE DIAMENTE 3A
28-september-2025
300
Exploration
LA NEGRA COJA 1A
10-august-2025
200
Exploration
LA NEGRA COJA 2A
06-august-2025
300
Exploration
LA NEGRA COJA 3A
10-august-2025
300
Exploration
LA NEGRA COJA 4A
06-august-2025
200
Exploration
LA NEGRA COJA 5A
09-august-2025
300
Exploration
LA NEGRA COJA 6A
11-august-2025
200
Exploration
LA NEGRA COJA 7A
09-august-2025
300
Exploration
LA NEGRA COJA 8A
11-august-2025
300
Exploration
LA NEGRA COJA 9A
09-august-2025
200
Exploration
LA NEGRA COJA 10A
11-august-2025
300
Exploration
LA NEGRA COJA 11A
10-august-2025
300
Exploration
LA NEGRA COJA 12A
11-august-2025
200
Exploration
LA NEGRA COJA 13A
10-august-2025
300
Exploration
LA NEGRA COJA 14A
11-august-2025
300
Exploration
LA NEGRA COJA 15A
10-august-2025
300
Exploration
LA NEGRA COJA 16A
18-august-2025
200
Exploration
LA NEGRA COJA 17A
17-august-2025
300
Exploration
LA NEGRA COJA 18A
18-august-2025
300
Exploration
LA NEGRA COJA 19A
11-august-2025
200
Exploration
NICE BARREL 1
05-august-2025
200
Exploration
NICE BARREL 2
05-august-2025
300
Exploration
NICE BARREL 3
06-august-2025
200
Exploration
NICE BARREL 4
05-august-2025
200
Exploration
NICE BARREL 5
06-august-2025
200
Exploration
NICE BARREL 6
05-august-2025
200
Exploration
NICE BARREL 7
10-august-2025
200
Exploration
NICE BARREL 13
28-september-2025
300
Exploration
NICE BARREL 12
28-september-2025
200
Exploration
Concession Name
Date of Expiration
ZORRO 1B
TESOROGOLD.COM.AU
9
ASX ANNOUNCEMENT 31 JANUARY 2023
28-september-2025
Size
(ha)
300
Concession
type
Exploration
NICE BARREL 10
28-september-2025
200
Exploration
NICE BARREL 9
28-september-2025
300
Exploration
NICE BARREL 8
28-september-2025
200
Exploration
SIERRA PATACONES 1
Replaced by SIERRA PATACONES 1A in process
300
Exploration
SIERRA PATACONES 2
Replaced by SIERRA PATACONES 2A in process
300
Exploration
SIERRA PATACONES 3
Replaced by SIERRA PATACONES 3A in process
300
Exploration
SIERRA PATACONES 4
Replaced by SIERRA PATACONES 4A in process
300
Exploration
SIERRA PATACONES 5
Replaced by SIERRA PATACONES 5A in process
300
Exploration
SIERRA PATACONES 6
Replaced by SIERRA PATACONES 6A in process
300
Exploration
SIERRA PATACONES 7
Replaced by SIERRA PATACONES 7A in process
300
Exploration
SIERRA PATACONES 8
Replaced by SIERRA PATACONES 8A in process
300
Exploration
SIERRA PATACONES 9
Replaced by SIERRA PATACONES 9A in process
300
Exploration
SIERRA PATACONES 10
Replaced by SIERRA PATACONES 10A in process
300
Exploration
SIERRA PATACONES 11
Replaced by SIERRA PATACONES 11A in process
300
Exploration
SIERRA PATACONES 12
Replaced by SIERRA PATACONES 12A in process
300
Exploration
SIERRA PATACONES 13
Replaced by SIERRA PATACONES 13A in process
300
Exploration
SIERRA PATACONES 14
Replaced by SIERRA PATACONES 14A in process
300
Exploration
SIERRA PATACONES 15
Replaced by SIERRA PATACONES 15A in process
300
Exploration
SIERRA PATACONES 20
Replaced by SIERRA PATACONES 20A in process
300
Exploration
SIERRA PATACONES 19
Replaced by SIERRA PATACONES 19A in process
300
Exploration
SIERRA PATACONES 18
Replaced by SIERRA PATACONES 18A in process
300
Exploration
SIERRA PATACONES 17
Replaced by SIERRA PATACONES 17A in process
300
Exploration
SIERRA PATACONES 16
Replaced by SIERRA PATACONES 16A in process
300
Exploration
SIERRA PATACONES 21
Replaced by SIERRA PATACONES 21A in process
300
Exploration
SIERRA PATACONES 22
Replaced by SIERRA PATACONES 22A in process
300
Exploration
SIERRA PATACONES 23
Replaced by SIERRA PATACONES 23A in process
300
Exploration
SIERRA PATACONES 24
Replaced by SIERRA PATACONES 24A in process
300
Exploration
SIERRA PATACONES 25
Replaced by SIERRA PATACONES 25A in process
300
Exploration
SIERRA PATACONES 26
Replaced by SIERRA PATACONES 26A in process
300
Exploration
SIERRA PATACONES 27
Replaced by SIERRA PATACONES 27A in process
300
Exploration
SIERRA PATACONES 28
Replaced by SIERRA PATACONES 28A in process
300
Exploration
SIERRA PATACONES 29
Replaced by SIERRA PATACONES 29A in process
300
Exploration
SIERRA PATACONES 30
Replaced by SIERRA PATACONES 30A in process
300
Exploration
SIERRA PATACONES 31
Replaced by SIERRA PATACONES 31A in process
300
Exploration
SIERRA PATACONES 32
Replaced by SIERRA PATACONES 32A in process
300
Exploration
SIERRA PATACONES 33
Replaced by SIERRA PATACONES 33A in process
300
Exploration
SIERRA PATACONES 34
Replaced by SIERRA PATACONES 34A in process
300
Exploration
SIERRA PATACONES 35
Replaced by SIERRA PATACONES 35A in process
300
Exploration
SIERRA PATACONES 42
Replaced by SIERRA PATACONES 42A in process
300
Exploration
SIERRA PATACONES 41
Replaced by SIERRA PATACONES 41A in process
300
Exploration
Concession Name
Date of Expiration
NICE BARREL 11
TESOROGOLD.COM.AU
10
ASX ANNOUNCEMENT 31 JANUARY 2023
Concession Name
Date of Expiration
Size
(ha)
Concession
type
SIERRA PATACONES 40
Replaced by SIERRA PATACONES 40A in process
300
Exploration
SIERRA PATACONES 39
Replaced by SIERRA PATACONES 39A in process
300
Exploration
SIERRA PATACONES 38
Replaced by SIERRA PATACONES 38A in process
300
Exploration
SIERRA PATACONES 37
Replaced by SIERRA PATACONES 37A in process
300
Exploration
SIERRA PATACONES 36
Replaced by SIERRA PATACONES 36A in process
300
Exploration
SIERRA PATACONES 43
Replaced by SIERRA PATACONES 43A in process
300
Exploration
SIERRA PATACONES 44
Replaced by SIERRA PATACONES 44A in process
300
Exploration
SIERRA PATACONES 45
Replaced by SIERRA PATACONES 45A in process
300
Exploration
SIERRA PATACONES 46
Replaced by SIERRA PATACONES 46A in process
300
Exploration
SIERRA PATACONES 47
Replaced by SIERRA PATACONES 47A in process
300
Exploration
SIERRA PATACONES 48
Replaced by SIERRA PATACONES 48A in process
300
Exploration
SIERRA PATACONES 49
Replaced by SIERRA PATACONES 49A in process
300
Exploration
SIERRA PATACONES 50
Replaced by SIERRA PATACONES 50A in process
300
Exploration
SIERRA PATACONES 51
Replaced by SIERRA PATACONES 51A in process
300
Exploration
SIERRA PATACONES 53
Replaced by SIERRA PATACONES 53A in process
300
Exploration
SIERRA PATACONES 54
Replaced by SIERRA PATACONES 54A in process
300
Exploration
SIERRA PATACONES 55
Replaced by SIERRA PATACONES 55A in process
300
Exploration
SIERRA PATACONES 56
Replaced by SIERRA PATACONES 56A in process
300
Exploration
SIERRA PATACONES 57
Replaced by SIERRA PATACONES 57A in process
300
Exploration
SIERRA PATACONES 62
Replaced by SIERRA PATACONES 62A in process
300
Exploration
SIERRA PATACONES 61
Replaced by SIERRA PATACONES 61A in process
300
Exploration
SIERRA PATACONES 60
Replaced by SIERRA PATACONES 60A in process
300
Exploration
SIERRA PATACONES 59
Replaced by SIERRA PATACONES 59A in process
300
Exploration
SIERRA PATACONES 58
Replaced by SIERRA PATACONES 58A in process
300
Exploration
SIERRA PATACONES 63
Replaced by SIERRA PATACONES 63A in process
300
Exploration
SIERRA PATACONES 64
Replaced by SIERRA PATACONES 64A in process
300
Exploration
SIERRA PATACONES 65
Replaced by SIERRA PATACONES 65A in process
300
Exploration
SIERRA PATACONES 66
Replaced by SIERRA PATACONES 66A in process
300
Exploration
SIERRA PATACONES 67
Replaced by SIERRA PATACONES 67A in process
300
Exploration
SIERRA PATACONES 68
Replaced by SIERRA PATACONES 68A in process
300
Exploration
SIERRA PATACONES 69
Replaced by SIERRA PATACONES 69A in process
300
Exploration
SIERRA PATACONES 70
Replaced by SIERRA PATACONES 70A in process
300
Exploration
SIERRA PATACONES 71
Replaced by SIERRA PATACONES 71A in process
300
Exploration
SIERRA PATACONES 72
Replaced by SIERRA PATACONES 72A in process
300
Exploration
SIERRA PATACONES 73
Replaced by SIERRA PATACONES 73A in process
300
Exploration
SIERRA PATACONES 74
Replaced by SIERRA PATACONES 74A in process
300
Exploration
SIERRA PATACONES 75
Replaced by SIERRA PATACONES 75A in process
300
Exploration
SIERRA PATACONES 76
Replaced by SIERRA PATACONES 76A in process
300
Exploration
SIERRA PATACONES 77
Replaced by SIERRA PATACONES 77A in process
300
Exploration
SIERRA PATACONES 84
Replaced by SIERRA PATACONES 84A in process
300
Exploration
TESOROGOLD.COM.AU
11
ASX ANNOUNCEMENT 31 JANUARY 2023
Concession Name
Date of Expiration
Size
(ha)
Concession
type
SIERRA PATACONES 83
Replaced by SIERRA PATACONES 83A in process
300
Exploration
SIERRA PATACONES 82
Replaced by SIERRA PATACONES 82A in process
300
Exploration
SIERRA PATACONES 81
Replaced by SIERRA PATACONES 81A in process
300
Exploration
SIERRA PATACONES 80
Replaced by SIERRA PATACONES 80A in process
300
Exploration
SIERRA PATACONES 79
Replaced by SIERRA PATACONES 79A in process
300
Exploration
SIERRA PATACONES 78
Replaced by SIERRA PATACONES 78A in process
300
Exploration
SIERRA PATACONES 52
Replaced by SIERRA PATACONES 52A in process
300
Exploration
GOLD STORE 72
Replaced by GOLD STORE 72A in process
300
Exploration
GOLD STORE 71
Replaced by GOLD STORE 71A in process
300
Exploration
GOLD STORE 70
Replaced by GOLD STORE 70A in process
300
Exploration
GOLD STORE 69
Replaced by GOLD STORE 69A in process
300
Exploration
GOLD STORE 68
Replaced by GOLD STORE 68A in process
300
Exploration
GOLD STORE 67
Replaced by GOLD STORE 67A in process
300
Exploration
GOLD STORE 66
Replaced by GOLD STORE 66A in process
300
Exploration
GOLD STORE 1
Replaced by GOLD STORE 1A in process
300
Exploration
GOLD STORE 2
Replaced by GOLD STORE 2A in process
300
Exploration
GOLD STORE 3
Replaced by GOLD STORE 3A in process
300
Exploration
GOLD STORE 4
Replaced by GOLD STORE 4A in process
300
Exploration
GOLD STORE 5
Replaced by GOLD STORE 5A in process
300
Exploration
GOLD STORE 6
Replaced by GOLD STORE 6A in process
300
Exploration
GOLD STORE 7
Replaced by GOLD STORE 7A in process
300
Exploration
GOLD STORE 8
Replaced by GOLD STORE 8A in process
300
Exploration
GOLD STORE 9
Replaced by GOLD STORE 9A in process
300
Exploration
GOLD STORE 10
Replaced by GOLD STORE 10A in process
300
Exploration
GOLD STORE 11
Replaced by GOLD STORE 11A in process
300
Exploration
GOLD STORE 12
Replaced by GOLD STORE 12A in process
300
Exploration
GOLD STORE 13
Replaced by GOLD STORE 13A in process
300
Exploration
GOLD STORE 14
Replaced by GOLD STORE 14A in process
300
Exploration
GOLD STORE 15
Replaced by GOLD STORE 15A in process
300
Exploration
GOLD STORE 16
Replaced by GOLD STORE 16A in process
300
Exploration
GOLD STORE 17
Replaced by GOLD STORE 17A in process
300
Exploration
GOLD STORE 18
Replaced by GOLD STORE 18A in process
300
Exploration
GOLD STORE 19
Replaced by GOLD STORE 19A in process
300
Exploration
GOLD STORE 20
Replaced by GOLD STORE 20A in process
300
Exploration
GOLD STORE 21
Replaced by GOLD STORE 21A in process
300
Exploration
GOLD STORE 22
Replaced by GOLD STORE 22A in process
300
Exploration
GOLD STORE 23
Replaced by GOLD STORE 23A in process
300
Exploration
GOLD STORE 24
Replaced by GOLD STORE 24A in process
300
Exploration
GOLD STORE 25
Replaced by GOLD STORE 25A in process
300
Exploration
GOLD STORE 26
Replaced by GOLD STORE 26A in process
300
Exploration
GOLD STORE 27
Replaced by GOLD STORE 27A in process
300
Exploration
GOLD STORE 28
Replaced by GOLD STORE 28A in process
300
Exploration
GOLD STORE 29
Replaced by GOLD STORE 29A in process
300
Exploration
GOLD STORE 30
Replaced by GOLD STORE 30A in process
300
Exploration
GOLD STORE 36
Replaced by GOLD STORE 36A in process
300
Exploration
TESOROGOLD.COM.AU
12
ASX ANNOUNCEMENT 31 JANUARY 2023
Replaced by GOLD STORE 35A in process
Size
(ha)
300
Concession
type
Exploration
GOLD STORE 34
Replaced by GOLD STORE 34A in process
300
Exploration
GOLD STORE 33
Replaced by GOLD STORE 33A in process
300
Exploration
GOLD STORE 37
Replaced by GOLD STORE 37A in process
300
Exploration
GOLD STORE 38
Replaced by GOLD STORE 38A in process
300
Exploration
GOLD STORE 39
Replaced by GOLD STORE 39A in process
300
Exploration
GOLD STORE 40
Replaced by GOLD STORE 40A in process
300
Exploration
GOLD STORE 41
Replaced by GOLD STORE 41A in process
300
Exploration
GOLD STORE 42
Replaced by GOLD STORE 42A in process
300
Exploration
GOLD STORE 43
Replaced by GOLD STORE 43A in process
300
Exploration
GOLD STORE 44
Replaced by GOLD STORE 44A in process
300
Exploration
GOLD STORE 45
Replaced by GOLD STORE 45A in process
300
Exploration
GOLD STORE 46
Replaced by GOLD STORE 46A in process
300
Exploration
GOLD STORE 47
Replaced by GOLD STORE 47A in process
300
Exploration
GOLD STORE 48
Replaced by GOLD STORE 48A in process
300
Exploration
GOLD STORE 49
Replaced by GOLD STORE 49A in process
300
Exploration
GOLD STORE 50
Replaced by GOLD STORE 50A in process
300
Exploration
GOLD STORE 51
Replaced by GOLD STORE 51A in process
300
Exploration
GOLD STORE 52
Replaced by GOLD STORE 52A in process
300
Exploration
GOLD STORE 53
Replaced by GOLD STORE 53A in process
300
Exploration
GOLD STORE 54
Replaced by GOLD STORE 54A in process
300
Exploration
GOLD STORE 55
Replaced by GOLD STORE 55A in process
300
Exploration
GOLD STORE 56
Replaced by GOLD STORE 56A in process
200
Exploration
GOLD STORE 57
Replaced by GOLD STORE 57A in process
300
Exploration
GOLD STORE 58
Replaced by GOLD STORE 58A in process
300
Exploration
GOLD STORE 59
Replaced by GOLD STORE 59A in process
300
Exploration
GOLD STORE 60
Replaced by GOLD STORE 60A in process
3
Share your feedback